1898 N RISING GLEN ROAD 90069

Certificate Information: 1898 N RISING GLEN ROAD 90069

Application / Permit
18010-30000-04492
Plan Check / Job No.
B18WL05931
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ACCESSORY LIVING QUARTER
Permit Issued
Issued on 2/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2018 APPLICANT
Green Plans Picked Up 9/26/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/2/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/4/2018 JASON HEALEY
Building Plans Picked Up 10/4/2018 APPLICANT
Applicant returned to address corrections 11/8/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/26/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/21/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/16/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/22/2019 KAMRAN GHOTBI RAVANDI
Issued 2/4/2019 LADBS
CofO in Progress 4/5/2024 RAUL BARAJAS
Permit Finaled 4/5/2024 RONALD MYRICK
CofO Issued 4/5/2024 RONALD MYRICK
Permit Finaled 4/5/2024 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/9/2018 STEVE MELGAR
BHO/Hillside ordinance Cleared 10/9/2018 STEVE MELGAR
ZI Cleared 10/9/2018 SARAH GOLDMAN
Hydrant and Access approval Cleared 10/10/2018 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 12/18/2018 MICHAEL CASTILLO
Sewer availability Cleared 12/18/2018 MICHAEL CASTILLO
BHO/Hillside ordinance Cleared 1/2/2019 NAZILA NOORIFAR
Low Impact Development Cleared 1/10/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 1/10/2019 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 1/16/2019 CALOSHA APPROVED
Green Code Cleared 1/17/2019 DONALD CRICHLOW

Contact Information

Contractor Gibson Gordon S Inc; Lic. No.: 524012-B 3000 31 STREET SUITE G      SANTA MONICA, CA 90405
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Hollingsworth, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/6/2019 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 5/15/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 5/30/2019 Corrections Issued DANNY TOLENTINO
Piling/Pier/Caisson 6/4/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 7/16/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 7/19/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 7/19/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 8/8/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/23/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/1/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/1/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 5/18/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 5/18/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/27/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 5/28/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/10/2020 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 8/4/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Approved RAUL BARAJAS
Green Building Rough 8/4/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/4/2020 Not Ready for Inspection RAUL BARAJAS
Wood Frame 8/4/2020 Partial Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 10/16/2020 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 10/22/2020 Approved RAUL BARAJAS
Green Building Rough 10/22/2020 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 10/22/2020 Approved RAUL BARAJAS
Wood Frame 10/22/2020 Approved RAUL BARAJAS
Insulation 10/23/2020 Approved RAUL BARAJAS
Deputy Grading 11/2/2020 No Access for Inspection ELMER BLAND
Drywall Nailing 11/4/2020 Approved RAUL BARAJAS
Deputy Steel/Welding 11/10/2020 No Access for Inspection ELMER BLAND
Interior/Exterior Lathing 12/10/2020 Approved RAUL BARAJAS
Shower Pan 12/16/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/21/2020 Approved RAUL BARAJAS
Footing/Foundation/Slab 2/26/2024 Approved ROY SPAULDING
Green Building Final 2/26/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready ROY SPAULDING
Structural Steel Frame 2/26/2024 Approved ROY SPAULDING
Final 2/28/2024 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved RAUL BARAJAS
Service/Power Release 2/28/2024 Approved RAUL BARAJAS
Smoke Detectors 2/28/2024 Approved RAUL BARAJAS
Final 4/5/2024 OK to Issue CofO RAUL BARAJAS