10450 W CHARING CROSS ROAD 90024
Certificate Information: 10450 W CHARING CROSS ROAD 90024
- Application / Permit
- 18010-30000-03553
- Plan Check / Job No.
- B18WL04570
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW RECREATION ROOM
- Permit Issued
- Issued on 10/3/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2018 | APPLICANT |
| Green Plans Picked Up | 7/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 8/20/2018 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 8/28/2018 | JASON HEALEY |
| Building Plans Picked Up | 8/28/2018 | APPLICANT |
| Applicant returned to address corrections | 9/14/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/26/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 10/3/2018 | KAMRAN GHOTBI RAVANDI |
| Issued | 10/3/2018 | LADBS |
| CofO in Progress | 1/26/2023 | CARLOS MATAMOROS |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
| CofO Issued | 2/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2018 | DENNIS BRAGIN |
| Sewer availability | Cleared | 8/28/2018 | DENNIS BRAGIN |
| Green Code | Cleared | 9/6/2018 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 9/21/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/26/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/26/2018 | ADRIAN SANCHEZ |
Contact Information
| Architect | Vertoch, Philip Girard; Lic. No.: C21731 | 1419-A CLOVERFIELD BLVD SANTA MONICA, CA 90404 |
| Contractor | Owner-Builder | , |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Engineer | Shah, Kamal Rajendra; Lic. No.: C46200 | 28039 SMYTH DR STE 200 VALENCIA, CA 91355 |
| Geologist | Irvine, Jon A; Lic. No.: EG1691 | 1150 ENCANTO DR ARCADIA, CA 91007 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/8/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 9/10/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 10/20/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 10/20/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/14/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 12/14/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 12/14/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 12/14/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 12/14/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 12/14/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 12/14/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 12/31/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 1/8/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | CHRISTOPHER WILSON |
| Final | 4/26/2022 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Service/Power Release | 4/26/2022 | Not Required | BRENDAN LOONEY |
| Smoke Detectors | 4/26/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 1/12/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 1/12/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 1/12/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 1/12/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 1/26/2023 | Approved | CARLOS MATAMOROS |
| Final | 1/26/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 1/26/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/26/2023 | Approved | CARLOS MATAMOROS |