11767 W CHENAULT ST 90049

Certificate Information: 11767 W CHENAULT ST 90049

Application / Permit
18010-30000-04007
Plan Check / Job No.
B18WL05279
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Accessory Living Quarter to Accessory Dwelling Unit. Per AB 494 & SB229.
Permit Issued
Issued on 5/29/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2018 APPLICANT
Green Plans Picked Up 9/4/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 ALFREDO JARA
Corrections Issued 9/10/2018 ALFREDO JARA
Quality Review Completed 9/20/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/20/2018 APPLICANT
Plan Check Approved 5/16/2019 ALFREDO JARA
Issued 5/29/2019 LADBS
CofO in Progress 10/20/2021 CARLOS MATAMOROS
Permit Finaled 3/8/2022 DANIEL ORRANTE
CofO Issued 3/8/2022 DANIEL ORRANTE
Permit Finaled 3/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/22/2018 ALFREDO JARA
Address approval Cleared 5/7/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/7/2019 ELAINE LEI
Low Impact Development Cleared 5/7/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/7/2019 ELAINE LEI
Sewer availability Cleared 5/16/2019 MAHELET GEBEYHU

Contact Information

Architect Walters, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/28/2020 Not Ready for Inspection ROBERT SHELLY
Deputy Drilled-In Anchors 8/18/2020 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 8/19/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 8/20/2020 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 8/24/2020 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 9/18/2020 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/18/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/24/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Approved CARLOS MATAMOROS
HVAC-Rough 3/2/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/2/2021 Approved CARLOS MATAMOROS
Underground Mechanical 3/2/2021 Corrections Issued CARLOS MATAMOROS
Insulation 3/18/2021 Approved CARLOS MATAMOROS
Shower Pan 3/18/2021 Approved CARLOS MATAMOROS
Drywall Nailing 3/26/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/26/2021 Approved CARLOS MATAMOROS
Sewer 7/1/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/6/2021 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 8/6/2021 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 8/16/2021 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Final 8/16/2021 Corrections Issued ANTHONY MCDOWALL
ELECTRICAL-Final 8/25/2021 Approved CARLOS MATAMOROS
Final 8/25/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 8/25/2021 Approved CARLOS MATAMOROS
Final 9/14/2021 Partial Approval CARLOS MATAMOROS
HVAC-Final 9/14/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 9/14/2021 Approved CARLOS MATAMOROS
Final 10/20/2021 OK to Issue CofO CARLOS MATAMOROS