11831 W CHAPARAL ST 90049

Certificate Information: 11831 W CHAPARAL ST 90049

Application / Permit
18010-30000-03095
Plan Check / Job No.
B18WL03974
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SINGLE FAMILY DWELLING W/ATT GARAGE, BASEMENT, & ROOF DECK
Permit Issued
Issued on 3/5/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 LAMAR DAVIS
Corrections Issued 8/13/2018 LAMAR DAVIS
Quality Review Completed 8/24/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/5/2018 APPLICANT
Green Plans Picked Up 9/6/2018 APPLICANT
Applicant returned to address corrections 3/28/2019 LAMAR DAVIS
Applicant returned to address corrections 4/9/2019 LAMAR DAVIS
Applicant returned to address corrections 4/24/2019 LAMAR DAVIS
Applicant returned to address corrections 5/8/2019 LAMAR DAVIS
Plan Check Approved 5/30/2019 LAMAR DAVIS
Plan Check Approved 12/20/2019 LAMAR DAVIS
Issued 3/5/2020 LADBS
CofO in Progress 7/27/2024 CARLOS MATAMOROS
Permit Finaled 8/7/2024 DANIEL ORRANTE
CofO Issued 8/7/2024 DANIEL ORRANTE
Permit Finaled 8/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/7/2018 KATHLEEN HUGHEY
Eng Process Fee Ord 176,300 Cleared 9/7/2018 KATHLEEN HUGHEY
Miscellaneous Cleared 9/7/2018 KIT AWAKUNI
Miscellaneous Cleared 9/7/2018 KIT AWAKUNI
Miscellaneous Cleared 9/7/2018 KIT AWAKUNI
Hydrant and Access approval Cleared 12/13/2018 PEJMAN NOORI
ZA Case Cleared 12/13/2018 SARAH GOLDMAN
Excavation more than 5-ft deep Cleared 3/28/2019 CALOSHA APPROVED
Miscellaneous Cleared 4/9/2019 LAMAR DAVIS
Miscellaneous Cleared 4/9/2019 LAMAR DAVIS
Low Impact Development Cleared 4/22/2019 MITESH PATEL
GPI Written Notices Cleared 4/24/2019 GRANT WOODS
Grading Pre-Inspection Cleared 4/24/2019 GRANT WOODS
Haul Route Cleared 4/24/2019 LAMAR DAVIS
Roof/Waste drainage to street Cleared 5/2/2019 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/2/2019 HISASHI KOBAYAKAWA
Green Code Cleared 5/7/2019 DONALD CRICHLOW

Contact Information

Architect Massara,, Carl; Lic. No.: C22628 1211 HOLLOW ROAD      BIRCHRUNVILLE, PA 19421
Contractor Owner-Builder       ,
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Phillips, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Geologist Feffer, Joshua Rafael; Lic. No.: GEO6861 12253 GORHAM AVENUE      LOS ANGELES, CA 90049

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/9/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 3/9/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 3/9/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/22/2021 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/1/2021 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 4/9/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 4/22/2021 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 4/26/2021 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 5/12/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Approved CARLOS MATAMOROS
Deputy Steel/Welding 5/20/2021 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 5/21/2021 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/2/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 6/29/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 6/29/2021 Approved CARLOS MATAMOROS
Underground Mechanical 6/29/2021 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 6/30/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Partial Approval ANTHONY MCDOWALL
Deputy Wood Construction 10/4/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 12/29/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/13/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Approved CARLOS MATAMOROS
Shower Pan 7/20/2022 Partial Approval CARLOS MATAMOROS
Wood Frame 8/22/2022 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 8/25/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 9/1/2022 Approved CARLOS MATAMOROS
Insulation 9/14/2022 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 9/14/2022 Approved CARLOS MATAMOROS
HVAC-Rough 10/7/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 10/13/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 10/13/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/13/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 10/18/2022 Approved CARLOS MATAMOROS
Insulation 11/7/2022 Approved CARLOS MATAMOROS
Drywall Nailing 11/16/2022 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/16/2022 Approved CARLOS MATAMOROS
Sewer 9/20/2023 Approved CARLOS MATAMOROS
Gas Test 9/27/2023 Approved CARLOS MATAMOROS
Underground Mechanical 9/27/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/12/2023 Corrections Issued CARLOS MATAMOROS
Gas Test 4/1/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 4/1/2024 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved STEPHANIE SWANSON
Service/Power Release 5/10/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/13/2024 Approved CARLOS MATAMOROS
Service/Power Release 5/14/2024 Approved CARLOS MATAMOROS
HVAC-Final 6/7/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/10/2024 Approved CARLOS MATAMOROS
Final 6/21/2024 Corrections Issued CARLOS MATAMOROS
Green Building Final 6/21/2024 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 6/21/2024 Approved CARLOS MATAMOROS
Structural Steel Frame 6/21/2024 Approved CARLOS MATAMOROS
Final 7/26/2024 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 7/26/2024 Approved CARLOS MATAMOROS