Piling/Pier/Caisson
|
5/19/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Footing/Foundation/Slab
|
8/18/2021
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Underground Mechanical
|
9/14/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Underground Mechanical
|
9/15/2021
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Reinforced Concrete Frame
|
9/22/2021
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Green Building Rough
|
9/23/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Light Gage Steel Frame
|
9/23/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Reinforced Concrete Frame
|
9/23/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Reinforced Masonry Frame
|
9/23/2021
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Verify Sprinkler Sign Off
|
9/23/2021
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Footing/Foundation/Slab
|
10/18/2021
|
Approved
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/24/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Drywall Nailing
|
5/26/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/14/2022
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/23/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Drywall Nailing
|
6/28/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Drywall Nailing
|
7/5/2022
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2022
|
Partial Approval
|
DAVID FEILER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/3/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Drywall Nailing
|
8/5/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Green Building Rough
|
8/5/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Drywall Nailing
|
8/9/2022
|
Partial Approval
|
KENNETH NAGLE
|
|
Green Building Rough
|
8/9/2022
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2022
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Drywall Nailing
|
8/16/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Green Building Rough
|
8/16/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/7/2022
|
Conditional Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Drywall Nailing
|
9/14/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Green Building Rough
|
9/14/2022
|
Partial Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/30/2022
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Drywall Nailing
|
11/7/2022
|
Partial Approval
|
CLAYTON GRAHAM
|
|
Green Building Rough
|
11/7/2022
|
Not Ready for Inspection
|
CLAYTON GRAHAM
|
|
Drywall Nailing
|
11/15/2022
|
Partial Approval
|
JOHNNY MIRANDA
|
|
Green Building Rough
|
11/15/2022
|
Not Ready for Inspection
|
JOHNNY MIRANDA
|
|
ELECTRICAL-Rough
|
1/13/2023
|
Corrections Issued
|
JOHNNY MIRANDA
|
|
HVAC-Rough
|
1/13/2023
|
Corrections Issued
|
JOHNNY MIRANDA
|
|
ELECTRICAL-Rough
|
1/19/2023
|
Approved
|
JOHNNY MIRANDA
|
|
HVAC-Rough
|
1/19/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/23/2023
|
Approved
|
JOHNNY MIRANDA
|
|
PLUMBING-Rough
|
2/28/2023
|
Approved
|
JOHNNY MIRANDA
|
|
BUILDING-Rough-Frame
|
3/10/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Green Building Rough
|
3/10/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Verify Sprinkler Sign Off
|
3/10/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Insulation
|
3/29/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Interior/Exterior Lathing
|
3/29/2023
|
Partial Approval
|
JOHNNY MIRANDA
|
|
Shower Pan
|
4/4/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Interior/Exterior Lathing
|
4/5/2023
|
Partial Approval
|
JOHNNY MIRANDA
|
|
Interior/Exterior Lathing
|
4/20/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Drywall Nailing
|
5/2/2023
|
Not Ready for Inspection
|
JOHNNY MIRANDA
|
|
Drywall Nailing
|
5/4/2023
|
Approved
|
JOHNNY MIRANDA
|
|
Gas Test
|
8/30/2024
|
Partial Approval
|
DANIEL VERA
|
|
PLUMBING-Rough
|
9/16/2024
|
Partial Approval
|
KENNETH NAGLE
|
|
ELECTRICAL-Final
|
1/2/2025
|
Not Ready for Inspection
|
DANIEL VERA
|
|
ELECTRICAL-Final
|
1/6/2025
|
Not Ready for Inspection
|
DANIEL VERA
|
|
HVAC-Final
|
1/23/2025
|
Corrections Issued
|
EVAN COOPER
|
|
ELECTRICAL-Final
|
1/27/2025
|
Approved
|
DANIEL VERA
|
|
HVAC-Final
|
1/28/2025
|
Approved
|
EVAN COOPER
|
|
PLUMBING-Final
|
3/4/2025
|
Approved
|
DANIEL VERA
|
|
Special/Order Compliance
|
3/4/2025
|
Partial Inspection
|
WILBER ROSALES
|
|
Gas Test
|
3/11/2025
|
Approved
|
WILBER ROSALES
|
|
Final
|
4/3/2025
|
Corrections Issued
|
BOBBY KEY
|
|
Green Building Final
|
4/3/2025
|
Corrections Issued
|
BOBBY KEY
|
|
Reinforced Masonry Frame
|
4/3/2025
|
Approved
|
BOBBY KEY
|
|
SGSOV-Seismic Gas S/O Valve
|
4/3/2025
|
SGSOV Not Ready
|
BOBBY KEY
|
|
Service/Power Release
|
4/3/2025
|
Not Ready for Inspection
|
BOBBY KEY
|
|
Smoke Detectors
|
4/3/2025
|
Approved
|
BOBBY KEY
|
|
Structural Steel Frame
|
4/3/2025
|
Approved
|
BOBBY KEY
|
|
Service/Power Release
|
4/29/2025
|
Approved
|
WILBER ROSALES
|
|
Service/Power Release
|
5/12/2025
|
Approved
|
WILBER ROSALES
|
|
Final
|
9/22/2025
|
Corrections Issued
|
KIRK SANDERS
|
|
Green Building Final
|
9/22/2025
|
Approved
|
KIRK SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
9/22/2025
|
SGSOV Not Ready
|
KIRK SANDERS
|
|
Final
|
10/14/2025
|
Corrections Issued
|
KIRK SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
10/14/2025
|
SGSOV Approved
|
KIRK SANDERS
|
|
Final
|
10/17/2025
|
OK to Issue CofO
|
KIRK SANDERS
|