1529 N SKYLARK LANE 90069

Certificate Information: 1529 N SKYLARK LANE 90069

Application / Permit
18010-30000-03456
Plan Check / Job No.
B18WL04434
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH BASEMENT
Permit Issued
Issued on 2/19/2019
Issuing Office
West Los Angeles
Current Status
Issued on 2/19/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/13/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 8/28/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/28/2018 JASON HEALEY
Building Plans Picked Up 8/28/2018 APPLICANT
Applicant returned to address corrections 9/21/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/1/2018 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 11/8/2018 APPLICANT
Applicant returned to address corrections 11/13/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/16/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/28/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/8/2019 KAMRAN GHOTBI RAVANDI
Issued 2/19/2019 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/31/2018 JEANETTE VONG
BHO/Hillside ordinance Cleared 8/31/2018 JEANETTE VONG
Permit Cleared 8/31/2018 JEANETTE VONG
Private street Cleared 9/13/2018 MARC WOERSCHING
Hydrant and Access approval Cleared 9/17/2018 GILBERT URREA
BHO/Hillside ordinance Cleared 9/25/2018 NAZILA NOORIFAR
Trees in Parkway Cleared 12/14/2018 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 12/18/2018 MICHAEL CASTILLO
Low Impact Development Cleared 12/18/2018 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/18/2018 MICHAEL CASTILLO
Sewer availability Cleared 12/18/2018 MICHAEL CASTILLO
Green Code Cleared 12/21/2018 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 12/28/2018 CALOSHA APPROVED
Miscellaneous Cleared 12/28/2018 TREVOR MARTIN

Contact Information

Contractor Aram G Construction Inc; Lic. No.: 961066-B 441 E SAN JOSE AVENUE #301      BURBANK, CA 91501
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Lau, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/11/2019 Approved DANNY TOLENTINO
Deputy Reinf. Concrete 1/17/2020 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 2/7/2020 Conditional Approval RICHARD STEINBACH
Pre-Inspection 9/29/2021 Partial Inspection RAUL BARAJAS
Special/Order Compliance 4/25/2022 Corrections Issued ALIZAH MAYAGOITIA
Grading Pre-Inspection 7/5/2022 Partial Inspection RAUL BARAJAS
Pre-Inspection 7/5/2022 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/25/2025 Corrections Issued CRAIG VAUGHAN
Pre-Inspection 8/25/2025 Not Ready for Inspection CRAIG VAUGHAN