11767 W CHENAULT ST 90049
Certificate Information: 11767 W CHENAULT ST 90049
- Application / Permit
- 18010-30000-04007
- Plan Check / Job No.
- B18WL05279
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Accessory Living Quarter to Accessory Dwelling Unit. Per AB 494 & SB229.
- Permit Issued
- Issued on 5/29/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2018 | APPLICANT |
| Green Plans Picked Up | 9/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | ALFREDO JARA |
| Corrections Issued | 9/10/2018 | ALFREDO JARA |
| Quality Review Completed | 9/20/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/20/2018 | APPLICANT |
| Plan Check Approved | 5/16/2019 | ALFREDO JARA |
| Issued | 5/29/2019 | LADBS |
| CofO in Progress | 10/20/2021 | CARLOS MATAMOROS |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
| CofO Issued | 3/8/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/22/2018 | ALFREDO JARA |
| Address approval | Cleared | 5/7/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 5/7/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/7/2019 | ELAINE LEI |
| Sewer availability | Cleared | 5/16/2019 | MAHELET GEBEYHU |
Contact Information
| Architect | Walters, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Deputy Drilled-In Anchors | 8/18/2020 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/19/2020 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/20/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/24/2020 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/18/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/18/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/24/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/2/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/2/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 3/2/2021 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 3/18/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 3/18/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/26/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/26/2021 | Approved | CARLOS MATAMOROS |
| Sewer | 7/1/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/6/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 8/6/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/16/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Final | 8/16/2021 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 8/25/2021 | Approved | CARLOS MATAMOROS |
| Final | 8/25/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 8/25/2021 | Approved | CARLOS MATAMOROS |
| Final | 9/14/2021 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 9/14/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/14/2021 | Approved | CARLOS MATAMOROS |
| Final | 10/20/2021 | OK to Issue CofO | CARLOS MATAMOROS |