4248 N BARRETT ROAD 90032
Certificate Information: 4248 N BARRETT ROAD 90032
- Application / Permit
- 18010-30000-06332
- Plan Check / Job No.
- B18WL08051
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/30/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2019 | MANUEL GARCIA |
| Corrections Issued | 1/14/2019 | MANUEL GARCIA |
| Quality Review Completed | 1/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/9/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 6/14/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/1/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/5/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/14/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 2/26/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/24/2020 | MANUEL GARCIA |
| Plan Check Approved | 3/27/2020 | MANUEL GARCIA |
| Building Plans Picked Up | 9/8/2020 | APPLICANT |
| Green Plans Picked Up | 9/8/2020 | APPLICANT |
| Issued | 10/30/2023 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 5/15/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 5/15/2019 | TREVOR MARTIN |
| ZI | Cleared | 5/15/2019 | TREVOR MARTIN |
| Construction near power lines | Cleared | 5/23/2019 | RIDWAN HARDY |
| Trees in Parkway | Cleared | 6/3/2019 | JOHN KIM |
| Hydrant and Access approval | Cleared | 6/11/2019 | GEORGE SUCHAND |
| Address approval | Cleared | 6/19/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/19/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/19/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/19/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2019 | LEE GUILBEAUX |
| Permit | Cleared | 6/21/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 7/29/2019 | MITESH PATEL |
| "D" conditions | Cleared | 9/10/2019 | DIANA JIMENEZ |
| "Q" conditions | Cleared | 9/10/2019 | DIANA JIMENEZ |
| Disturb/Remove Protected Trees | Cleared | 9/10/2019 | ADRIAN SANCHEZ |
| Landscape for retaining wall | Cleared | 9/10/2019 | DIANA JIMENEZ |
| Miscellaneous | Cleared | 9/10/2019 | DIANA JIMENEZ |
| Roof/Waste drainage to street | Cleared | 10/30/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/30/2019 | MARKOS PEREZ-BRAN |
| Work Adjacent to Public Way | Cleared | 11/13/2019 | ARMEN SARKISIAN |
| Encroachment in public way | Cleared | 11/25/2019 | ELENA LOPEZ |
| Building over 3-story or 36-ft | Cleared | 2/26/2020 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 2/26/2020 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 2/26/2020 | MANUEL GARCIA |
| Green Code | Cleared | 3/5/2020 | RICHARD GARCIA |
Contact Information
| Architect | Heeb,, Derek M; Lic. No.: C32338 | 406 BROADWAY 222C SANTA MONICA, CA 90401 |
| Contractor | Top Star Usa Construction Inc; Lic. No.: 1067089-B | 4127 WALNUT GROVE APT A ROSEMEAD, CA 91770 |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 112 ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2023 | Partial Inspection | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 1/18/2024 | Not Ready for Inspection | AMY COLIN |
| Protected Tree Letter | 1/18/2024 | Not Ready for Inspection | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Partial Approval | AMY COLIN |
| Masonry Wall/Backfill | 2/13/2024 | Corrections Issued | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 2/20/2024 | No Access for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 8/14/2024 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Corrections Issued | LILIANA PORTILLO |
| Piling/Pier/Caisson | 8/20/2024 | Corrections Issued | LILIANA PORTILLO |
| Piling/Pier/Caisson | 9/18/2024 | Partial Inspection | THOMAS LOGRASSO |
| Protected Tree Letter | 9/18/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/3/2024 | Corrections Issued | LILIANA PORTILLO |
| Piling/Pier/Caisson | 12/3/2024 | Corrections Issued | LILIANA PORTILLO |
| Protected Tree Letter | 12/3/2024 | Approved | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 12/17/2024 | Conditional Approval | LILIANA PORTILLO |
| Reinforced Concrete Frame | 1/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 2/19/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/19/2025 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Reinf. Concrete | 4/10/2025 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/14/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 4/14/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 4/21/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Steel/Welding | 4/29/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Piling/Pier/Caisson | 6/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Deputy Steel/Welding | 6/23/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/20/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 10/20/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/20/2025 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/20/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/23/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 10/23/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 10/24/2025 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 10/28/2025 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/30/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/30/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/30/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/20/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 12/10/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/18/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 1/13/2026 | Partial Approval | RONNIE MEDINA |
| Drywall Nailing | 2/24/2026 | Approved | GEM DE OCAMPO |
| Shower Pan | 3/10/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/20/2026 | Approved | LILIANA PORTILLO |