11700 W CHARNOCK ROAD #3 90066

Certificate Information: 11700 W CHARNOCK ROAD #3 90066

Application / Permit
18010-30000-06309
Plan Check / Job No.
B18WL08023
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRCUTION OF (N) 6 UNIT SMALL LOT SUBDIVISION 3 OF 6 SFD
Permit Issued
Issued on 2/22/2021
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2018 APPLICANT
Green Plans Picked Up 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 1/15/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 1/17/2019 CORA JOHNSON
Applicant returned to address corrections 10/9/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/27/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/7/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/24/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/3/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/28/2020 CHIHARU SUZUKI
Issued 2/22/2021 APPLICANT
Building Plans Picked Up 2/25/2021 APPLICANT
Refund in Progress 12/21/2021 SELENIA GARCIA
Refund Closed 12/21/2021 SELENIA GARCIA
Issued 12/21/2021 SELENIA GARCIA
CofO in Progress 10/18/2025 KIRK SANDERS
Permit Finaled 11/4/2025 RICHARD STEINBACH
CofO Issued 11/4/2025 RICHARD STEINBACH
Permit Finaled 11/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/17/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/17/2019 DENNIS BRAGIN
Permit Cleared 6/17/2019 DENNIS BRAGIN
Sewer availability Cleared 6/17/2019 DENNIS BRAGIN
Hydrant and Access approval Cleared 12/20/2019 JEREMY CARTER
Highway dedication Cleared 3/16/2020 RAYMOND MUGAMBWA
Trees in Parkway Cleared 5/6/2020 JOHN KIM
Low Impact Development Cleared 5/29/2020 JORGE MEJIA LEMUS
Green Code Cleared 6/22/2020 RICHARD GARCIA
Roof/Waste drainage to street Cleared 7/2/2020 DINAH GARIN
Building over 3-story or 36-ft Cleared 7/10/2020 CALOSHA APPROVED
Miscellaneous Cleared 7/16/2020 KATHLEEN HUGHEY
Tract Map conditions Cleared 7/30/2020 LOUIS ORTEGA

Contact Information

Architect Thibodeau,, Robert E; Lic. No.: C25585 812 LINCOLN BLVD      VENICE, CA 90291
Contractor Owner-Builder       ,
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/20/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/18/2021 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 9/14/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 9/15/2021 Partial Approval OGANES TARAKHCHYAN
Reinforced Concrete Frame 9/22/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/18/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 3/18/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval JOHNNY MIRANDA
Wood Frame 4/28/2022 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 5/20/2022 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 5/20/2022 Partial Approval RYAN SALAZAR
Gas Test 9/7/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 9/7/2022 Approved JOHN KIDWELL
HVAC-Rough 9/13/2022 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 9/20/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/2/2022 Corrections Issued JOHNNY MIRANDA
Green Building Rough 11/2/2022 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 11/2/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/4/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 11/4/2022 Not Ready for Inspection JOHNNY MIRANDA
Insulation 11/10/2022 Not Ready for Inspection JOHNNY MIRANDA
Insulation 11/14/2022 Corrections Issued CLAYTON GRAHAM
Insulation 11/18/2022 Approved JOHNNY MIRANDA
Drywall Nailing 11/30/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 11/30/2022 Not Ready for Inspection JESUS RODRIGUEZ
Drywall Nailing 12/5/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 12/5/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 2/3/2023 Partial Approval JOHNNY MIRANDA
Shower Pan 2/7/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/10/2023 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 2/28/2023 Partial Approval JOHNNY MIRANDA
Gas Test 8/30/2024 Partial Approval DANIEL VERA
PLUMBING-Rough 9/16/2024 Partial Approval KENNETH NAGLE
ELECTRICAL-Final 11/15/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 11/15/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 11/15/2024 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 12/6/2024 Approved DANIEL VERA
Drywall Nailing 12/6/2024 Approved DANIEL VERA
Final 12/6/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 12/6/2024 Not Ready for Inspection DANIEL VERA
Green Building Rough 12/6/2024 Approved DANIEL VERA
Reinforced Masonry Frame 12/6/2024 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Ready DANIEL VERA
Service/Power Release 12/6/2024 Not Ready for Inspection DANIEL VERA
Smoke Detectors 12/6/2024 Not Ready for Inspection DANIEL VERA
Structural Steel Frame 12/6/2024 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 12/16/2024 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 12/19/2024 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 12/30/2024 Approved EVAN COOPER
PLUMBING-Final 2/21/2025 Approved DANIEL VERA
Gas Test 3/11/2025 Approved WILBER ROSALES
Final 4/3/2025 Corrections Issued BOBBY KEY
Green Building Final 4/3/2025 Corrections Issued BOBBY KEY
HVAC-Final 4/3/2025 Corrections Issued BOBBY KEY
Reinforced Masonry Frame 4/3/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready BOBBY KEY
Service/Power Release 4/3/2025 Not Ready for Inspection BOBBY KEY
Smoke Detectors 4/3/2025 Approved BOBBY KEY
Structural Steel Frame 4/3/2025 Approved BOBBY KEY
Service/Power Release 4/29/2025 Approved WILBER ROSALES
Service/Power Release 5/13/2025 Approved WILBER ROSALES
Final 9/22/2025 Corrections Issued KIRK SANDERS
Green Building Final 9/22/2025 Approved KIRK SANDERS
HVAC-Final 9/22/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready KIRK SANDERS
Final 10/14/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved KIRK SANDERS
Final 10/17/2025 OK to Issue CofO KIRK SANDERS