1309 E PALMS BLVD 90291

Certificate Information: 1309 E PALMS BLVD 90291

Application / Permit
18010-30000-05952
Plan Check / Job No.
B18WL07766
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/2/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2018 APPLICANT
Assigned to Plan Check Engineer 1/9/2019 ERWIN PASCUA
Corrections Issued 1/17/2019 ERWIN PASCUA
Quality Review Completed 1/23/2019 MARJAN SHENASI
Building Plans Picked Up 1/23/2019 APPLICANT
Green Plans Picked Up 3/13/2019 APPLICANT
Applicant returned to address corrections 4/19/2019 ERWIN PASCUA
Applicant returned to address corrections 6/25/2019 ERWIN PASCUA
Plan Check Approved 6/26/2019 ERWIN PASCUA
Issued 8/2/2019 LADBS
CofO in Progress 12/8/2023 HERBERT GIRON
Permit Finaled 12/16/2023 DANIEL ORRANTE
CofO Issued 12/16/2023 DANIEL ORRANTE
Permit Finaled 12/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 2/6/2019 NOAH MCCOY
CPC Cleared 2/6/2019 NOAH MCCOY
Miscellaneous Cleared 2/6/2019 NOAH MCCOY
Miscellaneous Cleared 2/6/2019 NOAH MCCOY
Miscellaneous Cleared 2/6/2019 NOAH MCCOY
Miscellaneous Cleared 2/6/2019 NOAH MCCOY
ZA Case Cleared 2/6/2019 NOAH MCCOY
Address approval Cleared 2/7/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 2/7/2019 ROBERT DUFF
Permit Cleared 2/7/2019 ELENA LOPEZ
Low Impact Development Cleared 5/1/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/1/2019 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 6/5/2019 CHRISTOPHER LAW
Sewer availability Cleared 6/5/2019 CHRISTOPHER LAW
Green Code Cleared 6/13/2019 RICHARD GARCIA
GPI Written Notices Cleared 6/25/2019 ERWIN PASCUA
Grading Pre-Inspection Cleared 6/25/2019 ERWIN PASCUA
Trees in Parkway Cleared 6/26/2019 ADRIAN SANCHEZ

Contact Information

Architect , ; Lic. No.: C37422 12927 GREENE AVE      LOS ANGELES CA 90066,
Contractor Gaia Construction Inc; Lic. No.: 912485-B 2800 GLENDON AVENUE      LOS ANGELES, CA 90064
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/5/2019 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 11/5/2019 Corrections Issued DAVID HEINE
Grounding or Bonding 11/5/2019 Partial Approval DAVID HEINE
Underground Mechanical 11/5/2019 Corrections Issued DAVID HEINE
Excavation/Setback/Form/Re-Bar 11/8/2019 Partial Approval DAVID HEINE
Footing/Foundation/Slab 11/8/2019 Partial Approval DAVID HEINE
Underground Mechanical 11/8/2019 Partial Approval DAVID HEINE
Footing/Foundation/Slab 11/19/2019 Partial Approval DAVID HEINE
Reinforced Concrete Frame 11/19/2019 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 12/12/2019 Approved DAVID HEINE
Deputy Wood Construction 12/12/2019 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/6/2020 Partial Approval DAVID HEINE
Underground Mechanical 2/25/2020 Partial Approval DAVID HEINE
Pre-Inspection 7/9/2020 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 7/9/2020 Approved MATTHEW NUCKOLLS
HVAC-Rough 8/26/2020 Approved DAVID HEINE
PLUMBING-Rough 9/24/2020 Corrections Issued DAVID HEINE
PLUMBING-Rough 9/25/2020 Approved DAVID HEINE
ELECTRICAL-Rough 10/2/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 11/4/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 3/30/2021 Approved JOHNNY MIRANDA
Green Building Rough 3/30/2021 Approved JOHNNY MIRANDA
Structural Steel Frame 3/30/2021 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 3/30/2021 Approved JOHNNY MIRANDA
Insulation 4/8/2021 Approved JOHNNY MIRANDA
Drywall Nailing 4/16/2021 Approved JOHNNY MIRANDA
Shower Pan 4/16/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 4/30/2021 Partial Inspection JOHNNY MIRANDA
Deputy Reinf. Concrete 5/4/2021 Conditional Approval JOHNNY MIRANDA
Pre-Inspection 5/17/2021 Approved JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 6/11/2021 Partial Approval PIERRE VEGA
Wood Frame 6/11/2021 Partial Approval PIERRE VEGA
Interior/Exterior Lathing 7/22/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/30/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 9/7/2021 Partial Approval JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 11/22/2021 Approved DAVID FEILER
Sewer 3/7/2022 Partial Approval DAVID FEILER
Sewer 3/14/2022 Partial Approval JESUS RODRIGUEZ
Sewer 6/20/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/5/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 8/9/2022 Corrections Issued DAVID FEILER
HVAC-Final 8/10/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 8/12/2022 Approved DAVID FEILER
PLUMBING-Final 8/12/2022 Approved DAVID FEILER
HVAC-Final 8/22/2022 Partial Approval DAVID FEILER
Final 8/29/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 8/29/2022 Approved DAVID FEILER
Green Building Final 8/29/2022 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Approved DAVID FEILER
Service/Power Release 8/29/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 8/29/2022 Approved DAVID FEILER
Special/Order Compliance 1/20/2023 Corrections Issued MICHAEL PELHAM
Final 2/24/2023 Corrections Issued EVAN COOPER
Green Building Final 2/24/2023 Not Ready for Inspection EVAN COOPER
Service/Power Release 2/24/2023 Not Ready for Inspection EVAN COOPER
Final 3/16/2023 Not Ready for Inspection EVAN COOPER
Green Building Final 3/16/2023 Not Ready for Inspection EVAN COOPER
Service/Power Release 3/16/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Approved JESUS RODRIGUEZ
HVAC-Final 7/6/2023 Corrections Issued EVAN COOPER
Gas Test 10/26/2023 Corrections Issued HERBERT GIRON
HVAC-Final 10/26/2023 Approved HERBERT GIRON
PLUMBING-Final 10/26/2023 Approved HERBERT GIRON
Gas Test 10/30/2023 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 10/30/2023 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 10/31/2023 Approved TEMISTOCLES CAAL
Final 11/28/2023 Corrections Issued HERBERT GIRON
Green Building Final 11/28/2023 Approved HERBERT GIRON
Service/Power Release 11/28/2023 Not Ready for Inspection HERBERT GIRON
Final 12/7/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 12/7/2023 Approved HERBERT GIRON