1821-1829 S REDONDO BLVD 90019

Certificate Information: 1821-1829 S REDONDO BLVD 90019

Application / Permit
18010-30000-04713
Plan Check / Job No.
B18WL06236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DEWLLING WITH ATTACHED GARAGE PER VTT-80308-SL. LOT #10
Permit Issued
Issued on 12/26/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 11/6/2018 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 11/6/2018 APPLICANT
Quality Review Completed 11/7/2018 JASON HEALEY
Building Plans Picked Up 11/8/2018 APPLICANT
Applicant returned to address corrections 12/10/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/10/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/29/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/28/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/17/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 10/1/2019 KAMRAN GHOTBI RAVANDI
Issued 12/26/2019 LADBS
CofO in Progress 7/30/2022 SCOTT FINNILA
Permit Finaled 8/3/2022 DEROLD HAUFF
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/13/2018 ROBERT DUFF
Address approval Cleared 12/20/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/20/2018 STEVE MELGAR
Highway dedication Cleared 12/20/2018 STEVE MELGAR
Permit Cleared 12/24/2018 STEVE MELGAR
Roof/Waste drainage to street Cleared 2/6/2019 JAMES KHO
Low Impact Development Cleared 2/15/2019 MITESH PATEL
Trees in Parkway Cleared 2/27/2019 JOHN KIM
Tract Map conditions Cleared 3/28/2019 MOTOUMI SASAKI
Green Code Cleared 4/16/2019 RICHARD GARCIA
Flood clearance Cleared 8/9/2019 SYLVIA DHIMDIS
Sewer availability Cleared 8/19/2019 ELENA LOPEZ

Contact Information

Contractor Century 26 Construction Inc; Lic. No.: 1056879-B 269 S BEVERLY DR #263      BEVERLY HILLS, CA 90212

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/12/2020 Partial Approval SCOTT FINNILA
FLOOD-Elevation Certificate 5/15/2020 Approved SCOTT FINNILA
Footing/Foundation/Slab 5/15/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 5/18/2020 Conditional Approval SABAS ALONSO
Deputy Reinf. Concrete 5/19/2020 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/22/2020 Partial Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/27/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 5/29/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 6/8/2020 No Access for Inspection SCOTT FINNILA
Deputy Reinf. Concrete 6/17/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/18/2020 Conditional Approval SCOTT FINNILA
Deputy Reinf. Concrete 6/19/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 8/14/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 8/19/2020 Partial Approval SCOTT FINNILA
Green Building Rough 8/19/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 9/21/2020 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 9/21/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/28/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/14/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 11/12/2020 Partial Approval SCOTT FINNILA
Green Building Rough 11/12/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 11/19/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 1/12/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 1/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 4/19/2021 Approved SCOTT FINNILA
Insulation 4/21/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Partial Approval SCOTT FINNILA
Insulation 4/22/2021 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 4/27/2021 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 5/3/2021 Approved SCOTT FINNILA
Deputy Wood Construction 5/4/2021 Conditional Approval MICHAEL FAUNCE
Interior/Exterior Lathing 5/13/2021 Partial Approval SCOTT FINNILA
Insulation 5/21/2021 Approved SCOTT FINNILA
Drywall Nailing 6/2/2021 Approved SCOTT FINNILA
Green Building Rough 6/2/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/23/2021 Approved SCOTT FINNILA
Underground Mechanical 10/26/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 1/26/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 1/26/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 3/3/2022 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/26/2022 Partial Approval SCOTT FINNILA
FLOOD-Proofing Certificate 5/26/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 5/26/2022 Partial Approval SCOTT FINNILA
Green Building Final 5/26/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 5/26/2022 Approved SCOTT FINNILA
Smoke Detectors 5/26/2022 Approved SCOTT FINNILA
Structural Steel Frame 5/26/2022 Partial Approval SCOTT FINNILA
Gas Test 6/6/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 6/7/2022 Partial Inspection SCOTT FINNILA
Gas Test 6/23/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/27/2022 Approved SCOTT FINNILA
PLUMBING-Final 6/27/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/30/2022 Approved SCOTT FINNILA
ELECTRICAL-Final 7/30/2022 Approved SCOTT FINNILA
FLOOD-Proofing Certificate 7/30/2022 Approved SCOTT FINNILA
Final 7/30/2022 OK to Issue CofO SCOTT FINNILA
Footing/Foundation/Slab 7/30/2022 Approved SCOTT FINNILA
Green Building Final 7/30/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 7/30/2022 SGSOV Approved SCOTT FINNILA
Structural Steel Frame 7/30/2022 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 7/30/2022 Approved SCOTT FINNILA