1027 N BONNIE BRAE ST 1-39 90026

Certificate Information: 1027 N BONNIE BRAE ST 1-39 90026

Application / Permit
18010-30000-06113
Plan Check / Job No.
B18WL07910
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
4 StoryType V-A apartment on 1 level Type-I subterranean garage. with ADU
Permit Issued
Issued on 12/22/2022
Issuing Office
Valley
Current Status
Issued on 12/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2018 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 1/22/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 1/30/2019 CORA JOHNSON
Disabled Access Plans Picked Up 2/5/2019 APPLICANT
Green Plans Picked Up 2/5/2019 APPLICANT
Applicant returned to address corrections 3/21/2022 TARIK SAOUD
Applicant returned to address corrections 10/14/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/17/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/19/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/21/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/23/2022 KAVIAN REFAHI
Applicant returned to address corrections 11/2/2022 KAVIAN REFAHI
Plan Check Approved 11/4/2022 KAVIAN REFAHI
Building Plans Picked Up 11/4/2022 APPLICANT
Issued 12/22/2022 APPLICANT

Permit Application Clearance Information

Trees in Parkway Cleared 3/20/2019 ADRIAN SANCHEZ
Highway dedication Cleared 2/9/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/11/2022 CHRISTOPHER ROCHA
Address approval Cleared 2/23/2022 CHRISTOPHER ROCHA
Permit Cleared 2/23/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 3/8/2022 WALLIE JONG
Low Impact Development Cleared 3/15/2022 ORVAL HERNANDEZ-MARCI
Fire Marshall Fire Life Safety Cleared 6/28/2022 PEJMAN NOORI
DAS Clearance Cleared 7/5/2022 KAMRAN GHOTBI RAVANDI
Hydrant and Access approval Cleared 8/1/2022 RUEL COLE
Green Code Cleared 9/16/2022 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 9/21/2022 CHRISTOPHER ROCHA
Frnt yard landscape/Water mgmt Cleared 9/22/2022 MAYELA VILLA
Opn space landscape/Water mgmt Cleared 9/22/2022 MAYELA VILLA
GPI Written Notices Cleared 10/17/2022 KAMRAN GHOTBI RAVANDI
Grading Pre-Inspection Cleared 10/17/2022 KAMRAN GHOTBI RAVANDI
Building over 3-story or 36-ft Cleared 11/2/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/2/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 11/16/2022 KHOUNG LE

