8514-8526 S HOOVER ST 90044
Certificate Information: 8514-8526 S HOOVER ST 90044
- Application / Permit
- 18010-30000-06245
- Plan Check / Job No.
- B18WL07961
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- (N) 3-UNIT RETAIL STRUCTURE AT AUTOMOTIVE FUELING STATION FACILITY.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | REZA HAGHIGHAT |
| Disabled Access Plans Picked Up | 1/24/2019 | APPLICANT |
| Corrections Issued | 2/15/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 2/27/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/28/2019 | APPLICANT |
| Plan Check Approved | 2/20/2020 | REZA HAGHIGHAT |
| Issued | 2/24/2020 | LADBS |
| TCO Issued (Expire Date: 12-12-2022) | 6/15/2022 | TED RIES |
| CofO in Progress | 9/7/2022 | JAMES POWERS |
| CofO Issued | 9/9/2022 | ERNESTO CORRAL |
| Permit Finaled | 9/9/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 10/18/2019 | JIM URQUHART |
| Community Plan Implem. Overlay | Cleared | 11/7/2019 | HELEN JADALI |
| Driveway location | Cleared | 11/7/2019 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | THOMAS LANG |
| Internal circulation | Cleared | 11/7/2019 | PETE EYRE |
| Permit | Cleared | 11/7/2019 | THOMAS LANG |
| ZI | Cleared | 11/7/2019 | HELEN JADALI |
| "Q" conditions | Cleared | 11/14/2019 | SARAH GOLDMAN |
| Automotive Use | Cleared | 11/14/2019 | SARAH GOLDMAN |
| Green Code | Cleared | 11/14/2019 | DONALD CRICHLOW |
| Sewer availability | Cleared | 11/14/2019 | DINAH GARIN |
| ZA Case | Cleared | 11/14/2019 | SARAH GOLDMAN |
| ZI | Cleared | 11/14/2019 | SARAH GOLDMAN |
| DAS Clearance | Cleared | 11/21/2019 | REZA HAGHIGHAT |
| Hydrant and Access approval | Cleared | 11/21/2019 | JOHN CONNEALLY |
| Automotive Use | Cleared | 12/10/2019 | DENZEL HENDERSON |
| Comm Cor/Mini-Mall | Cleared | 12/10/2019 | DENZEL HENDERSON |
| Comm Cor/Mini-Mall | Cleared | 12/10/2019 | DENZEL HENDERSON |
| Highway dedication | Cleared | 1/7/2020 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 2/10/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JUAN ASHTON |
| Food Service Establishment | Cleared | 2/18/2020 | RAMESHBHAIR PATEL |
| Food establishment approval | Cleared | 2/18/2020 | LACDHS APPROVED |
Contact Information
| Architect | Manligas,, Amorsolo Rubio; Lic. No.: C15983 | 13106 CHAPMAN AVENUE APT 4-104 GARDEN GROVE, CA 92840 |
| Contractor | Skyson Construction Co; Lic. No.: 515183-B | 17609 VENTURA BLVD #218 ENCINO, CA 91316 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2020 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 4/22/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 4/23/2020 | Conditional Approval | JAMES POWERS |
| Footing/Foundation/Slab | 4/24/2020 | Not Ready for Inspection | RONALD PACHECO |
| Deputy Reinf. Masonry | 5/4/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 5/4/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 5/4/2020 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/4/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 5/5/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/12/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 5/12/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/12/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 5/18/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/26/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 5/26/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 5/26/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/26/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 6/10/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 6/10/2020 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 6/10/2020 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/10/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 6/16/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/16/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 6/19/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/19/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 6/23/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/23/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Steel/Welding | 6/24/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 6/25/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 6/29/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/29/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 6/29/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 6/29/2020 | Not Ready for Inspection | JAMES POWERS |
| Structural Steel Frame | 6/29/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/29/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 7/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Structural Steel Frame | 7/2/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Wall Anchors | 7/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/6/2020 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 7/9/2020 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/9/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 7/10/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 8/20/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 8/24/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 8/26/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/23/2020 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 11/23/2020 | Partial Approval | JAMES POWERS |
| Insulation | 11/30/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/30/2020 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 11/30/2020 | Partial Approval | JAMES POWERS |
| Insulation | 12/3/2020 | Approved | JAMES POWERS |
| Drywall Nailing | 12/10/2020 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 12/23/2020 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 1/5/2021 | Approved | JAMES POWERS |
| T-Bar Ceiling | 2/23/2021 | Partial Approval | JAMES POWERS |
| Piling/Pier/Caisson | 9/2/2021 | Partial Approval | JAMES POWERS |
| T-Bar Ceiling | 9/28/2021 | Approved | JAMES POWERS |
| Special/Order Compliance | 11/18/2021 | Partial Inspection | TED RIES |
| Special/Order Compliance | 1/18/2022 | Partial Approval | JAMES POWERS |
| Final | 5/25/2022 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 5/25/2022 | Approved | JAMES POWERS |
| Green Building Final | 5/25/2022 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 5/25/2022 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 5/25/2022 | Approved | JAMES POWERS |
| Structural Steel Frame | 5/25/2022 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | JAMES POWERS |
| Wood Frame | 5/25/2022 | Approved | JAMES POWERS |
| Final | 6/8/2022 | Not Ready for Inspection | JAMES POWERS |
| Structural Steel Frame | 6/8/2022 | Approved | JAMES POWERS |
| Final | 9/6/2022 | OK to Issue CofO | JAMES POWERS |