426 S PALOS VERDES ST 90731
Certificate Information: 426 S PALOS VERDES ST 90731
- Application / Permit
- 18010-40000-03432
- Plan Check / Job No.
- B18SP00689
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- (N) 126'-10" X 163'-8" CARPORT SUPPORTING SOLAR PANEL ROOF AND RESTRIPE PARKING LOT.
- Permit Issued
- Issued on 10/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 7/25/2018 | APPLICANT |
| Green Plans Picked Up | 7/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/23/2018 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 8/31/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/4/2018 | APPLICANT |
| Applicant returned to address corrections | 11/30/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/9/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/10/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 5/16/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 5/29/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/11/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/1/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 9/18/2019 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 10/18/2019 | JAHANSHAH POURHASSAN |
| Issued | 10/23/2019 | LADBS |
| CofO in Progress | 7/12/2021 | JOEY BUCHANAN |
| CofO Issued | 7/13/2021 | NICK LAROCCA |
| Permit Finaled | 7/13/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Green Code | Cleared | 7/13/2018 | RICHARD GARCIA |
| Port of LA Approval | Cleared | 11/30/2018 | JOHN IBRAHIM |
| City owned building/parcel | Cleared | 12/10/2018 | HAROOT AVANESIAN |
| Historic monument | Cleared | 12/10/2018 | MELISSA JONES |
| Hydrant and Access approval | Cleared | 12/10/2018 | ROBERT DUFF |
| Low Impact Development | Cleared | 12/10/2018 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 12/10/2018 | JOHNATHAN YU |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2018 | JAMES MORALEZ |
| Miscellaneous | Cleared | 12/11/2018 | JAMES MORALEZ |
| Roof/Waste drainage to street | Cleared | 12/11/2018 | JAMES MORALEZ |
| DAS Clearance | Cleared | 1/3/2019 | ELIZABETH TOMS |
| Specific Plan | Cleared | 1/3/2019 | KYLE WINSTON |
| Grading Pre-Inspection | Cleared | 5/21/2019 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 5/29/2019 | JAHANSHAH POURHASSAN |
| "D" conditions | Cleared | 10/7/2019 | NOAH MCCOY |
Contact Information
| Architect | , ; Lic. No.: C34479 | , |
| Contractor | Permacity Empower Corp; Lic. No.: 757547-B | 1415 N BATAVIA ORANGE, CA 92867 |
| Engineer | Abuhamdan, Fouad; Lic. No.: C77455 | 26075 DONELGAL LANE LAKE FOREST, CA 92630 |
| Engineer | Noel, Shane Nelson; Lic. No.: S4800 | 11550 QUINALT POINT SAN DIEGO, CA 92131 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 12/9/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/20/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/21/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/22/2020 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 7/24/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/27/2020 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 7/28/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/29/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/30/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 7/31/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/4/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/5/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 8/6/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/6/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 8/7/2020 | Approved | JOEY BUCHANAN |
| Final | 3/1/2021 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/1/2021 | Approved | JOEY BUCHANAN |
| Green Building Final | 3/1/2021 | Approved | JOEY BUCHANAN |
| Green Building Rough | 3/1/2021 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 3/1/2021 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 3/1/2021 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 3/1/2021 | Approved | JOEY BUCHANAN |