468 E 41ST ST 90011

Certificate Information: 468 E 41ST ST 90011

Application / Permit
18010-30000-05927
Plan Check / Job No.
B18WL07752
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY TYPE VB SINGLE FAMILI DWELLING EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 3/7/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 SERGIO SILVA
Corrections Issued 1/10/2019 SERGIO SILVA
Quality Review Completed 1/17/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/18/2019 APPLICANT
Green Plans Picked Up 1/18/2019 APPLICANT
Applicant returned to address corrections 3/4/2019 SERGIO SILVA
Plan Check Approved 3/7/2019 SERGIO SILVA
Issued 3/7/2019 LADBS
CofO in Progress 4/9/2021 ROBERT MCDOWELL
Permit Finaled 4/20/2021 DEROLD HAUFF
CofO Issued 4/20/2021 DEROLD HAUFF
Permit Finaled 4/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/22/2019 KARAN PATEL
Permit Cleared 1/22/2019 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 1/29/2019 KAREN LE
Sewer availability Cleared 1/29/2019 KAREN LE
Trees in Parkway Cleared 1/31/2019 JOHN KIM
Green Code Cleared 2/15/2019 DONALD CRICHLOW
Green Code Cleared 2/15/2019 RICHARD GARCIA
Hydrant and Access approval Cleared 2/19/2019 ROBERT DUFF
Low Impact Development Cleared 2/22/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/22/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/11/2019 Approved ROBERT MCDOWELL
Underground Mechanical 3/11/2019 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/12/2019 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 3/12/2019 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/2/2019 Partial Approval ALEJANDRO DE ARTOLA
Sewer 4/8/2019 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/15/2019 Not Ready for Inspection ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/17/2019 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Partial Approval VICTOR PUKHALSKY
PLUMBING-Rough 6/5/2019 Not Ready for Inspection VICTOR PUKHALSKY
Deputy Wood Construction 6/6/2019 Partial Approval VICTOR PUKHALSKY
Interior/Exterior Lathing 6/15/2019 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 6/15/2019 No Access for Inspection FREDDIE RIVERA
PLUMBING-Rough 6/19/2019 Not Ready for Inspection VICTOR PUKHALSKY
HVAC-Rough 12/10/2019 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 12/16/2019 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 12/16/2019 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 12/19/2019 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 12/19/2019 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 12/26/2019 No Access for Inspection JOSEPH MCGARRY
PLUMBING-Rough 12/26/2019 No Access for Inspection JOSEPH MCGARRY
Insulation 6/16/2020 Approved SABAS ALONSO
Drywall Nailing 6/19/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/14/2020 Approved SABAS ALONSO
Shower Pan 7/14/2020 Corrections Issued SABAS ALONSO
Shower Pan 7/23/2020 Not Ready for Inspection SABAS ALONSO
Shower Pan 7/28/2020 Approved SABAS ALONSO
Underground Mechanical 8/4/2020 Approved ENRIQUE MIRELES
Gas Test 8/19/2020 Approved ROBERT MCDOWELL
Service/Power Release 8/19/2020 Not Ready for Inspection ROBERT MCDOWELL
Service/Power Release 8/21/2020 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 8/27/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 10/6/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 10/6/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
ELECTRICAL-Final 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
Final 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
Green Building Final 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
Green Building Rough 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
HVAC-Final 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
PLUMBING-Final 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Not Ready DONALD CRICHLOW
Service/Power Release 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
Smoke Detectors 10/16/2020 Not Ready for Inspection DONALD CRICHLOW
Verify Sprinkler Sign Off 10/16/2020 Approved DONALD CRICHLOW
ELECTRICAL-Final 10/21/2020 Corrections Issued DONALD CRICHLOW
HVAC-Final 10/21/2020 Corrections Issued DONALD CRICHLOW
PLUMBING-Final 10/21/2020 Corrections Issued DONALD CRICHLOW
BUILDING-Rough-Frame 11/4/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 11/4/2020 Approved SCOTT FINNILA
Final 11/4/2020 Corrections Issued SCOTT FINNILA
Green Building Final 11/4/2020 Approved SCOTT FINNILA
Green Building Rough 11/4/2020 Approved SCOTT FINNILA
HVAC-Final 11/4/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Final 11/4/2020 Partial Approval SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 11/4/2020 Corrections Issued SCOTT FINNILA
Smoke Detectors 11/4/2020 Approved SCOTT FINNILA
Final 11/17/2020 Corrections Issued ROBERT MCDOWELL
HVAC-Final 11/17/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Not Ready ROBERT MCDOWELL
Service/Power Release 11/17/2020 Approved ROBERT MCDOWELL
Final 12/18/2020 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved OSVALDO PARAMO
Final 4/9/2021 OK to Issue CofO ROBERT MCDOWELL