3240 N IREDELL LANE 91604
Certificate Information: 3240 N IREDELL LANE 91604
- Application / Permit
- 18010-30000-05392
- Plan Check / Job No.
- B18WL07062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW ACCESSORY LIVING QUARTERS. TYPE VB FULLY SPRINKLERED.
- Permit Issued
- Issued on 7/16/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/16/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2018 | APPLICANT |
| Green Plans Picked Up | 11/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2018 | RICARDO RAMIREZ |
| Corrections Issued | 11/26/2018 | RICARDO RAMIREZ |
| Quality Review Completed | 12/5/2018 | MARJAN SHENASI |
| Building Plans Picked Up | 12/6/2018 | APPLICANT |
| Applicant returned to address corrections | 2/4/2019 | RICARDO RAMIREZ |
| Plan Check Approved | 7/9/2019 | RICARDO RAMIREZ |
| Issued | 7/16/2019 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/15/2019 | JOHN DALLAS |
| Green Code | Cleared | 2/28/2019 | DONALD CRICHLOW |
| BHO/Hillside ordinance | Cleared | 3/8/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/8/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/8/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 3/8/2019 | RYAN HUDSON |
| Permit | Cleared | 3/8/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 3/8/2019 | ELAINE LEI |
| Sewer availability | Cleared | 3/8/2019 | ELAINE LEI |
| ZA Case | Cleared | 3/12/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 7/2/2019 | TREVOR MARTIN |
| Specific Plan | Cleared | 7/2/2019 | TREVOR MARTIN |
| GPI Written Notices | Cleared | 7/9/2019 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 7/9/2019 | RICARDO RAMIREZ |
Contact Information
| Architect | Rigo, De Righi, Fabio N; Lic. No.: C27735 | 10956 WEYBURN AVE. #210 LOS ANGELES, CA 90024 |
| Contractor | Albino Construction Inc; Lic. No.: 477121-B | 12568 W WASHINGTON BLVD SUITE 200 LOS ANGELES, CA 90066 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/22/2019 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 9/23/2019 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 11/13/2019 | Partial Approval | RAYMOND KEHOE |
| Reinforced Concrete Frame | 11/19/2019 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 12/12/2019 | Partial Approval | RAYMOND KEHOE |
| Reinforced Concrete Frame | 12/23/2019 | Partial Approval | RAYMOND KEHOE |
| Reinforced Concrete Frame | 2/21/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/28/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/16/2020 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 4/2/2020 | Conditional Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 4/24/2020 | Approved | TROY SANDERS |
| Reinforced Concrete Frame | 5/28/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 7/30/2020 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/30/2020 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 7/30/2020 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/3/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 9/3/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/27/2021 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 7/29/2021 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 8/23/2021 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/8/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 11/8/2021 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 11/8/2021 | Approved | ARAM AVEDISIAN |
| Final | 7/5/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 7/5/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/5/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/5/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 7/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/14/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/14/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/22/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/22/2022 | Approved | CHRISTOPHE COCHRAN |