668 N EAST CHANNEL ROAD 90402

Certificate Information: 668 N EAST CHANNEL ROAD 90402

Application / Permit
18010-30000-04029
Plan Check / Job No.
B18WL05325
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY TYPE VB SINGEL FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 2/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 SERGIO SILVA
Corrections Issued 9/13/2018 SERGIO SILVA
Quality Review Completed 9/20/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/28/2018 SERGIO SILVA
Applicant returned to address corrections 12/7/2018 SERGIO SILVA
Green Plans Picked Up 2/22/2019 APPLICANT
Applicant returned to address corrections 3/1/2019 SERGIO SILVA
Applicant returned to address corrections 5/4/2020 SERGIO SILVA
Applicant returned to address corrections 7/27/2020 SERGIO SILVA
Plan Check Approved 10/1/2020 SERGIO SILVA
Issued 11/25/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT
CofO in Progress 12/28/2022 BRENDAN LOONEY
Permit Finaled 2/27/2023 DANIEL ORRANTE
CofO Issued 2/27/2023 DANIEL ORRANTE
Permit Finaled 2/27/2023 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 9/11/2018 SERGIO SILVA
Grading Pre-Inspection Cleared 9/11/2018 SERGIO SILVA
BHO/Hillside ordinance Cleared 10/4/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 10/4/2018 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 10/4/2018 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/28/2018 CHRISTOPHER LAW
Haul Route Cleared 3/10/2020 SERGIO SILVA
Miscellaneous Cleared 3/10/2020 SERGIO SILVA
Address approval Cleared 3/18/2020 DINAH GARIN
Permit Cleared 3/18/2020 DINAH GARIN
Sewer availability Cleared 3/18/2020 DINAH GARIN
Flood clearance Cleared 3/19/2020 DINAH GARIN
ZA Case Cleared 3/23/2020 MAXFIELD VERMY
Trees in Parkway Cleared 4/13/2020 JOHN KIM
Hydrant and Access approval Cleared 4/14/2020 JEREMY CARTER
Green Code Cleared 6/8/2020 RICHARD GARCIA
Low Impact Development Cleared 6/22/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 6/23/2020 MAHELET GEBEYHU
Watercourse Cleared 6/23/2020 MAHELET GEBEYHU
Excavation more than 5-ft deep Cleared 7/27/2020 CALOSHA APPROVED
Disturb/Remove Protected Trees Cleared 7/30/2020 STEPHEN DUPREY
Miscellaneous Cleared 10/1/2020 SERGIO SILVA
Miscellaneous Cleared 11/20/2020 NIKTA MOUSAVI

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Guzman,, Martin; Lic. No.: C79193 4054 W 165TH STREET      LAWNDALE, CA 90260
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Lycklama, James Heinz; Lic. No.: L7525 32218 N BIG OAK LN      CASTAIC, CA 91384
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 3/9/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/9/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 4/9/2021 Partial Approval JOHN KIDWELL
Grounding or Bonding 4/15/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 4/15/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/21/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/18/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 5/21/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 8/24/2021 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 9/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 10/25/2021 Partial Inspection JOHN KIDWELL
Green Building Rough 10/25/2021 Partial Inspection JOHN KIDWELL
Structural Steel Frame 10/25/2021 Partial Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 10/25/2021 Partial Inspection JOHN KIDWELL
HVAC-Rough 11/5/2021 Approved JOHN KIDWELL
PLUMBING-Rough 12/2/2021 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 12/7/2021 Approved JOHN KIDWELL
PLUMBING-Rough 12/7/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/27/2022 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval MICHAEL PELHAM
Verify Sprinkler Sign Off 1/27/2022 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 2/4/2022 Approved JOHN KIDWELL
FLOOD-Proofing Certificate 2/4/2022 Approved JOHN KIDWELL
Green Building Rough 2/4/2022 Approved JOHN KIDWELL
Insulation 2/4/2022 Approved JOHN KIDWELL
Drywall Nailing 2/22/2022 Approved JOHN KIDWELL
Shower Pan 3/16/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/1/2022 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 4/5/2022 Partial Approval JOHN KIDWELL
Shower Pan 4/12/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/25/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/29/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/7/2022 Partial Approval MICHAEL PELHAM
Piling/Pier/Caisson 6/13/2022 Partial Approval JOHN KIDWELL
Gas Test 7/25/2022 Approved BRENDAN LOONEY
PLUMBING-Final 10/20/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 11/3/2022 Approved KEVIN SARGSYAN
HVAC-Final 11/7/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 11/10/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 11/14/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 11/18/2022 Approved KEVIN SARGSYAN
Final 12/20/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 12/20/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 12/20/2022 Approved KEVIN SARGSYAN
Smoke Detectors 12/20/2022 Approved KEVIN SARGSYAN
Structural Steel Frame 12/20/2022 Approved KEVIN SARGSYAN
Final 12/27/2022 OK to Issue CofO BRENDAN LOONEY