2843 S KERCKHOFF AVE 90731
Certificate Information: 2843 S KERCKHOFF AVE 90731
- Application / Permit
- 18010-40000-04617
- Plan Check / Job No.
- B18SP00992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE EQUIPPED THROUGHOUT WITH FIRE SPRINKLERS IN COMPLIANCE WITH NFPA 13D.
- Permit Issued
- Issued on 1/8/2021
- Issuing Office
- Current Status
- Issued on 1/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | SERGIO SILVA |
| Corrections Issued | 11/5/2018 | SERGIO SILVA |
| Quality Review Completed | 11/16/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/4/2018 | SERGIO SILVA |
| Applicant returned to address corrections | 1/17/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 5/2/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 7/9/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 8/19/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 2/11/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 2/28/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 3/19/2020 | SERGIO SILVA |
| Green Plans Picked Up | 3/24/2020 | APPLICANT |
| Plan Check Approved | 11/16/2020 | SERGIO SILVA |
| Building Plans Picked Up | 12/8/2020 | APPLICANT |
| Issued | 1/8/2021 | APPLICANT |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 12/11/2018 | SOPHIE GABEL-SCHEINBAU |
| Address approval | Cleared | 2/24/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/26/2020 | JEREMY CARTER |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | CHINH DINH |
| Permit | Cleared | 2/27/2020 | CHINH DINH |
| Sewer availability | Cleared | 3/3/2020 | CHINH DINH |
| Trees in Parkway | Cleared | 3/9/2020 | JOHN KIM |
| Low Impact Development | Cleared | 3/11/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/11/2020 | RENZ SORIANO |
| GPI Written Notices | Cleared | 3/19/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 3/19/2020 | SERGIO SILVA |
| Green Code | Cleared | 3/19/2020 | RICHARD GARCIA |
| Coastal Zone | Cleared | 10/23/2020 | DENZEL HENDERSON |
| Hold | Cleared | 1/14/2021 | JASON SHEETS |
Contact Information
| Architect | Studio, M+A; Lic. No.: C32566 | 5608 E PEABODY ST LONG BEACH, CA 90808 |
| Engineer | Gss, Engineering, Inc; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Mid-Cities, Engineering; Lic. No.: C41697 | 9744 MAPLE ST STE 101 BELLFLOWER, CA 90706 |
| Engineer | Pacific, Engineering; Lic. No.: C36235 | 17703 CRENSHAW BLVD TORRANCE, CA 90504 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Corrections Issued | JAMES CHAVEZ |
| Special/Order Compliance | 12/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Special/Order Compliance | 12/29/2023 | Conditional Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 2/2/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Partial Approval | EUGENE CASSIDY |
| Masonry Wall/Backfill | 2/27/2024 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Partial Approval | JAMES CHAVEZ |
| Masonry Wall/Backfill | 3/29/2024 | Partial Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/7/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 12/22/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/29/2025 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/29/2025 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 1/8/2026 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/13/2026 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 1/16/2026 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/16/2026 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/15/2026 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/15/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 4/15/2026 | Corrections Issued | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 4/15/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 4/15/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/12/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/12/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 5/12/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/12/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 5/14/2026 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/14/2026 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 5/15/2026 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/27/2026 | Approved | ARTHUR NEGRETE |