3688 S OVERLAND AVE 90034

Certificate Information: 3688 S OVERLAND AVE 90034

Application / Permit
18010-30000-05373
Plan Check / Job No.
B18WL07027
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New privately funded TOC Tier 3 project of an 8-story 138 unit apartment building (14 of the units to be Extremely Low Income) with commercial on frst floor over garage.
Permit Issued
Issued on 1/26/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2018 APPLICANT
Assigned to Plan Check Engineer 11/21/2018 MANUEL GARCIA
Corrections Issued 11/27/2018 MANUEL GARCIA
Quality Review Completed 12/6/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/4/2019 MANUEL GARCIA
Applicant returned to address corrections 7/8/2019 MANUEL GARCIA
Applicant returned to address corrections 9/18/2019 MANUEL GARCIA
Applicant returned to address corrections 12/4/2019 MANUEL GARCIA
Applicant returned to address corrections 1/8/2020 MANUEL GARCIA
Applicant returned to address corrections 1/17/2020 MANUEL GARCIA
Applicant returned to address corrections 1/29/2020 MANUEL GARCIA
Applicant returned to address corrections 2/25/2020 MANUEL GARCIA
Applicant returned to address corrections 1/14/2021 MANUEL GARCIA
Plan Check Approved 1/15/2021 MANUEL GARCIA
Issued 1/26/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
TCO Issued (Expire Date: 04-22-2024) 10/25/2023 DAVID TSAU
CofO in Progress 12/14/2023 DAVID TSAU
Permit Finaled 12/14/2023 DAVID TSAU
CofO Issued 12/14/2023 DAVID TSAU
Permit Finaled 12/14/2023 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 9/18/2019 JENNY CEA
Eng Process Fee Ord 176,300 Cleared 9/18/2019 JENNY CEA
Hydrant and Access approval Cleared 11/13/2019 JEREMY CARTER
GPI Written Notices Cleared 12/4/2019 MANUEL GARCIA
Grading Pre-Inspection Cleared 12/4/2019 MANUEL GARCIA
Certificate of Compliance Cleared 12/18/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 12/18/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 12/18/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 12/18/2019 SOPHIE GABEL-SCHEINBAU
Low Impact Development Cleared 12/26/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/26/2019 ERIK BEASLEY
Building over 3-story or 36-ft Cleared 1/17/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/17/2020 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 2/11/2020 MICHAEL ZIRBES
Fire Marshall Fire Life Safety Cleared 2/13/2020 VIDAL GARCIA
Comm Cor/Mini-Mall Cleared 2/19/2020 SARAH GOLDMAN
Comm Cor/Mini-Mall Cleared 2/19/2020 SARAH GOLDMAN
Frnt yard landscape/Water mgmt Cleared 2/19/2020 SARAH GOLDMAN
Miscellaneous Cleared 2/19/2020 SARAH GOLDMAN
Miscellaneous Cleared 2/19/2020 SARAH GOLDMAN
Miscellaneous Cleared 2/19/2020 SARAH GOLDMAN
Opn space landscape/Water mgmt Cleared 2/19/2020 SARAH GOLDMAN
Site Plan review Cleared 2/19/2020 SARAH GOLDMAN
Miscellaneous Cleared 2/21/2020 TRACY TATE
Construction near power lines Cleared 2/26/2020 ERNEST FRESQUEZ
Specific Plan Cleared 2/27/2020 FREDDY GARCIA
DAS Clearance Cleared 2/28/2020 SOMKIAT SUPANYACHOTSKUL
Green Code Cleared 3/3/2020 RICHARD GARCIA
Sewer availability Cleared 3/6/2020 CELINA MORENO
Work Adjacent to Public Way Cleared 7/23/2020 SAUL GARCIA
Trees in Parkway Cleared 8/25/2020 JOHN KIM
Permit Cleared 12/15/2020 MAHELET GEBEYHU
Highway dedication Cleared 12/17/2020 RAYMOND MUGAMBWA