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor P And N Construction Inc; Lic. No.: 800653-B 8730 WILSHIRE BLVD #202      BEVERLY HILLS, CA 90211
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2023 Partial Inspection DAVID BURKHEAD
Pre-Inspection 2/14/2023 Not Ready for Inspection TIMOTHY POWELL
Deputy Steel/Welding 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 6/23/2023 Partial Approval TIMOTHY POWELL
Footing/Foundation/Slab 6/29/2023 Partial Approval TIMOTHY POWELL
Green Building Rough 7/5/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 7/5/2023 Partial Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 7/5/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 7/13/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 7/13/2023 Partial Approval TIMOTHY POWELL
Verify Sprinkler Sign Off 7/13/2023 Not Ready for Inspection TIMOTHY POWELL
Deputy Reinf. Concrete 7/14/2023 Approved TIMOTHY POWELL
Deputy Shotcrete 7/14/2023 Approved TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/14/2023 Partial Inspection TIMOTHY POWELL
Deputy Reinf. Concrete 7/17/2023 Approved TIMOTHY POWELL
Deputy Shotcrete 7/17/2023 Approved TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 7/17/2023 Partial Inspection TIMOTHY POWELL
Deputy Reinf. Masonry 7/20/2023 Approved TIMOTHY POWELL
Green Building Rough 7/20/2023 Not Ready for Inspection TIMOTHY POWELL
Masonry Wall/Backfill 7/20/2023 Partial Inspection TIMOTHY POWELL
Reinforced Masonry Frame 7/20/2023 Partial Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 7/20/2023 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 7/25/2023 Partial Approval TIMOTHY POWELL
Footing/Foundation/Slab 7/28/2023 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 8/2/2023 Approved TIMOTHY POWELL
Deputy Shotcrete 8/2/2023 Approved TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 8/2/2023 Partial Inspection TIMOTHY POWELL
Deputy Other (see comments) 8/3/2023 Conditional Approval TIMOTHY POWELL
Deputy Shotcrete 8/3/2023 Conditional Approval TIMOTHY POWELL
Deputy Shotcrete 8/4/2023 No Access for Inspection TIMOTHY POWELL
Reinforced Masonry Frame 8/8/2023 Partial Approval TIMOTHY POWELL
Deputy Reinf. Concrete 8/15/2023 Conditional Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 8/15/2023 Conditional Approval JULIAN CAPUCETTI
Green Building Rough 8/21/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 8/21/2023 Partial Approval TIMOTHY POWELL
Verify Sprinkler Sign Off 8/21/2023 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 9/11/2023 Partial Approval TIMOTHY POWELL
Deputy Shotcrete 10/4/2023 Conditional Approval TIMOTHY POWELL
Deputy Shotcrete 10/5/2023 Conditional Approval RONALD JIMENEZ
Deputy Shotcrete 10/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/10/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 10/25/2023 Approved RONALD JIMENEZ
Reinforced Concrete Frame 10/25/2023 Partial Inspection RONALD JIMENEZ
Verify Sprinkler Sign Off 10/25/2023 Not Ready for Inspection RONALD JIMENEZ
Deputy Reinf. Concrete 11/7/2023 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 11/7/2023 Conditional Approval RONALD JIMENEZ
Reinforced Concrete Frame 11/7/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 11/8/2023 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 11/8/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 11/9/2023 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 11/9/2023 Partial Approval RONALD JIMENEZ
Deputy Reinf. Concrete 11/13/2023 Conditional Approval RONALD JIMENEZ
Reinforced Concrete Frame 11/14/2023 Partial Approval RONALD JIMENEZ
Verify Sprinkler Sign Off 11/14/2023 Not Ready for Inspection RONALD JIMENEZ
Deputy Reinf. Concrete 11/16/2023 Conditional Approval RONALD JIMENEZ
Deputy Shotcrete 11/16/2023 Conditional Approval RONALD JIMENEZ
Deputy Shotcrete 11/17/2023 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Masonry 11/20/2023 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Masonry 11/21/2023 Conditional Approval RONALD JIMENEZ
Masonry Wall/Backfill 11/22/2023 Partial Approval RAMAZANALI ALMASI
Deputy Steel/Welding 12/1/2023 Conditional Approval RONALD JIMENEZ
Deputy Steel/Welding 12/8/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 1/11/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 1/23/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/24/2024 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 1/24/2024 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/26/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 1/26/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 1/26/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Corrections Issued JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Not Ready for Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/5/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/13/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/28/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/28/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Inspection JEFFREY FULTON
Insulation 7/9/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval LARRY ARNICK
Insulation 7/23/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 7/24/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Inspection JEFFREY FULTON
Wood Frame 7/24/2024 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 7/25/2024 Conditional Approval JEFFREY FULTON
Wood Frame 7/25/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Inspection JEFFREY FULTON
Wood Frame 8/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/6/2024 Partial Inspection JEFFREY FULTON
Insulation 8/6/2024 Partial Inspection JEFFREY FULTON
Insulation 8/12/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 8/13/2024 Partial Inspection JEFFREY FULTON
Insulation 8/13/2024 Partial Inspection JEFFREY FULTON
Wood Frame 8/13/2024 Partial Inspection JEFFREY FULTON
Insulation 8/23/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/5/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/12/2024 Partial Approval LARRY ARNICK
Drywall Nailing 9/16/2024 Partial Inspection JEFFREY FULTON
Insulation 9/16/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Partial Inspection JEFFREY FULTON
Wood Frame 10/2/2024 Partial Inspection JEFFREY FULTON
Insulation 10/4/2024 Partial Approval TIMOTHY POWELL
Insulation 10/8/2024 Corrections Issued LARRY ARNICK
Insulation 10/17/2024 Partial Inspection JEFFREY FULTON
Wood Frame 10/17/2024 Partial Inspection JEFFREY FULTON
Insulation 10/28/2024 Partial Approval TIMOTHY POWELL
Insulation 10/29/2024 Partial Inspection JEFFREY FULTON
Insulation 12/2/2024 Partial Inspection JEFFREY FULTON
Insulation 12/5/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 12/5/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/5/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/6/2024 Partial Inspection JEFFREY FULTON
Insulation 12/9/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/9/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/11/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/11/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/12/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 12/13/2024 Partial Inspection JEFFREY FULTON
Insulation 12/16/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 12/18/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/18/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/20/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 12/23/2024 Partial Approval RAMAZANALI ALMASI
Interior/Exterior Lathing 1/2/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/6/2025 Partial Inspection JEFFREY FULTON
Insulation 1/6/2025 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 1/6/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/14/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 1/22/2025 Corrections Issued JEFFREY FULTON
Drywall Nailing 4/7/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/10/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/17/2025 Partial Approval LARRY ARNICK
Drywall Nailing 4/18/2025 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 4/23/2025 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/23/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/3/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 7/15/2025 Approved DAVID BURKHEAD
Pre-Inspection 1/28/2026 Conditional Approval LARRY ARNICK
Drywall Nailing 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 2/25/2026 Approved RONALD JIMENEZ
Green Building Final 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
Pre-Inspection 2/25/2026 Approved RONALD JIMENEZ
Reinforced Concrete Frame 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
Verify Sprinkler Sign Off 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 2/25/2026 Not Ready for Inspection RONALD JIMENEZ
Pre-Inspection 3/6/2026 Partial Inspection DAVID BURKHEAD
Drywall Nailing 7/8/2026 Partial Approval RONALD JIMENEZ
Final 7/8/2026 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 7/8/2026 Not Ready for Inspection RONALD JIMENEZ
Reinforced Concrete Frame 7/8/2026 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/8/2026 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 7/8/2026 Approved RONALD JIMENEZ
Verify Sprinkler Sign Off 7/8/2026 Approved RONALD JIMENEZ
Wood Frame 7/8/2026 Approved RONALD JIMENEZ
Pre-Inspection 7/9/2026 Approved RONALD JIMENEZ
Drywall Nailing 7/15/2026 Not Ready for Inspection RONALD JIMENEZ
Final 7/15/2026 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 7/15/2026 Not Ready for Inspection RONALD JIMENEZ