980 N STONE CANYON ROAD 90077
Certificate Information: 980 N STONE CANYON ROAD 90077
- Application / Permit
- 18010-30001-03708
- Plan Check / Job No.
- B20WL02717
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- supplemental ref to pcis # 18010-30000-03708, to convert proposed cabana to ADU w/ (n) additions per state law. (See comment)
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/27/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/28/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 7/30/2020 | APPLICANT |
| Plan Check Approved | 3/2/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/15/2021 | APPLICANT |
| Permit Finaled | 4/17/2024 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/2/2020 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 10/2/2020 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 10/2/2020 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 10/2/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/6/2020 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 10/6/2020 | DENZEL HENDERSON |
| ZI | Cleared | 10/6/2020 | DENZEL HENDERSON |
| Address approval | Cleared | 10/9/2020 | HISASHI KOBAYAKAWA |
| Flood clearance | Cleared | 12/1/2020 | RAYMOND LAM |
| Low Impact Development | Cleared | 12/3/2020 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 12/15/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 1/13/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Silverston & Associates Inc; Lic. No.: 488695-B | 3480 LOS FLORES CYN MALIBU, CA 90265 |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
| Engineer | Masterman, Gary Clyde; Lic. No.: GE567 | 4580 MOHAWK DR LARKSPUR, CO 80118 |
| Geologist | Schick, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 5/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/23/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/30/2021 | Conditional Approval | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/4/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 8/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Corrections Issued | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 2/18/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 2/18/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/31/2022 | Corrections Issued | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 6/17/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/17/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 6/17/2022 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 6/17/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/22/2022 | Partial Approval | CHRISTOPHER WILSON |
| FLOOD-Proofing Certificate | 6/29/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/29/2022 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 6/29/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 7/20/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 7/26/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 3/30/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 4/9/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 4/10/2024 | Partial Approval | CHRISTOPHER WILSON |
| Final | 4/15/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Smoke Detectors | 4/15/2024 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/16/2024 | Partial Inspection | CHRISTOPHER WILSON |