8602 N PENFIELD AVE 91306

Certificate Information: 8602 N PENFIELD AVE 91306

Application / Permit
18010-30000-05320
Plan Check / Job No.
B18WL06960
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229 IN REAR OF THE LOT.
Permit Issued
Issued on 3/3/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 REZA HAGHIGHAT
Corrections Issued 11/19/2018 REZA HAGHIGHAT
Quality Review Completed 11/29/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/29/2018 APPLICANT
Green Plans Picked Up 11/30/2018 APPLICANT
Plan Check Approved 4/22/2019 REZA HAGHIGHAT
Plan Check Approved 4/22/2019 REZA HAGHIGHAT
Issued 3/3/2020 LADBS
CofO in Progress 2/26/2022 JEFFREY PARD
Permit Finaled 2/28/2022 JOHN JANSON
CofO Issued 2/28/2022 JOHN JANSON
Permit Finaled 2/28/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/7/2018 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 12/7/2018 PHILLIP WILSON
Roof/Waste drainage to street Cleared 12/7/2018 PHILLIP WILSON
Sewer availability Cleared 12/7/2018 PHILLIP WILSON
Hydrant and Access approval Cleared 12/11/2018 GILBERT URREA
Green Code Cleared 12/13/2018 DONALD CRICHLOW
Low Impact Development Cleared 12/14/2018 JORGE MEJIA LEMUS
Construction near power lines Cleared 4/13/2019 WALTER RAMIREZ

Contact Information

Contractor Mateo'S Painting; Lic. No.: 1050294-B 6355 DE SOTO AVE #A426      WOODLAND HILLS, CA 91367
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2020 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 3/31/2020 Not Ready for Inspection DAVID SCANTLIN
Piling/Pier/Caisson 3/31/2020 Not Ready for Inspection DAVID SCANTLIN
Pre-Inspection 3/31/2020 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 4/1/2020 Corrections Issued MICHAEL TEMPLE
Piling/Pier/Caisson 4/1/2020 Not Ready for Inspection MICHAEL TEMPLE
Pre-Inspection 4/1/2020 Not Ready for Inspection MICHAEL TEMPLE
Pre-Inspection 6/18/2020 Partial Approval JEFFREY PARD
Pre-Inspection 6/23/2020 Partial Approval JEFFREY PARD
Pre-Inspection 7/23/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 9/11/2020 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 9/17/2020 Corrections Issued DONALD SUNSERI
Footing/Foundation/Slab 10/6/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Approved JEFFREY PARD
PLUMBING-Rough 1/27/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/11/2021 Corrections Issued JEFFREY PARD
Green Building Rough 5/11/2021 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 5/19/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 5/19/2021 Approved JEFFREY PARD
Green Building Rough 5/19/2021 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 5/19/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 5/19/2021 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/19/2021 Approved JEFFREY PARD
Insulation 5/25/2021 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 5/25/2021 Partial Approval DAVID SANDOVAL
Insulation 6/3/2021 Approved JEFFREY PARD
Drywall Nailing 6/11/2021 Approved JEFFREY PARD
Green Building Rough 6/11/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 7/27/2021 Not Ready for Inspection LILIANA PORTILLO
Shower Pan 7/27/2021 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 7/29/2021 Approved JEFFREY PARD
Pre-Inspection 8/12/2021 Partial Inspection DEANDRE HOFFMAN
Final 9/2/2021 Corrections Issued JEFFREY PARD
Green Building Final 9/2/2021 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Not Ready JEFFREY PARD
Service/Power Release 9/2/2021 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 9/2/2021 Corrections Issued JEFFREY PARD
Final 9/9/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 9/9/2021 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved JEFFREY PARD
Service/Power Release 9/9/2021 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 9/9/2021 Not Ready for Inspection JEFFREY PARD
Final 10/6/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 10/6/2021 Not Ready for Inspection JEFFREY PARD
Service/Power Release 10/6/2021 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 10/6/2021 Not Ready for Inspection JEFFREY PARD
Final 2/14/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 2/14/2022 Approved JEFFREY PARD
Service/Power Release 2/14/2022 Approved JEFFREY PARD
Smoke Detectors 2/14/2022 Approved JEFFREY PARD