25427 S PRESIDENT AVE 90710

Certificate Information: 25427 S PRESIDENT AVE 90710

Application / Permit
18010-40000-04508
Plan Check / Job No.
B18SP00968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) Two-Story Accessory Dwelling Unit per per SB229 and AB494 with attached 2-car garage amd 1-car carport.
Permit Issued
Issued on 2/4/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 TARIK SAOUD
Green Plans Picked Up 10/26/2018 APPLICANT
Corrections Issued 11/7/2018 TARIK SAOUD
Quality Review Completed 11/14/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/24/2019 TARIK SAOUD
Plan Check Approved 1/28/2019 TARIK SAOUD
Issued 2/4/2019 LADBS
Building Plans Picked Up 4/24/2020 APPLICANT
CofO in Progress 9/19/2025 EUGENE CASSIDY
Permit Finaled 9/25/2025 ANSON MAGLASANG
CofO Issued 9/25/2025 ANSON MAGLASANG
Permit Finaled 9/25/2025 ANSON MAGLASANG

Permit Application Clearance Information

Green Code Cleared 11/8/2018 DONALD CRICHLOW
Address approval Cleared 12/7/2018 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 12/7/2018 PHILLIP WILSON
Roof/Waste drainage to street Cleared 12/7/2018 PHILLIP WILSON
Sewer availability Cleared 12/7/2018 PHILLIP WILSON
Hydrant and Access approval Cleared 1/15/2019 GEORGE SUCHAND
Low Impact Development Cleared 1/23/2019 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Blangy,, Michel Patrick; Lic. No.: C68963 1507 21ST STREET      MANHATTAN BEACH, CA 90266

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2019 Partial Approval ANSON MAGLASANG
METHANE-Barrier 5/9/2019 Not Ready for Inspection ANSON MAGLASANG
METHANE-Subgrade 5/9/2019 Not Ready for Inspection ANSON MAGLASANG
Deputy Reinf. Concrete 5/10/2019 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 6/14/2019 Partial Approval ANSON MAGLASANG
Green Building Rough 6/14/2019 Not Ready for Inspection ANSON MAGLASANG
METHANE-Rough 6/14/2019 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 6/14/2019 Not Ready for Inspection ANSON MAGLASANG
METHANE-Subgrade 7/29/2019 Approved ANSON MAGLASANG
Footing/Foundation/Slab 8/16/2019 Approved ANSON MAGLASANG
METHANE-Barrier 8/16/2019 Approved ANSON MAGLASANG
PLUMBING-Rough 8/16/2019 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 9/17/2019 Not Ready for Inspection JOHN KLARIN
Green Building Rough 9/17/2019 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 9/17/2019 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 9/17/2019 Approved JOHN KLARIN
Verify Sprinkler Sign Off 9/17/2019 Approved JOHN KLARIN
Wood Frame 9/17/2019 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 10/22/2019 Not Ready for Inspection JOHN KLARIN
Final 10/22/2019 Not Ready for Inspection JOHN KLARIN
Green Building Final 10/22/2019 Not Ready for Inspection JOHN KLARIN
Green Building Rough 10/22/2019 Not Ready for Inspection JOHN KLARIN
METHANE-Final 10/22/2019 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 10/22/2019 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/22/2019 SGSOV Not Ready JOHN KLARIN
Service/Power Release 10/22/2019 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/22/2019 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 11/6/2019 Corrections Issued ANSON MAGLASANG
HVAC-Rough 11/6/2019 Corrections Issued ANSON MAGLASANG
Pre-Inspection 1/9/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 1/23/2020 Not Ready for Inspection JOHN KLARIN
Underground Mechanical 3/17/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/13/2023 Not Ready for Inspection EUGENE CASSIDY
Final 6/13/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 6/13/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 6/13/2023 Approved EUGENE CASSIDY
METHANE-Final 6/13/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 6/13/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/13/2023 Not Required EUGENE CASSIDY
Smoke Detectors 6/13/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/10/2023 Not Ready for Inspection EUGENE CASSIDY
Final 7/10/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 7/10/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 7/10/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 7/10/2023 Approved EUGENE CASSIDY
Smoke Detectors 7/10/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/3/2023 Approved EUGENE CASSIDY
Final 8/3/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 8/3/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Final 8/3/2023 Approved EUGENE CASSIDY
METHANE-Rough 8/3/2023 Approved EUGENE CASSIDY
Final 8/9/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 8/9/2023 Not Ready for Inspection EUGENE CASSIDY
Final 8/15/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 8/15/2023 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 8/15/2023 Not Ready for Inspection EUGENE CASSIDY
Final 4/3/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 4/3/2024 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 4/3/2024 Not Ready for Inspection EUGENE CASSIDY
Final 3/26/2025 Corrections Issued EUGENE CASSIDY
Final 5/30/2025 Corrections Issued JOHN KLARIN
Green Building Final 5/30/2025 Corrections Issued JOHN KLARIN
Service/Power Release 5/30/2025 Not Ready for Inspection JOHN KLARIN
Final 9/12/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 9/12/2025 Approved EUGENE CASSIDY
Service/Power Release 9/12/2025 Not Ready for Inspection EUGENE CASSIDY
Final 9/19/2025 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 9/19/2025 Not Required EUGENE CASSIDY