Pre-Inspection
|
5/6/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/22/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Sewer
|
10/1/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
10/7/2019
|
Partial Approval
|
MATT KELLERMAN
|
|
Sewer
|
10/7/2019
|
Partial Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
FLOOD-Elevation Certificate
|
10/17/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/17/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
FLOOD-Elevation Certificate
|
10/22/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/28/2019
|
Partial Inspection
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
12/2/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
FLOOD-Elevation Certificate
|
12/2/2019
|
Approved
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/2/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/11/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/13/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/24/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
2/7/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/16/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/17/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/4/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/5/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/7/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
6/3/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/26/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/2/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
7/2/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Reinf. Concrete
|
7/6/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
7/21/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
FLOOD-Proofing Certificate
|
7/28/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
9/8/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/22/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
9/22/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
9/22/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/6/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
10/6/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/6/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/23/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/23/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
11/23/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
11/23/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
11/23/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Insulation
|
12/16/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Rough-Elec/Plmb/HVAC
|
12/16/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Insulation
|
1/4/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
1/4/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
1/4/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
1/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
1/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
1/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
3/19/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/19/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/23/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
3/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
ELECTRICAL-Rough
|
4/12/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
4/12/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
4/19/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
4/19/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/11/2021
|
No Access for Inspection
|
MATT KELLERMAN
|
|
Interior/Exterior Lathing
|
5/13/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
5/25/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/25/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
6/2/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
PLUMBING-Rough
|
6/8/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
6/10/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
6/15/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
6/17/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
6/29/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/14/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
7/23/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
7/29/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/2/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/4/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/4/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/11/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/12/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
8/17/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
8/17/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
8/17/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
8/20/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
8/20/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
8/25/2021
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Drywall Nailing
|
9/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
9/8/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
9/17/2021
|
Partial Approval
|
JAVIER RAMOS JR
|
|
Interior/Exterior Lathing
|
10/27/2021
|
Approved
|
KRISTEN CAUSEY
|
|
Shower Pan
|
11/1/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/16/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
11/16/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/16/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/19/2021
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
12/15/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Wood Frame
|
12/15/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
ELECTRICAL-Rough
|
1/5/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
1/27/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
2/18/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
2/18/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
4/8/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
4/8/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
4/8/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Insulation
|
5/24/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
5/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
5/27/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/8/2022
|
Corrections Issued
|
CLAYTON GRAHAM
|
|
PLUMBING-Rough
|
7/12/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
7/25/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
8/3/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/9/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/15/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
8/22/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/25/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/26/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
9/1/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/1/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
9/1/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
9/1/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
9/1/2022
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/27/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Grading Pre-Inspection
|
10/3/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
10/6/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
10/6/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
10/6/2022
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
10/6/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
12/29/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/29/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
1/25/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
1/25/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
1/25/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
1/25/2023
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
1/25/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
4/10/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
4/10/2023
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
8/28/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/28/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
8/28/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
8/28/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
12/4/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
12/4/2023
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Final
|
12/18/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
12/18/2023
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
1/30/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
2/9/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
2/9/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Final
|
2/12/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
2/12/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Final
|
2/27/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
2/27/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
2/27/2024
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/29/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
3/13/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
3/19/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/26/2024
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/27/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
3/29/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/29/2024
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
4/3/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
4/3/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
4/3/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/3/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
4/4/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/4/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
4/5/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/5/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
4/5/2024
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
4/5/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
4/5/2024
|
Approved
|
CHRISTOPHER WILSON
|