11771 E BELLAGIO ROAD 90049
Certificate Information: 11771 E BELLAGIO ROAD 90049
- Application / Permit
- 18010-30000-05887
- Plan Check / Job No.
- B18WL07707
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- LOT 5: NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER SMALL LOT SUBDIVISION PER VTT-72465-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | ERWIN PASCUA |
| Corrections Issued | 1/15/2019 | ERWIN PASCUA |
| Quality Review Completed | 1/23/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 2/6/2019 | APPLICANT |
| Applicant returned to address corrections | 8/30/2019 | ERWIN PASCUA |
| Green Plans Picked Up | 9/12/2019 | APPLICANT |
| Applicant returned to address corrections | 9/20/2019 | ERWIN PASCUA |
| Applicant returned to address corrections | 10/1/2019 | ERWIN PASCUA |
| Applicant returned to address corrections | 11/20/2020 | ERWIN PASCUA |
| Applicant returned to address corrections | 6/22/2021 | ERWIN PASCUA |
| Plan Check Approved | 7/2/2021 | ERWIN PASCUA |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 10/22/2024 | CARLOS MATAMOROS |
| CofO Issued | 10/26/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/26/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2019 | JOSE CRUZ RODRIGUEZ |
| CPC | Cleared | 3/11/2019 | NOAH MCCOY |
| CPC | Cleared | 3/11/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2019 | JOSE CRUZ RODRIGUEZ |
| Hydrant and Access approval | Cleared | 3/11/2019 | ROBERT DUFF |
| Sewer availability | Cleared | 3/11/2019 | JOSE CRUZ RODRIGUEZ |
| ZA Case | Cleared | 3/11/2019 | NOAH MCCOY |
| Low Impact Development | Cleared | 8/7/2019 | JORGE MEJIA LEMUS |
| "Q" conditions | Cleared | 8/16/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 8/16/2019 | NOAH MCCOY |
| GPI Written Notices | Cleared | 8/30/2019 | ERWIN PASCUA |
| Grading Pre-Inspection | Cleared | 8/30/2019 | ERWIN PASCUA |
| Green Code | Cleared | 11/6/2019 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 9/4/2020 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 10/5/2020 | KATHLEEN LEE |
| Permit | Cleared | 10/5/2020 | KATHLEEN LEE |
| Trees in Parkway | Cleared | 11/9/2020 | JOHN KIM |
Contact Information
| Architect | Ashofteh,, Farhad; Lic. No.: C19728 | 833 HAVERFORD AVENUE PACIFIC PALISADES, CA 90272 |
| Contractor | Daniel S D Construction Inc; Lic. No.: 657391-B | 2934 BEVERLY GLEN CIRCLE #357 LOS ANGELES, CA 90077 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Chang,, Paul Pao-Lin; Lic. No.: GE2181 | 1529 ELKWOOD DR WEST COVINA, CA 91791 |
| Engineer | Chen,, Shaofu; Lic. No.: C76834 | 5589 CARMELLO COURT RANCHO CUCAMONGA, CA 91739 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2022 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/11/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/21/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 3/22/2022 | Conditional Approval | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 3/22/2022 | Approved | BRENDAN LOONEY |
| Deputy Steel/Welding | 4/8/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/11/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/12/2022 | Approved | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/14/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/21/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/22/2022 | Approved | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/26/2022 | Approved | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/26/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 5/4/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 5/9/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/11/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/12/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/13/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 6/1/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 6/10/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 6/16/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 6/16/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 7/8/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 7/21/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 7/21/2022 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/28/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/4/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 1/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 1/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 1/18/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/26/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 2/22/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 3/1/2023 | Conditional Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 3/2/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 3/29/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 4/5/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/5/2023 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 4/5/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/5/2023 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 4/5/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/19/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/25/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 5/3/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 5/3/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 5/18/2023 | Approved | CARLOS MATAMOROS |
| Sewer | 10/16/2023 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 10/24/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/25/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/1/2024 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 2/2/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 2/9/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/9/2024 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 2/12/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/8/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/26/2024 | Approved | CARLOS MATAMOROS |
| Final | 10/16/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/16/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 10/16/2024 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 10/16/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 10/16/2024 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 10/16/2024 | Approved | CARLOS MATAMOROS |
| Final | 10/22/2024 | OK to Issue CofO | CARLOS MATAMOROS |