6045 1/2 N CLEON AVE 91606

Certificate Information: 6045 1/2 N CLEON AVE 91606

Application / Permit
18010-30000-04767
Plan Check / Job No.
B18WL06308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New two story duplex with attached two car garage (front units). Fully sprinklered Type VB.
Permit Issued
Issued on 3/4/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 3/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2018 APPLICANT
Green Plans Picked Up 10/12/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 RICARDO RAMIREZ
Corrections Issued 10/20/2018 RICARDO RAMIREZ
Quality Review Completed 10/25/2018 TARIK SAOUD
Building Plans Picked Up 10/26/2018 APPLICANT
Plan Check Approved 11/20/2018 RICARDO RAMIREZ
Issued 3/4/2019 LADBS
CofO in Progress 3/17/2020 RAYMOND KEHOE
Permit Finaled 3/26/2020 MICHAEL SMITH
CofO Issued 3/26/2020 MICHAEL SMITH
Permit Finaled 3/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/26/2018 KARAN PATEL
Hydrant and Access approval Cleared 10/26/2018 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 10/29/2018 APEKSHYA BAJRACHARYA
Highway dedication Cleared 10/29/2018 APEKSHYA BAJRACHARYA
Permit Cleared 10/29/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 10/29/2018 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 10/29/2018 ADRIAN SANCHEZ
Green Code Cleared 11/1/2018 DONALD CRICHLOW
Low Impact Development Cleared 11/8/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/8/2018 ADRIAN SANCHEZ

Contact Information

Contractor Mc Construction; Lic. No.: 1028997-B 23280 HAMLIN ST      WEST HILLS, CA 91307
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2019 Not Ready for Inspection KEVIN BEAULIEU
Rough-Elec/Plmb/HVAC 3/5/2019 Partial Approval KEVIN BEAULIEU
Excavation/Setback/Form/Re-Bar 3/13/2019 Conditional Approval KEVIN BEAULIEU
BUILDING-Rough-Frame 4/8/2019 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/8/2019 Partial Approval BEAU COLLINS
Wood Frame 4/30/2019 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 8/2/2019 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 8/2/2019 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 8/2/2019 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 8/2/2019 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/12/2019 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/12/2019 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/12/2019 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/12/2019 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/12/2019 Approved MISAEL ESPARZA
PLUMBING-Rough 8/12/2019 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 8/12/2019 Approved MISAEL ESPARZA
Pre-Inspection 8/16/2019 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/21/2019 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 8/21/2019 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/21/2019 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/27/2019 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 8/27/2019 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/27/2019 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 8/27/2019 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 8/27/2019 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/27/2019 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/16/2019 Partial Approval MISAEL ESPARZA
Green Building Rough 9/16/2019 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/16/2019 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 9/18/2019 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/24/2019 Corrections Issued MISAEL ESPARZA
Insulation 9/24/2019 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 9/24/2019 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 10/2/2019 Approved MISAEL ESPARZA
Drywall Nailing 10/15/2019 Approved RAYMOND KEHOE
ELECTRICAL-Rough 12/17/2019 No Access for Inspection MISAEL ESPARZA
HVAC-Rough 12/17/2019 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/17/2019 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
ELECTRICAL-Final 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
Final 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
Footing/Foundation/Slab 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
Gas Test 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
Green Building Final 1/30/2020 Corrections Issued RAYMOND KEHOE
HVAC-Final 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
PLUMBING-Final 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 1/30/2020 SGSOV Not Ready RAYMOND KEHOE
Service/Power Release 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
Smoke Detectors 1/30/2020 Not Ready for Inspection RAYMOND KEHOE
ELECTRICAL-Final 2/6/2020 No Access for Inspection DANIEL ORRANTE
Gas Test 2/6/2020 No Access for Inspection DANIEL ORRANTE
HVAC-Final 2/6/2020 No Access for Inspection DANIEL ORRANTE
Service/Power Release 2/6/2020 No Access for Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 2/7/2020 No Access for Inspection RAYMOND KEHOE
Final 2/7/2020 No Access for Inspection RAYMOND KEHOE
Footing/Foundation/Slab 2/7/2020 No Access for Inspection RAYMOND KEHOE
Green Building Final 2/7/2020 No Access for Inspection RAYMOND KEHOE
PLUMBING-Final 2/7/2020 No Access for Inspection RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 2/7/2020 SGSOV Not Ready RAYMOND KEHOE
Smoke Detectors 2/7/2020 Corrections Issued RAYMOND KEHOE
BUILDING-Rough-Frame 2/13/2020 Approved DANIEL ORRANTE
Final 2/13/2020 Corrections Issued DANIEL ORRANTE
Footing/Foundation/Slab 2/13/2020 Approved DANIEL ORRANTE
Green Building Final 2/13/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 2/13/2020 SGSOV Not Ready DANIEL ORRANTE
Service/Power Release 2/13/2020 Approved DANIEL ORRANTE
Smoke Detectors 2/13/2020 Approved DANIEL ORRANTE
Final 2/26/2020 Corrections Issued RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 2/26/2020 SGSOV Approved RAYMOND KEHOE
ELECTRICAL-Final 3/4/2020 Approved RAYMOND KEHOE
Final 3/4/2020 Not Ready for Inspection RAYMOND KEHOE
HVAC-Final 3/4/2020 Approved RAYMOND KEHOE
PLUMBING-Final 3/4/2020 Approved RAYMOND KEHOE
Service/Power Release 3/4/2020 Not Ready for Inspection RAYMOND KEHOE
Final 3/17/2020 OK to Issue CofO RAYMOND KEHOE