25427 S PRESIDENT AVE 90710
Certificate Information: 25427 S PRESIDENT AVE 90710
- Application / Permit
- 18010-40000-04508
- Plan Check / Job No.
- B18SP00968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) Two-Story Accessory Dwelling Unit per per SB229 and AB494 with attached 2-car garage amd 1-car carport.
- Permit Issued
- Issued on 2/4/2019
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | TARIK SAOUD |
| Green Plans Picked Up | 10/26/2018 | APPLICANT |
| Corrections Issued | 11/7/2018 | TARIK SAOUD |
| Quality Review Completed | 11/14/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/24/2019 | TARIK SAOUD |
| Plan Check Approved | 1/28/2019 | TARIK SAOUD |
| Issued | 2/4/2019 | LADBS |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| CofO in Progress | 9/19/2025 | EUGENE CASSIDY |
| Permit Finaled | 9/25/2025 | ANSON MAGLASANG |
| CofO Issued | 9/25/2025 | ANSON MAGLASANG |
| Permit Finaled | 9/25/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Green Code | Cleared | 11/8/2018 | DONALD CRICHLOW |
| Address approval | Cleared | 12/7/2018 | PHILLIP WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2018 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 12/7/2018 | PHILLIP WILSON |
| Sewer availability | Cleared | 12/7/2018 | PHILLIP WILSON |
| Hydrant and Access approval | Cleared | 1/15/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 1/23/2019 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Blangy,, Michel Patrick; Lic. No.: C68963 | 1507 21ST STREET MANHATTAN BEACH, CA 90266 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2019 | Partial Approval | ANSON MAGLASANG |
| METHANE-Barrier | 5/9/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| METHANE-Subgrade | 5/9/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| Deputy Reinf. Concrete | 5/10/2019 | Conditional Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/14/2019 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 6/14/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| METHANE-Rough | 6/14/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 6/14/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| METHANE-Subgrade | 7/29/2019 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/16/2019 | Approved | ANSON MAGLASANG |
| METHANE-Barrier | 8/16/2019 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 8/16/2019 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 9/17/2019 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 9/17/2019 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 9/17/2019 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 9/17/2019 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/17/2019 | Approved | JOHN KLARIN |
| Wood Frame | 9/17/2019 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Final | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2019 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/22/2019 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 11/6/2019 | Corrections Issued | ANSON MAGLASANG |
| HVAC-Rough | 11/6/2019 | Corrections Issued | ANSON MAGLASANG |
| Pre-Inspection | 1/9/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 1/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 3/17/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 6/13/2023 | Approved | EUGENE CASSIDY |
| METHANE-Final | 6/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 6/13/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/13/2023 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 6/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/10/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 7/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/10/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/10/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | EUGENE CASSIDY |
| Final | 8/3/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/3/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 8/3/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 8/3/2023 | Approved | EUGENE CASSIDY |
| Final | 8/9/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/9/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/15/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/15/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/3/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 4/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 3/26/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 5/30/2025 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 5/30/2025 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 5/30/2025 | Not Ready for Inspection | JOHN KLARIN |
| Final | 9/12/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/12/2025 | Approved | EUGENE CASSIDY |
| Service/Power Release | 9/12/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/19/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 9/19/2025 | Not Required | EUGENE CASSIDY |