841 E COMMONWEALTH AVE 90291
Certificate Information: 841 E COMMONWEALTH AVE 90291
- Application / Permit
- 18010-30000-04220
- Plan Check / Job No.
- B18WL05596
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of (e) att. garage and portion of (e) sfd 2nd floor to a new accessory dwelling unit (ADU) per AB 494 & SB 229.
- Permit Issued
- Issued on 3/4/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | MANUEL GARCIA |
| Corrections Issued | 9/10/2018 | MANUEL GARCIA |
| Building Plans Picked Up | 9/12/2018 | APPLICANT |
| Applicant returned to address corrections | 12/20/2018 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/30/2019 | REZA HAGHIGHAT |
| Issued | 3/4/2019 | LADBS |
| CofO in Progress | 6/19/2020 | DAVID HEINE |
| No Progress | 10/26/2020 | VINCENT COTTON |
| CofO in Progress | 2/22/2021 | PIERRE VEGA |
| CofO Issued | 2/23/2021 | VINCENT COTTON |
| Permit Finaled | 2/23/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/1/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 10/1/2018 | STEVE MELGAR |
| Construction near power lines | Cleared | 10/4/2018 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2019 | JOSE CRUZ RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/20/2019 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 7/16/2019 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/22/2019 | Corrections Issued | DAVID HEINE |
| Deputy Drilled-In Anchors | 7/24/2019 | Partial Approval | DAVID HEINE |
| Deputy Drilled-In Anchors | 7/26/2019 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 7/29/2019 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 11/8/2019 | Not Ready for Inspection | DAVID HEINE |
| Green Building Rough | 11/8/2019 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2019 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 12/16/2019 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 12/16/2019 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/23/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 1/31/2020 | Corrections Issued | DAVID HEINE |
| PLUMBING-Rough | 1/31/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 2/11/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 2/18/2020 | Approved | DAVID HEINE |
| Green Building Rough | 2/18/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 3/10/2020 | Approved | DAVID HEINE |
| Gas Test | 4/28/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 4/28/2020 | Approved | DAVID HEINE |
| Final | 6/16/2020 | Conditional Approval | DAVID HEINE |
| Green Building Final | 6/16/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Approved | DAVID HEINE |
| Smoke Detectors | 6/16/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 6/19/2020 | Approved | DAVID HEINE |
| Final | 6/19/2020 | OK to Issue CofO | DAVID HEINE |
| HVAC-Final | 6/19/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 6/19/2020 | Approved | DAVID HEINE |
| Service/Power Release | 10/26/2020 | Approved | KENNETH NAGLE |
| Special/Order Compliance | 11/20/2020 | Corrections Issued | DAVID HEINE |