Contact Information

Architect Reed,, John G; Lic. No.: C14523 657 ROSE AVENUE      VENICE, CA 90291
Contractor Oakmont Capital; Lic. No.: 1004478-B 8721 SANTA MONICA BLVD STE 224      LOS ANGELES, CA 90069
Engineer Benichou,, Ety; Lic. No.: S5263 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2021 Approved JEFF BYTHEWAY
Special/Order Compliance 1/28/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/6/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/6/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/7/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/13/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/13/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/14/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/15/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 4/15/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 4/19/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/20/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 4/21/2021 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 4/22/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 4/22/2021 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 4/22/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 4/23/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 4/23/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 4/26/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/27/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/27/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 4/29/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/29/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/3/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/4/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/5/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/7/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 5/10/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/10/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/11/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 5/12/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/17/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/17/2021 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 5/17/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/18/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/28/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 5/28/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/2/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/2/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 6/4/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 6/5/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/7/2021 Approved TED RIES
Deputy Reinf. Masonry 6/7/2021 Approved TED RIES
Deputy Shotcrete 6/7/2021 Approved TED RIES
Piling/Pier/Caisson 6/7/2021 Partial Approval TED RIES
Reinforced Concrete Frame 6/7/2021 Partial Approval TED RIES
Deputy Reinf. Masonry 6/8/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/9/2021 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 6/10/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/10/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/10/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/15/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/15/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/15/2021 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 6/15/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 6/15/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 6/16/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 6/16/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 6/17/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/18/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/18/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 6/18/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 6/18/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 6/21/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/21/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/22/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/23/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 6/24/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 6/24/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 6/24/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 6/25/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/7/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/9/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 7/9/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/13/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/15/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/16/2021 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 7/16/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 7/19/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 7/19/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 7/19/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 7/20/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 7/20/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 7/20/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/21/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 7/21/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 7/22/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 7/22/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 7/22/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/23/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/23/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 7/23/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/27/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/27/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/28/2021 Conditional Approval TED RIES
Deputy Reinf. Masonry 7/28/2021 Conditional Approval TED RIES
Reinforced Masonry Frame 7/28/2021 Partial Approval TED RIES
Deputy Reinf. Masonry 7/29/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 7/30/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 7/30/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 8/2/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/2/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 8/3/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/4/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/4/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 8/5/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 8/6/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/6/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 8/6/2021 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 8/9/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/10/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 8/11/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/11/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/13/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/17/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 8/17/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 8/18/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 8/19/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/19/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 8/19/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/19/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 8/19/2021 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 8/20/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 8/20/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/23/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/25/2021 Conditional Approval JONATHAN ALLEN
Deputy Reinf. Concrete 8/26/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 8/26/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/26/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/31/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/31/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/2/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/10/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/13/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 9/13/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/14/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 9/14/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/15/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 9/15/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 9/16/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/17/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 9/21/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/22/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 9/22/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 9/22/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 9/27/2021 Conditional Approval TED RIES
Reinforced Concrete Frame 9/27/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/28/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 9/28/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 10/5/2021 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 10/5/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 10/6/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/7/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/13/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/14/2021 Conditional Approval TED RIES
Reinforced Concrete Frame 10/14/2021 Partial Inspection TED RIES
Deputy Reinf. Concrete 10/18/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/21/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 10/21/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 10/22/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 10/22/2021 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 10/25/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 10/26/2021 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/19/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 11/22/2021 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/23/2021 Approved JEFF BYTHEWAY
Deputy Wood Construction 11/24/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 12/17/2021 Approved NICK LAROCCA
Deputy Wood Construction 12/20/2021 Approved JEFF BYTHEWAY
Deputy Wood Construction 12/21/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 12/22/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 12/23/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 1/6/2022 Conditional Approval JOHN DODGE
Deputy Wood Construction 1/7/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/20/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/21/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 1/26/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 1/27/2022 Approved JEFF BYTHEWAY
Insulation 1/27/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Wood Construction 1/28/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/7/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/8/2022 Approved DERRICK SPENCER
Deputy Wood Construction 2/9/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/10/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 2/11/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/22/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 2/23/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/24/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/25/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/2/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/3/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/4/2022 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 3/22/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/23/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/24/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/25/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 3/30/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 3/31/2022 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/1/2022 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 5/3/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 5/4/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 5/5/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 5/6/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Wood Construction 5/17/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval JEFF BYTHEWAY
Insulation 5/17/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 5/18/2022 Approved JEFF BYTHEWAY
Drywall Nailing 5/18/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 5/19/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 5/20/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval JEFF BYTHEWAY
Wood Frame 5/24/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Partial Approval ALAN NOVAK
Deputy Wood Construction 6/1/2022 Conditional Approval DAVID TSAU
Deputy Wood Construction 6/2/2022 Approved JEFF BYTHEWAY
Wood Frame 6/2/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 6/3/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 6/7/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/8/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/9/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/10/2022 Approved JEFF BYTHEWAY
Insulation 6/10/2022 Partial Inspection JEFF BYTHEWAY
Deputy Wood Construction 6/14/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 6/15/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/16/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/17/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/21/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 6/22/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 6/23/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Wood Construction 6/24/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 7/11/2022 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Wood Construction 7/12/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 7/13/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 7/14/2022 Approved JEFF BYTHEWAY
Deputy Wood Construction 7/15/2022 Approved JEFF BYTHEWAY
Drywall Nailing 7/19/2022 Partial Approval SORIN CIRSTOIU
Insulation 7/22/2022 Partial Approval DERRICK SPENCER
Insulation 7/29/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 8/2/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/3/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/4/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/12/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 8/15/2022 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 8/16/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 9/1/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/6/2022 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 9/7/2022 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/13/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 9/16/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 9/23/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 10/7/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 10/19/2022 Partial Approval DAVID TSAU
Interior/Exterior Lathing 11/3/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 12/16/2022 Partial Approval DERRICK SPENCER
Structural Steel Frame 2/21/2023 Approved DERRICK SPENCER
Final 8/15/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 8/15/2023 Approved DERRICK SPENCER
Reinforced Masonry Frame 8/15/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Approved DERRICK SPENCER
Smoke Detectors 8/15/2023 Approved DERRICK SPENCER
Final 8/22/2023 Not Ready for Inspection DERRICK SPENCER
Final 9/6/2023 Not Ready for Inspection DERRICK SPENCER
Final 9/15/2023 Not Ready for Inspection DERRICK SPENCER
Final 10/16/2023 Not Ready for Inspection DERRICK SPENCER
Final 10/24/2023 Not Ready for Inspection DERRICK SPENCER
Final 11/29/2023 OK to Issue CofO DERRICK SPENCER