4506 E ESMERALDA ST Unit 2-3 90032

Certificate Information: 4506 E ESMERALDA ST Unit 2-3 90032

Application / Permit
18010-70000-02255
Plan Check / Job No.
B18SL00726
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX W/ ATTACHED GARAGE (CENTER LOT) 2 OF 3
Permit Issued
Issued on 4/16/2019
Issuing Office
South Los Angeles
Current Status
CofO Corrected on 6/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2018 APPLICANT
Green Plans Picked Up 6/12/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 ZAW HAN
Corrections Issued 7/12/2018 ZAW HAN
Quality Review Completed 7/16/2018 HERNAN ARREOLA
Building Plans Picked Up 7/23/2018 APPLICANT
Applicant returned to address corrections 9/10/2018 ZAW HAN
Applicant returned to address corrections 1/4/2019 ZAW HAN
Plan Check Approved 2/4/2019 ZAW HAN
Issued 4/16/2019 LADBS
CofO in Progress 6/14/2021 ELMER BLAND
Re-Activate Permit 6/18/2021 DEROLD HAUFF
CofO Issued-Status Void 6/18/2021 DEROLD HAUFF
Permit Finaled-Status Void 6/18/2021 DEROLD HAUFF
Permit Finaled 6/18/2021 DEROLD HAUFF
CofO Corrected 6/18/2021 DEROLD HAUFF
Permit Finaled 6/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/16/2018 ADRIAN SANCHEZ
Address approval Cleared 10/16/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 10/16/2018 ADRIAN SANCHEZ
Highway dedication Cleared 10/16/2018 ADRIAN SANCHEZ
Permit Cleared 10/16/2018 ADRIAN SANCHEZ
Sewer availability Cleared 10/16/2018 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 10/19/2018 HELENE ROTOLO
Hydrant and Access approval Cleared 10/19/2018 GEORGE SUCHAND
Prkng lot landscape/Water mgmt Cleared 10/19/2018 HELENE ROTOLO
Green Code Cleared 10/29/2018 DONALD CRICHLOW
Low Impact Development Cleared 11/29/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/29/2018 ADRIAN SANCHEZ
GPI Written Notices Cleared 1/4/2019 TODD MALAND
Grading Pre-Inspection Cleared 1/4/2019 TODD MALAND

Contact Information

Architect Tavasci,, Robert J; Lic. No.: C26023 3351 ORANGEWOOD AVENUE      ROSSMOOR, CA 90720
Contractor Dapena Construction Inc; Lic. No.: 1046676-B 32812 SAIL WAY      DANA POINT, CA 92629
Engineer Christenson, Paul Scott; Lic. No.: C57182 3529 COASTVIEW CT      CARLSBAD, CA 92010
Engineer Montemayor,, G F; Lic. No.: C25258 1617 S WAVERLY GLEN WAY      HACIENDA HEIGHTS, CA 91745
Engineer Shubeck,, Robert James; Lic. No.: GE773 60 HACKAMORE LANE      BELL CANYON, CA 91307

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/9/2019 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/19/2019 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 10/8/2019 Approved ENRIQUE MIRELES
Deputy Steel/Welding 11/19/2019 Approved ENRIQUE MIRELES
Deputy Steel/Welding 11/21/2019 Approved ENRIQUE MIRELES
Deputy Steel/Welding 11/22/2019 Approved ENRIQUE MIRELES
Smoke Detectors 11/25/2019 Approved ENRIQUE MIRELES
Deputy Steel/Welding 11/26/2019 Approved ENRIQUE MIRELES
Deputy Steel/Welding 12/9/2019 Approved ENRIQUE MIRELES
Deputy Wood Construction 12/11/2019 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/24/2020 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 3/20/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 3/20/2020 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 3/20/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 5/5/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/6/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/11/2020 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 5/14/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/20/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/28/2020 Conditional Approval SCOTT FINNILA
Green Building Rough 7/28/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 7/28/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 8/6/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/10/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/10/2020 Approved ENRIQUE MIRELES
Drywall Nailing 8/27/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 9/1/2020 Approved ENRIQUE MIRELES
Insulation 9/1/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/6/2020 Approved COREY HUPP
Sewer 10/6/2020 Approved COREY HUPP
Gas Test 10/15/2020 Partial Approval COREY HUPP
HVAC-Final 12/17/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Final 12/18/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 3/18/2021 Corrections Issued COREY HUPP
HVAC-Final 3/18/2021 Corrections Issued COREY HUPP
PLUMBING-Final 3/18/2021 Corrections Issued COREY HUPP
ELECTRICAL-Final 4/8/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 4/8/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 4/8/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 4/19/2021 Approved OSVALDO PARAMO
PLUMBING-Final 4/19/2021 Approved OSVALDO PARAMO
Final 5/3/2021 Conditional Approval CRAIG VAUGHAN
Green Building Final 5/3/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/3/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 5/3/2021 Approved CRAIG VAUGHAN
Final 6/14/2021 OK to Issue CofO ELMER BLAND