219 N HOMEWOOD ROAD 90049

Certificate Information: 219 N HOMEWOOD ROAD 90049

Application / Permit
18010-30000-06066
Plan Check / Job No.
B18WL07882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with attached 3 car garage & 1 level basement.
Permit Issued
Issued on 8/8/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2018 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 JAHANSHAH POURHASSAN
Green Plans Picked Up 1/25/2019 APPLICANT
Corrections Issued 2/7/2019 JAHANSHAH POURHASSAN
Quality Review Completed 2/14/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/19/2019 APPLICANT
Applicant returned to address corrections 5/24/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/7/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/10/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/24/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/8/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/11/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/22/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/25/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/6/2019 JAHANSHAH POURHASSAN
Plan Check Approved 8/7/2019 JAHANSHAH POURHASSAN
Issued 8/8/2019 LADBS
CofO in Progress 4/26/2023 KEVIN SARGSYAN
Permit Finaled 4/26/2023 DANIEL ORRANTE
CofO Issued 4/26/2023 DANIEL ORRANTE
Permit Finaled 4/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/19/2019 STEVEN JIN
BHO/Hillside ordinance Cleared 2/19/2019 STEVEN JIN
BHO/Hillside ordinance Cleared 2/19/2019 STEVEN JIN
BHO/Hillside ordinance Cleared 2/19/2019 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 2/19/2019 STEVEN JIN
Permit Cleared 2/19/2019 STEVEN JIN
Construction near power lines Cleared 4/17/2019 NADER ISKANDER
Hydrant and Access approval Cleared 4/17/2019 GEORGE SUCHAND
Sewer availability Cleared 4/23/2019 CHRISTOPHER LAW
Low Impact Development Cleared 5/10/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/16/2019 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 5/17/2019 JOHN KIM
Excavation more than 5-ft deep Cleared 5/24/2019 CALOSHA APPROVED
Green Code Cleared 8/6/2019 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Gill,, Gary Edward; Lic. No.: S3382 7527 SUNNYSIDE AVE N      SEATTLE, WA 98103
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Plouff,, Kacie Allison; Lic. No.: L9013 27821 FREMONT COURT 6      VALENCIA, CA 91355
Geologist Kennedy,, Cameron L; Lic. No.: EG2631 25208 W DOLCE COURT      STEVENSON RANCH, CA 91381
Landscape Architect Jensen,, Peter Cassidy; Lic. No.: LA5663 1158 26TH ST      SANTA MONICA, CA 90403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2020 Approved TIM CHRISTENSEN
Piling/Pier/Caisson 2/19/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/20/2020 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 3/20/2020 Not Ready for Inspection TIM CHRISTENSEN
Deputy Reinf. Concrete 3/25/2020 Conditional Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 3/25/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 3/25/2020 Partial Inspection TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/16/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/23/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/30/2020 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 5/5/2020 Conditional Approval TIM CHRISTENSEN
PLUMBING-Rough 5/18/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 5/26/2020 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 5/28/2020 Conditional Approval TIM CHRISTENSEN
Special/Order Compliance 6/11/2020 Partial Inspection ROBERT SHELLY
Deputy Steel/Welding 6/23/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 7/8/2020 Partial Approval TIM CHRISTENSEN
Structural Steel Frame 7/9/2020 Partial Approval TIM CHRISTENSEN
Deputy Steel/Welding 7/10/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 7/20/2020 Partial Approval TIM CHRISTENSEN
Deputy Steel/Welding 7/21/2020 Conditional Approval TIM CHRISTENSEN
Deputy Steel/Welding 7/23/2020 Conditional Approval TIM CHRISTENSEN
Deck 7/24/2020 Approved TIM CHRISTENSEN
Structural Steel Frame 7/24/2020 Approved TIM CHRISTENSEN
Deputy Reinf. Concrete 7/27/2020 Approved ROBERT SHELLY
Deputy Steel/Welding 8/12/2020 Corrections Issued ROBERT SHELLY
Deputy Steel/Welding 8/13/2020 Conditional Approval TIM CHRISTENSEN
Structural Steel Frame 8/14/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Conditional Approval TIM CHRISTENSEN
Deputy Wood Construction 8/27/2020 Conditional Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Conditional Approval TIM CHRISTENSEN
Deputy Steel/Welding 10/29/2020 Conditional Approval TIM CHRISTENSEN
Structural Steel Frame 11/2/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 3/26/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 3/26/2021 Corrections Issued JUAN VALENZUELA
Smoke Detectors 3/30/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 3/30/2021 Not Ready for Inspection JUAN VALENZUELA
Structural Steel Frame 4/7/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 4/20/2021 Not Ready for Inspection PIERRE VEGA
Shower Pan 4/28/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 4/29/2021 Partial Approval PIERRE VEGA
PLUMBING-Rough 5/5/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 5/7/2021 Conditional Approval JUAN VALENZUELA
Green Building Rough 5/10/2021 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 5/11/2021 Approved JUAN VALENZUELA
Underground Mechanical 5/11/2021 Partial Approval JUAN VALENZUELA
Sewer 5/13/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 5/19/2021 Corrections Issued KENNETH NAGLE
Green Building Rough 5/19/2021 Not Ready for Inspection KENNETH NAGLE
Verify Sprinkler Sign Off 5/19/2021 Not Ready for Inspection KENNETH NAGLE
Sewer 5/21/2021 Approved JUAN VALENZUELA
Underground Mechanical 5/21/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 5/26/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/28/2021 Conditional Approval JUAN VALENZUELA
Green Building Rough 5/28/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 5/28/2021 Approved JUAN VALENZUELA
Insulation 6/1/2021 Approved JUAN VALENZUELA
Drywall Nailing 6/8/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 6/17/2021 Partial Approval JUAN VALENZUELA
Shower Pan 9/3/2021 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 9/7/2021 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 9/9/2021 Approved JAVIER RAMOS JR
Deputy Steel/Welding 10/22/2021 Conditional Approval DANIEL ORRANTE
ELECTRICAL-Rough 4/4/2022 Approved BRENDAN LOONEY
Underground Mechanical 5/19/2022 Partial Approval JUAN VALENZUELA
HVAC-Final 7/13/2022 Not Ready for Inspection JUAN VALENZUELA
Special/Order Compliance 1/17/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 1/17/2023 Partial Approval KEVIN SARGSYAN
HVAC-Final 3/1/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/6/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 3/6/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/9/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/15/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 3/15/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/16/2023 Corrections Issued KEVIN SARGSYAN
Smoke Detectors 3/16/2023 Approved KEVIN SARGSYAN
Special/Order Compliance 3/21/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 3/30/2023 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 4/4/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/21/2023 Approved KEVIN SARGSYAN
Final 4/21/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/21/2023 Approved KEVIN SARGSYAN
Green Building Final 4/21/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/21/2023 Approved KEVIN SARGSYAN
Final 4/25/2023 OK to Issue CofO KEVIN SARGSYAN