Excavation/Setback/Form/Re-Bar
|
1/24/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
2/4/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
2/10/2020
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
3/2/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/4/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
3/5/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
4/2/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
4/2/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
4/2/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
4/17/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
4/17/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
4/17/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
4/22/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/1/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
5/19/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
5/21/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
6/24/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
6/24/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
6/24/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
7/13/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Reinforced Concrete Frame
|
7/13/2020
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
7/13/2020
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
7/14/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
7/15/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
9/14/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
10/2/2020
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/14/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/16/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
10/17/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/19/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
11/13/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
12/8/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
12/8/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
12/8/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/16/2020
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
12/18/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
12/21/2020
|
Approved
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
12/28/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
1/25/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
1/27/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
1/28/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
4/5/2021
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
4/12/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/15/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/8/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
PLUMBING-Rough
|
6/17/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
7/6/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
7/6/2021
|
Partial Inspection
|
AMY COLIN
|
|
HVAC-Rough
|
7/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
7/12/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/14/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
7/14/2021
|
Partial Inspection
|
ADAM ESCOTO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
7/22/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
7/22/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
7/26/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
7/28/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/10/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
8/13/2021
|
Approved
|
SHAVONNE ESPINOZA
|
|
ELECTRICAL-Rough
|
8/19/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/25/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/26/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/26/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
8/31/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
8/31/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
8/31/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
8/31/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
9/2/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
9/22/2021
|
Partial Approval
|
JAVIER RAMOS JR
|
|
Insulation
|
9/24/2021
|
Approved
|
JAVIER RAMOS JR
|
|
Interior/Exterior Lathing
|
9/24/2021
|
Partial Approval
|
JAVIER RAMOS JR
|
|
BUILDING-Rough-Frame
|
9/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
9/30/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/6/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
10/6/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
10/19/2021
|
Approved
|
RYAN SALAZAR
|
|
Underground Mechanical
|
10/25/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/5/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
HVAC-Rough
|
11/5/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
BUILDING-Rough-Frame
|
11/9/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
11/9/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
11/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/1/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/1/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
12/1/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/20/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/20/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
12/20/2021
|
Partial Inspection
|
CLAYTON GRAHAM
|
|
Underground Mechanical
|
12/28/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
1/14/2022
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
1/27/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/9/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
3/14/2022
|
Corrections Issued
|
MICHAEL PELHAM
|
|
ELECTRICAL-Final
|
3/31/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/27/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/29/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Sewer
|
4/29/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
5/5/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
5/6/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
5/6/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
5/9/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
5/9/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
5/12/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
5/16/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
5/18/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
5/20/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
5/20/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
5/20/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
5/20/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
5/20/2022
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
5/20/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
5/20/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
5/23/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
5/25/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Final
|
6/1/2022
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|