982 N STONE CANYON ROAD 90077

Certificate Information: 982 N STONE CANYON ROAD 90077

Application / Permit
18010-30000-03708
Plan Check / Job No.
B18WL04830
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
accessory recreation building with shower open to the outside.
Permit Issued
Issued on 5/1/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 8/28/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/28/2018 JASON HEALEY
Applicant returned to address corrections 12/20/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/25/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/12/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/8/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/18/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/19/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/29/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 5/1/2019 KAMRAN GHOTBI RAVANDI
Issued 5/1/2019 LADBS
Building Plans Picked Up 12/7/2020 APPLICANT
Permit Finaled 4/23/2024 DANIEL ORRANTE
CofO Issued 4/23/2024 DANIEL ORRANTE
Permit Finaled 4/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/11/2018 ROBERT DUFF
ZA Case Cleared 9/26/2018 DANALYNN DOMINGUEZ
ZI Cleared 9/26/2018 DANALYNN DOMINGUEZ
BHO/Hillside ordinance Cleared 2/12/2019 TAO YANG
BHO/Hillside ordinance Cleared 2/12/2019 TAO YANG
BHO/Hillside ordinance Cleared 2/13/2019 HISASHI KOBAYAKAWA
Watercourse Cleared 2/13/2019 TAO YANG
Eng Process Fee Ord 176,300 Cleared 3/11/2019 ELENA LOPEZ
Sewer availability Cleared 3/11/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 3/20/2019 KRISTEN LY
Flood clearance Cleared 3/28/2019 SYLVIA DHIMDIS
Green Code Cleared 3/28/2019 DONALD CRICHLOW
Low Impact Development Cleared 4/16/2019 ANDRES COVARRUBIAS

Contact Information

Contractor Silverston & Associates Inc; Lic. No.: 488695-B 3480 LOS FLORES CYN      MALIBU, CA 90265
Engineer Erdelyi, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025
Engineer Masterman, Gary Clyde; Lic. No.: GE567 4580 MOHAWK DR      LARKSPUR, CO 80118
Geologist Schick, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/3/2021 Conditional Approval CHRISTOPHER WILSON
FLOOD-Elevation Certificate 7/29/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/29/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/2/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 8/3/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/4/2021 Approved CHRISTOPHER WILSON
PLUMBING-Rough 8/4/2021 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 5/24/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/27/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/17/2022 Approved MICHAEL PELHAM
ELECTRICAL-Rough 6/17/2022 Corrections Issued CHRISTOPHER WILSON
FLOOD-Proofing Certificate 6/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Approved CHRISTOPHER WILSON
Green Building Rough 6/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 6/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/17/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 6/22/2022 Approved CHRISTOPHER WILSON
HVAC-Rough 6/22/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 6/22/2022 Approved CHRISTOPHER WILSON
Service/Power Release 8/17/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 9/27/2022 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved CHRISTOPHER WILSON
Wood Frame 9/27/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/17/2024 Approved CHRISTOPHER WILSON
Drywall Nailing 4/17/2024 Approved CHRISTOPHER WILSON
FLOOD-Elevation Certificate 4/17/2024 Approved CHRISTOPHER WILSON
FLOOD-Proofing Certificate 4/17/2024 Approved CHRISTOPHER WILSON
Final 4/17/2024 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/17/2024 Approved CHRISTOPHER WILSON
Green Building Final 4/17/2024 Approved CHRISTOPHER WILSON
Green Building Rough 4/17/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved CHRISTOPHER WILSON
Service/Power Release 4/17/2024 Approved CHRISTOPHER WILSON
Smoke Detectors 4/17/2024 Approved CHRISTOPHER WILSON