310-310 1/2 S BREED ST 90033
Certificate Information: 310-310 1/2 S BREED ST 90033
- Application / Permit
- 18010-40000-04145
- Plan Check / Job No.
- B18SP00870
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3 story duplex with attached garage
- Permit Issued
- Issued on 8/8/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | MARJAN SHENASI |
| Corrections Issued | 9/10/2018 | MARJAN SHENASI |
| Green Plans Picked Up | 9/10/2018 | APPLICANT |
| Quality Review Completed | 9/12/2018 | JASON HEALEY |
| Building Plans Picked Up | 9/14/2018 | APPLICANT |
| Applicant returned to address corrections | 10/30/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 12/3/2018 | MARJAN SHENASI |
| Plan Check Approved | 12/6/2018 | MARJAN SHENASI |
| Issued | 8/8/2019 | LADBS |
| CofO in Progress | 11/10/2021 | ROBERT VORHIS |
| Permit Finaled | 11/17/2021 | DEROLD HAUFF |
| CofO Issued | 11/17/2021 | DEROLD HAUFF |
| Permit Finaled | 11/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2018 | ADRIAN SANCHEZ |
| Permit | Cleared | 9/26/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 9/26/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/18/2018 | RICHARD GARCIA |
| Project located in CRA area | Cleared | 10/30/2018 | JIM URQUHART |
| Low Impact Development | Cleared | 11/28/2018 | RYAN HUDSON |
| Hydrant and Access approval | Cleared | 11/29/2018 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 11/29/2018 | MICHAEL CASTILLO |
| Trees in Parkway | Cleared | 12/4/2018 | JOEL HERNANDEZ |
| GPI Written Notices | Cleared | 12/5/2018 | MARJAN SHENASI |
| Grading Pre-Inspection | Cleared | 12/5/2018 | MARJAN SHENASI |
Contact Information
| Contractor | Southwest Servicing Group; Lic. No.: 767296-B | 869 EAST FOOTHILL BLVD STE H UPLAND, CA 91786 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/27/2019 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 9/9/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 9/9/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 9/9/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 9/27/2019 | Partial Inspection | ROBERT CORNELL |
| METHANE-Barrier | 9/27/2019 | Corrections Issued | ROBERT CORNELL |
| METHANE-Subgrade | 9/27/2019 | Corrections Issued | ROBERT CORNELL |
| Excavation/Setback/Form/Re-Bar | 5/12/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Corrections Issued | DONALD CRICHLOW |
| Pre-Inspection | 9/4/2020 | Corrections Issued | DONALD CRICHLOW |
| Underground Mechanical | 9/4/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 9/16/2020 | Partial Approval | ROBERT VORHIS |
| METHANE-Barrier | 9/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 9/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 9/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Special/Order Compliance | 10/1/2020 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/20/2020 | Partial Inspection | ROBERT VORHIS |
| METHANE-Barrier | 11/20/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 11/20/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 12/4/2020 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/9/2020 | Approved | ROBERT VORHIS |
| METHANE-Barrier | 12/9/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Partial Inspection | ROBERT VORHIS |
| Drywall Nailing | 12/29/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Partial Approval | RUBEN SALAS |
| Deputy Wood Construction | 1/15/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 1/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Partial Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 2/10/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/10/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/10/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/10/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| METHANE-Rough | 2/10/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/10/2021 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/10/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/16/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 2/16/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 2/16/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 2/16/2021 | Approved | ROBERT VORHIS |
| METHANE-Rough | 2/16/2021 | Approved | ROBERT VORHIS |
| Insulation | 2/22/2021 | Approved | SCOTT FINNILA |
| Drywall Nailing | 2/26/2021 | Approved | ROBERT VORHIS |
| Sewer | 7/21/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 10/26/2021 | Approved | ROBERT VORHIS |
| Gas Test | 10/26/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 10/26/2021 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Final | 11/9/2021 | OK to Issue CofO | ROBERT VORHIS |
| Green Building Final | 11/9/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 11/9/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 11/9/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | ROBERT VORHIS |
| Service/Power Release | 11/9/2021 | Approved | ROBERT VORHIS |
| Smoke Detectors | 11/9/2021 | Approved | ROBERT VORHIS |