4846 E BUCHANAN ST 90042

Certificate Information: 4846 E BUCHANAN ST 90042

Application / Permit
18010-70000-01180
Plan Check / Job No.
B18SL00405
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY, 28' X X32', TYPE VB, R3-OCC SINGLE FAMILY DWELLING ON TOP OF 2-CAR GARAGE
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2018 APPLICANT
Green Plans Picked Up 4/19/2018 APPLICANT
Assigned to Plan Check Engineer 4/23/2018 DEVIN GORDON
Corrections Issued 5/3/2018 DEVIN GORDON
Quality Review Completed 5/4/2018 KESETE HAREGOT
Building Plans Picked Up 5/8/2018 APPLICANT
Plan Check Approved 1/16/2020 VU NGUYEN
Issued 1/16/2020 LADBS
CofO in Progress 8/31/2022 CRAIG VAUGHAN
CofO in Progress 8/31/2022 CRAIG VAUGHAN
Permit Finaled 9/8/2022 DEROLD HAUFF
CofO Issued 9/8/2022 DEROLD HAUFF
Permit Finaled 9/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 10/4/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 10/4/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 10/4/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/4/2019 EMIL KYUPELYAN
Permit Cleared 10/4/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 12/5/2019 JEREMY CARTER
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 12/6/2019 NEGAR NEJAD
Roof/Waste drainage to street Cleared 12/6/2019 THAN WIN
Sewer availability Cleared 12/6/2019 THAN WIN
GPI Written Notices Cleared 1/16/2020 DEVIN GORDON
Grading Pre-Inspection Cleared 1/16/2020 DEVIN GORDON

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Madrigal, Juan Jose; Lic. No.: S5379 7486 SUNGOLD AVE      CORONA, CA 92880

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/8/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/15/2020 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 7/16/2020 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/29/2020 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 7/30/2020 No Access for Inspection CRAIG VAUGHAN
Masonry Wall/Backfill 8/4/2020 Partial Approval DAVID MATSON
Footing/Foundation/Slab 2/19/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/12/2021 Partial Approval CRAIG VAUGHAN
Underground Mechanical 3/12/2021 Partial Approval CRAIG VAUGHAN
Insulation 3/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval CRAIG VAUGHAN
Insulation 3/18/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/26/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/25/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 5/25/2021 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 5/25/2021 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/25/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/2/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 6/2/2021 Approved CRAIG VAUGHAN
Green Building Rough 6/2/2021 Approved CRAIG VAUGHAN
HVAC-Rough 6/2/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/2/2021 Corrections Issued CRAIG VAUGHAN
Wood Frame 6/2/2021 Approved CRAIG VAUGHAN
Insulation 6/9/2021 Approved CRAIG VAUGHAN
Drywall Nailing 6/14/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/14/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/21/2021 Approved BENEVA JACKSON
Shower Pan 6/21/2021 Approved BENEVA JACKSON
Sewer 8/26/2021 Approved CRAIG VAUGHAN
Final 8/15/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/15/2022 Approved CRAIG VAUGHAN
Gas Test 8/15/2022 Approved CRAIG VAUGHAN
Green Building Final 8/15/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 8/15/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 8/15/2022 Approved CRAIG VAUGHAN
Final 8/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 8/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 8/30/2022 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 8/30/2022 Approved CRAIG VAUGHAN