9830 W CARDIGAN PL 90210

Certificate Information: 9830 W CARDIGAN PL 90210

Application / Permit
18010-30000-04761
Plan Check / Job No.
B18WL06294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 1/28/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2018 APPLICANT
Green Plans Picked Up 10/12/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/23/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/24/2018 JASON HEALEY
Applicant returned to address corrections 11/13/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/11/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/19/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/9/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/23/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/24/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/4/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/11/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/4/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/30/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/8/2020 KAMRAN GHOTBI RAVANDI
Issued 1/28/2020 LADBS
Building Plans Picked Up 5/18/2020 APPLICANT
CofO in Progress 3/30/2023 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 3/31/2023 DANIEL ORRANTE
CofO Issued 3/31/2023 DANIEL ORRANTE
Permit Finaled 3/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/10/2018 ALINE MILLER
BHO/Hillside ordinance Cleared 12/10/2018 ALINE MILLER
BHO/Hillside ordinance Cleared 12/10/2018 ALINE MILLER
Eng Process Fee Ord 176,300 Cleared 12/10/2018 ALINE MILLER
Permit Cleared 12/10/2018 ALINE MILLER
Sewer availability Cleared 12/10/2018 ALINE MILLER
Hydrant and Access approval Cleared 12/11/2018 ROBERT DUFF
Trees in Parkway Cleared 3/11/2019 ADRIAN SANCHEZ
ZI Cleared 3/13/2019 TREVOR MARTIN
Green Code Cleared 6/6/2019 DONALD CRICHLOW
Low Impact Development Cleared 11/7/2019 JORGE MEJIA LEMUS
Miscellaneous Cleared 12/9/2019 JOSE CRUZ RODRIGUEZ
Roof/Waste drainage to street Cleared 12/9/2019 JOSE CRUZ RODRIGUEZ
Excavation more than 5-ft deep Cleared 12/30/2019 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2020 Partial Approval ANTHONY MCDOWALL
Deputy Grading 9/25/2020 Partial Approval MATT KELLERMAN
Deputy Grading 9/29/2020 Conditional Approval ANTHONY MCDOWALL
Deputy Grading 9/30/2020 No Access for Inspection VASIL MIHALEV
Deputy Reinf. Concrete 9/30/2020 Conditional Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 9/30/2020 Not Ready for Inspection ANTHONY MCDOWALL
Piling/Pier/Caisson 9/30/2020 Not Ready for Inspection ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 10/2/2020 Partial Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 10/2/2020 Partial Approval ANTHONY MCDOWALL
Deputy Other (see comments) 10/5/2020 Conditional Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 10/6/2020 Partial Approval ANTHONY MCDOWALL
Deputy Other (see comments) 10/7/2020 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 10/7/2020 Conditional Approval ANTHONY MCDOWALL
Deputy Drilled-In Anchors 10/14/2020 Conditional Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 10/15/2020 Partial Approval ANTHONY MCDOWALL
Deputy Grading 10/19/2020 Conditional Approval ANTHONY MCDOWALL
Deputy Grading 10/20/2020 Conditional Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 10/20/2020 Partial Approval ANTHONY MCDOWALL
Deputy Grading 11/4/2020 Conditional Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 11/4/2020 Partial Approval ANTHONY MCDOWALL
FLOOD-Elevation Certificate 11/4/2020 Not Ready for Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 11/4/2020 Partial Approval ANTHONY MCDOWALL
Deputy Grading 11/5/2020 Approved MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/9/2020 Partial Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 11/9/2020 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 11/10/2020 Conditional Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 11/10/2020 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 11/23/2020 Partial Approval ANTHONY MCDOWALL
FLOOD-Elevation Certificate 11/30/2020 Approved ANTHONY MCDOWALL
Footing/Foundation/Slab 11/30/2020 Partial Approval ANTHONY MCDOWALL
Reinforced Concrete Frame 11/30/2020 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 12/3/2020 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Drilled-In Anchors 12/7/2020 Conditional Approval ANTHONY MCDOWALL
Deputy Other (see comments) 12/7/2020 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 12/8/2020 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 12/14/2020 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 12/16/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 12/16/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 12/21/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 12/28/2020 Conditional Approval MATT KELLERMAN
Deputy Drilled-In Anchors 1/6/2021 Conditional Approval ANTHONY MCDOWALL
PLUMBING-Rough 1/12/2021 Corrections Issued ANTHONY MCDOWALL
Deputy Reinf. Concrete 1/13/2021 Conditional Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 1/14/2021 Partial Approval ANTHONY MCDOWALL
Reinforced Concrete Frame 1/14/2021 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Shotcrete 1/15/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Shotcrete 1/19/2021 Conditional Approval ANTHONY MCDOWALL
PLUMBING-Rough 2/5/2021 Partial Approval ANTHONY MCDOWALL
Masonry Wall/Backfill 2/9/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 3/4/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 3/8/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 3/31/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/1/2021 Conditional Approval ANTHONY MCDOWALL
PLUMBING-Rough 4/8/2021 Partial Approval ANTHONY MCDOWALL
Deputy Other (see comments) 4/20/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/20/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Other (see comments) 4/22/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/22/2021 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 4/26/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/27/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/28/2021 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 9/22/2021 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 9/24/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/5/2021 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 10/8/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 10/8/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/25/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/28/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 11/5/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/5/2021 Approved BRENDAN LOONEY
Piling/Pier/Caisson 11/8/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 11/9/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 11/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 12/6/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 12/7/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 2/10/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/3/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 3/9/2022 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 3/9/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/18/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 3/22/2022 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 4/22/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/5/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/6/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/9/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Wood Frame 5/23/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/24/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/27/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 5/31/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/2/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/2/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/8/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/8/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
FLOOD-Proofing Certificate 6/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 6/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/14/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 6/14/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/14/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/17/2022 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 6/17/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 6/29/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/30/2022 Corrections Issued STEPHANIE SWANSON
Shower Pan 6/30/2022 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 6/30/2022 Partial Inspection HERBERT GIRON
Shower Pan 7/5/2022 Approved GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/11/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/12/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/14/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/14/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/18/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/18/2022 Partial Approval BRENDAN LOONEY
Masonry Wall/Backfill 7/22/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 10/5/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Gas Test 10/21/2022 Approved CARLOS MATAMOROS
Underground Mechanical 10/21/2022 Approved CARLOS MATAMOROS
Service/Power Release 11/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 11/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 11/14/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 11/14/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 11/16/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 11/30/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 1/6/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 1/19/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Final 1/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 1/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 1/23/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/23/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 1/23/2023 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 1/23/2023 Approved GERMAN RODRIGUEZ MENDOZA
Structural Steel Frame 1/23/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 2/27/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 3/7/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 3/29/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA