6045 1/2 N CLEON AVE 91606
Certificate Information: 6045 1/2 N CLEON AVE 91606
- Application / Permit
- 18010-30000-04767
- Plan Check / Job No.
- B18WL06308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New two story duplex with attached two car garage (front units). Fully sprinklered Type VB.
- Permit Issued
- Issued on 3/4/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 3/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2018 | APPLICANT |
| Green Plans Picked Up | 10/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2018 | RICARDO RAMIREZ |
| Corrections Issued | 10/20/2018 | RICARDO RAMIREZ |
| Quality Review Completed | 10/25/2018 | TARIK SAOUD |
| Building Plans Picked Up | 10/26/2018 | APPLICANT |
| Plan Check Approved | 11/20/2018 | RICARDO RAMIREZ |
| Issued | 3/4/2019 | LADBS |
| CofO in Progress | 3/17/2020 | RAYMOND KEHOE |
| Permit Finaled | 3/26/2020 | MICHAEL SMITH |
| CofO Issued | 3/26/2020 | MICHAEL SMITH |
| Permit Finaled | 3/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2018 | KARAN PATEL |
| Hydrant and Access approval | Cleared | 10/26/2018 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2018 | APEKSHYA BAJRACHARYA |
| Highway dedication | Cleared | 10/29/2018 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 10/29/2018 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 10/29/2018 | APEKSHYA BAJRACHARYA |
| Trees in Parkway | Cleared | 10/29/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 11/1/2018 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 11/8/2018 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/8/2018 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Mc Construction; Lic. No.: 1028997-B | 23280 HAMLIN ST WEST HILLS, CA 91307 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/5/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Rough-Elec/Plmb/HVAC | 3/5/2019 | Partial Approval | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 3/13/2019 | Conditional Approval | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 4/8/2019 | Partial Approval | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2019 | Partial Approval | BEAU COLLINS |
| Wood Frame | 4/30/2019 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/2/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/2/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 8/2/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/2/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/12/2019 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/12/2019 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2019 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/12/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/12/2019 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/12/2019 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/12/2019 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 8/16/2019 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/21/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/21/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/21/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/27/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 8/27/2019 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/27/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/27/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/27/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/16/2019 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 9/16/2019 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/16/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/18/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/24/2019 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 9/24/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/24/2019 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/2/2019 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 10/15/2019 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Rough | 12/17/2019 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/17/2019 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/17/2019 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| ELECTRICAL-Final | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Final | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Footing/Foundation/Slab | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Gas Test | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Green Building Final | 1/30/2020 | Corrections Issued | RAYMOND KEHOE |
| HVAC-Final | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| PLUMBING-Final | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| SGSOV-Seismic Gas S/O Valve | 1/30/2020 | SGSOV Not Ready | RAYMOND KEHOE |
| Service/Power Release | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Smoke Detectors | 1/30/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| ELECTRICAL-Final | 2/6/2020 | No Access for Inspection | DANIEL ORRANTE |
| Gas Test | 2/6/2020 | No Access for Inspection | DANIEL ORRANTE |
| HVAC-Final | 2/6/2020 | No Access for Inspection | DANIEL ORRANTE |
| Service/Power Release | 2/6/2020 | No Access for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 2/7/2020 | No Access for Inspection | RAYMOND KEHOE |
| Final | 2/7/2020 | No Access for Inspection | RAYMOND KEHOE |
| Footing/Foundation/Slab | 2/7/2020 | No Access for Inspection | RAYMOND KEHOE |
| Green Building Final | 2/7/2020 | No Access for Inspection | RAYMOND KEHOE |
| PLUMBING-Final | 2/7/2020 | No Access for Inspection | RAYMOND KEHOE |
| SGSOV-Seismic Gas S/O Valve | 2/7/2020 | SGSOV Not Ready | RAYMOND KEHOE |
| Smoke Detectors | 2/7/2020 | Corrections Issued | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 2/13/2020 | Approved | DANIEL ORRANTE |
| Final | 2/13/2020 | Corrections Issued | DANIEL ORRANTE |
| Footing/Foundation/Slab | 2/13/2020 | Approved | DANIEL ORRANTE |
| Green Building Final | 2/13/2020 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 2/13/2020 | SGSOV Not Ready | DANIEL ORRANTE |
| Service/Power Release | 2/13/2020 | Approved | DANIEL ORRANTE |
| Smoke Detectors | 2/13/2020 | Approved | DANIEL ORRANTE |
| Final | 2/26/2020 | Corrections Issued | RAYMOND KEHOE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2020 | SGSOV Approved | RAYMOND KEHOE |
| ELECTRICAL-Final | 3/4/2020 | Approved | RAYMOND KEHOE |
| Final | 3/4/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| HVAC-Final | 3/4/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Final | 3/4/2020 | Approved | RAYMOND KEHOE |
| Service/Power Release | 3/4/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Final | 3/17/2020 | OK to Issue CofO | RAYMOND KEHOE |