11700 W CHARNOCK ROAD #3 90066
Certificate Information: 11700 W CHARNOCK ROAD #3 90066
- Application / Permit
- 18010-30000-06309
- Plan Check / Job No.
- B18WL08023
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONSTRCUTION OF (N) 6 UNIT SMALL LOT SUBDIVISION 3 OF 6 SFD
- Permit Issued
- Issued on 2/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2018 | APPLICANT |
| Green Plans Picked Up | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 1/15/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 1/17/2019 | CORA JOHNSON |
| Applicant returned to address corrections | 10/9/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/27/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/7/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/24/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/10/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/3/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/28/2020 | CHIHARU SUZUKI |
| Issued | 2/22/2021 | APPLICANT |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Refund in Progress | 12/21/2021 | SELENIA GARCIA |
| Refund Closed | 12/21/2021 | SELENIA GARCIA |
| Issued | 12/21/2021 | SELENIA GARCIA |
| CofO in Progress | 10/18/2025 | KIRK SANDERS |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
| CofO Issued | 11/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2019 | DENNIS BRAGIN |
| Permit | Cleared | 6/17/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/17/2019 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 12/20/2019 | JEREMY CARTER |
| Highway dedication | Cleared | 3/16/2020 | RAYMOND MUGAMBWA |
| Trees in Parkway | Cleared | 5/6/2020 | JOHN KIM |
| Low Impact Development | Cleared | 5/29/2020 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 6/22/2020 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 7/2/2020 | DINAH GARIN |
| Building over 3-story or 36-ft | Cleared | 7/10/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 7/16/2020 | KATHLEEN HUGHEY |
| Tract Map conditions | Cleared | 7/30/2020 | LOUIS ORTEGA |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/18/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/15/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Reinforced Concrete Frame | 9/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/18/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 4/28/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/20/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/20/2022 | Partial Approval | RYAN SALAZAR |
| Gas Test | 9/7/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 9/7/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 9/13/2022 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/20/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/2/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 11/2/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 11/4/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 11/10/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 11/14/2022 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 11/18/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/30/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 11/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 12/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 12/5/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 2/7/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/28/2023 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 8/30/2024 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 9/16/2024 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Final | 11/15/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 11/15/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 11/15/2024 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 12/6/2024 | Approved | DANIEL VERA |
| Final | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 12/6/2024 | Approved | DANIEL VERA |
| Reinforced Masonry Frame | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | DANIEL VERA |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| Structural Steel Frame | 12/6/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 12/16/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 12/19/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 12/30/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/21/2025 | Approved | DANIEL VERA |
| Gas Test | 3/11/2025 | Approved | WILBER ROSALES |
| Final | 4/3/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/3/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 4/3/2025 | Corrections Issued | BOBBY KEY |
| Reinforced Masonry Frame | 4/3/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 4/3/2025 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 4/3/2025 | Approved | BOBBY KEY |
| Structural Steel Frame | 4/3/2025 | Approved | BOBBY KEY |
| Service/Power Release | 4/29/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 5/13/2025 | Approved | WILBER ROSALES |
| Final | 9/22/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/22/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 9/22/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Not Ready | KIRK SANDERS |
| Final | 10/14/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | KIRK SANDERS |
| Final | 10/17/2025 | OK to Issue CofO | KIRK SANDERS |