1118 N FLINT AVE 90744
Certificate Information: 1118 N FLINT AVE 90744
- Application / Permit
- 18010-40000-04967
- Plan Check / Job No.
- B18SP01089
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family dwelling with attached garage at rear of lot (House 2)
- Permit Issued
- Issued on 3/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2018 | JASON JANGADA |
| Corrections Issued | 12/4/2018 | JASON JANGADA |
| Quality Review Completed | 12/13/2018 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 2/7/2020 | JASON JANGADA |
| Applicant returned to address corrections | 2/10/2020 | JASON JANGADA |
| Applicant returned to address corrections | 2/25/2020 | JASON JANGADA |
| Applicant returned to address corrections | 2/26/2020 | JASON JANGADA |
| Applicant returned to address corrections | 3/10/2020 | JASON JANGADA |
| Green Plans Picked Up | 10/14/2020 | APPLICANT |
| Applicant returned to address corrections | 11/17/2020 | JASON JANGADA |
| Building Plans Picked Up | 12/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/19/2021 | JASON JANGADA |
| Applicant returned to address corrections | 6/16/2022 | JASON JANGADA |
| Applicant returned to address corrections | 2/16/2023 | JASON JANGADA |
| Applicant returned to address corrections | 2/23/2023 | JASON JANGADA |
| Plan Check Approved | 2/28/2023 | JASON JANGADA |
| Issued | 3/1/2023 | APPLICANT |
| CofO in Progress | 6/26/2024 | EUGENE CASSIDY |
| Permit Finaled | 7/3/2024 | ANSON MAGLASANG |
| CofO Issued | 7/3/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/3/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2019 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 2/19/2019 | ROBERT DUFF |
| Permit | Cleared | 2/19/2019 | JAMES MORALEZ |
| Sewer availability | Cleared | 2/19/2019 | JAMES MORALEZ |
| Low Impact Development | Cleared | 3/4/2019 | MITESH PATEL |
| ZA Case | Cleared | 3/4/2021 | DANIEL CORONADO |
| "Q" conditions | Cleared | 5/13/2021 | DANIEL CORONADO |
| Clean Up Green Up | Cleared | 11/18/2022 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | ANA SORIANO |
| Trees in Parkway | Cleared | 2/1/2023 | ADALBERTO VERA |
| Green Code | Cleared | 2/28/2023 | RICHARD GARCIA |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 7/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/12/2023 | Approved | EUGENE CASSIDY |
| Insulation | 7/25/2023 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 7/25/2023 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 7/25/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/1/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/1/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 12/1/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 12/1/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/1/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | EUGENE CASSIDY |
| Insulation | 12/11/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/15/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/8/2024 | Approved | EUGENE CASSIDY |
| Gas Test | 1/23/2024 | Approved | EUGENE CASSIDY |
| Sewer | 1/23/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 1/23/2024 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 1/23/2024 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 1/29/2024 | Approved | EUGENE CASSIDY |
| Gas Test | 4/1/2024 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 4/1/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/11/2024 | Conditional Approval | EUGENE CASSIDY |
| HVAC-Final | 6/11/2024 | Approved | EUGENE CASSIDY |
| Service/Power Release | 6/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/20/2024 | Approved | EUGENE CASSIDY |
| Final | 6/20/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/20/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/20/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/20/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/20/2024 | Approved | EUGENE CASSIDY |
| Final | 6/25/2024 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 6/25/2024 | Approved | EUGENE CASSIDY |