2315 S BEVERWIL DR 90034

Certificate Information: 2315 S BEVERWIL DR 90034

Application / Permit
18010-30000-05536
Plan Check / Job No.
B18WL07321
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) S.F.R. TWO STORY WITH A BASEMENT, ATTACHED GARAGE, AND OPEN PATIO
Permit Issued
Issued on 2/10/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 12/10/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 12/13/2018 CORA JOHNSON
Green Plans Picked Up 5/7/2019 APPLICANT
Applicant returned to address corrections 5/16/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/8/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/17/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/13/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/10/2020 KAMRAN GHOTBI RAVANDI
Issued 2/10/2020 LADBS
Building Plans Picked Up 3/31/2022 APPLICANT
CofO in Progress 11/21/2022 OGANES TARAKHCHYAN
Permit Finaled 12/17/2022 DANIEL ORRANTE
CofO Issued 12/17/2022 DANIEL ORRANTE
Permit Finaled 12/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 5/1/2019 MARTIN FRAGOSO
Permit Cleared 5/1/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 5/1/2019 ERIK BEASLEY
Trees in Parkway Cleared 5/3/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/6/2019 CELINA MORENO
Sewer availability Cleared 5/6/2019 CELINA MORENO
Hydrant and Access approval Cleared 6/3/2019 GILBERT URREA
Green Code Cleared 7/2/2019 RICHARD GARCIA
Certificate of Compliance Cleared 9/10/2019 SARAH GOLDMAN
Excavation more than 5-ft deep Cleared 2/10/2020 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2020 Partial Inspection RONALD WEBER
FLOOD-Elevation Certificate 5/26/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 5/26/2020 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 5/26/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 5/26/2020 Not Ready for Inspection KEVIN SARGSYAN
FLOOD-Elevation Certificate 5/29/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 5/29/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 5/29/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 5/29/2020 Not Ready for Inspection KEVIN SARGSYAN
Special/Order Compliance 5/29/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 6/23/2020 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 7/23/2020 Conditional Approval KEVIN SARGSYAN
FLOOD-Elevation Certificate 7/28/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/28/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 7/28/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 7/28/2020 Not Ready for Inspection KEVIN SARGSYAN
Deputy Other (see comments) 7/30/2020 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 7/30/2020 Conditional Approval KEVIN SARGSYAN
FLOOD-Elevation Certificate 8/4/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/4/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 8/4/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 8/4/2020 Not Ready for Inspection KEVIN SARGSYAN
FLOOD-Elevation Certificate 8/28/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/28/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 8/28/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 8/28/2020 Not Ready for Inspection KEVIN SARGSYAN
Deputy Reinf. Concrete 9/1/2020 Conditional Approval KEVIN SARGSYAN
FLOOD-Elevation Certificate 9/9/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 9/9/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 9/9/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 9/9/2020 No Access for Inspection KEVIN SARGSYAN
PLUMBING-Rough 9/25/2020 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 9/29/2020 No Access for Inspection KENNETH NAGLE
METHANE-Rough 10/1/2020 Partial Approval KEVIN SARGSYAN
Underground Mechanical 10/1/2020 Not Ready for Inspection KEVIN SARGSYAN
Deputy Methane Barrier 10/21/2020 Conditional Approval KEVIN SARGSYAN
Deputy Methane Barrier 10/22/2020 Conditional Approval KEVIN SARGSYAN
Deputy Methane Barrier 10/23/2020 No Access for Inspection KENNETH NAGLE
METHANE-Barrier 10/23/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 11/2/2020 No Access for Inspection KEVIN SARGSYAN
METHANE-Subgrade 11/2/2020 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/5/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/5/2020 Partial Approval KEVIN SARGSYAN
METHANE-Subgrade 11/5/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/24/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 11/24/2020 Not Ready for Inspection KEVIN SARGSYAN
Underground Mechanical 11/24/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 12/1/2020 Corrections Issued KEVIN SARGSYAN
METHANE-Subgrade 12/1/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 12/1/2020 Partial Approval KEVIN SARGSYAN
Pre-Inspection 12/3/2020 Partial Approval KEVIN SARGSYAN
METHANE-Subgrade 12/8/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 12/11/2020 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/15/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 2/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/23/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Partial Approval KEVIN SARGSYAN
HVAC-Rough 3/22/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Approved KEVIN SARGSYAN
HVAC-Rough 4/9/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 4/19/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 4/22/2021 Approved KEVIN SARGSYAN
METHANE-Rough 5/3/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 5/3/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 5/17/2021 Approved KEVIN SARGSYAN
Green Building Rough 6/9/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/9/2021 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 6/14/2021 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 6/14/2021 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 6/14/2021 Approved KEVIN SARGSYAN
Insulation 6/21/2021 Approved KEVIN SARGSYAN
Drywall Nailing 7/15/2021 Approved KEVIN SARGSYAN
Shower Pan 7/15/2021 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 7/16/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/7/2021 Approved SHAVONNE ESPINOZA
Sewer 10/7/2021 Approved KRISTEN BEVERIDGE
Verify Rec and Parks Fee Memo 10/12/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/24/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 3/8/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 3/8/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 3/11/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 3/11/2022 Approved KEVIN SARGSYAN
HVAC-Final 3/15/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/18/2022 Approved KEVIN SARGSYAN
Service/Power Release 10/12/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Final 10/18/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 11/3/2022 Approved OGANES TARAKHCHYAN
Final 11/8/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/8/2022 Approved OGANES TARAKHCHYAN
Green Building Final 11/8/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 11/8/2022 Approved OGANES TARAKHCHYAN
Gas Test 11/14/2022 Approved OGANES TARAKHCHYAN
Final 11/18/2022 OK to Issue CofO OGANES TARAKHCHYAN