844-844 1/2 W 65TH ST 90044

Certificate Information: 844-844 1/2 W 65TH ST 90044

Application / Permit
18010-70000-01862
Plan Check / Job No.
B18SL00628
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX AT REAR 2 OF 2
Permit Issued
Issued on 2/26/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 MOHAMMAD FIROUZBAKHT
Corrections Issued 5/29/2018 MOHAMMAD FIROUZBAKHT
Quality Review Completed 6/5/2018 DAVID CHANG
Building Plans Picked Up 6/13/2018 APPLICANT
Green Plans Picked Up 6/13/2018 APPLICANT
Plan Check Approved 2/24/2020 MIGUEL JIMENEZ
Issued 2/26/2020 LADBS
CofO in Progress 8/25/2020 ALEJANDRO DE ARTOLA
Permit Finaled 10/15/2020 DEROLD HAUFF
CofO Issued 10/15/2020 DEROLD HAUFF
Permit Finaled 10/15/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2018 STEVE MELGAR
Hydrant and Access approval Cleared 6/21/2018 GEORGE SUCHAND
Sewer availability Cleared 6/21/2018 STEVE MELGAR
Green Code Cleared 7/17/2018 NEGAR NEJAD
Low Impact Development Cleared 8/2/2018 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 8/2/2018 NAZILA NOORIFAR

Contact Information

Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 3/23/2020 Approved EUGENE CASSIDY
Deputy Wood Construction 4/1/2020 Conditional Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 4/16/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 4/16/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/17/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 4/17/2020 Approved EUGENE CASSIDY
HVAC-Rough 4/17/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/17/2020 Not Ready for Inspection EUGENE CASSIDY
Insulation 4/23/2020 Approved EUGENE CASSIDY
Drywall Nailing 4/29/2020 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/29/2020 Approved ALEJANDRO DE ARTOLA
Gas Test 5/27/2020 Not Ready for Inspection EUGENE CASSIDY
Sewer 5/27/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/16/2020 Approved JOSEPH MCGARRY
Final 7/16/2020 Corrections Issued JOSEPH MCGARRY
Gas Test 7/16/2020 Approved JOSEPH MCGARRY
Green Building Final 7/16/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/16/2020 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 7/16/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 7/16/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/16/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/22/2020 Approved JOSEPH MCGARRY
Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/22/2020 Approved JOSEPH MCGARRY
HVAC-Final 7/22/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 7/22/2020 Approved JOSEPH MCGARRY
Service/Power Release 7/22/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 8/12/2020 Not Ready for Inspection COREY HUPP
Service/Power Release 8/12/2020 Not Ready for Inspection COREY HUPP
Final 8/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 8/18/2020 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/25/2020 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 8/25/2020 Approved ALEJANDRO DE ARTOLA