890 N LINDA FLORA DR 90049

Certificate Information: 890 N LINDA FLORA DR 90049

Application / Permit
18010-30000-03036
Plan Check / Job No.
B18WL03954
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED GARAGE AND BASEMENT
Permit Issued
Issued on 7/1/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2018 APPLICANT
Green Plans Picked Up 7/9/2018 APPLICANT
Assigned to Plan Check Engineer 7/26/2018 TARIK SAOUD
Corrections Issued 7/30/2018 TARIK SAOUD
Quality Review Completed 8/14/2018 JOSE RODRIGUEZ
Plan Check Approved 12/10/2018 TARIK SAOUD
Plan Check Approved 12/10/2018 CHARLES CANNING
Issued 7/1/2019 LADBS
Building Plans Picked Up 9/22/2020 APPLICANT
CofO in Progress 8/22/2022 CARLOS MATAMOROS
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 8/17/2018 NADER ISKANDER
Hydrant and Access approval Cleared 8/17/2018 GEORGE SUCHAND
Trees in Parkway Cleared 8/17/2018 TARIK SAOUD
CPC Cleared 8/22/2018 SARAH GOLDMAN
BHO/Hillside ordinance Cleared 10/9/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 10/9/2018 CHRISTOPHER LAW
BHO/Hillside ordinance Cleared 10/9/2018 CHRISTOPHER LAW
Low Impact Development Cleared 10/9/2018 MARTIN FRAGOSO
Green Code Cleared 10/11/2018 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 10/25/2018 HISASHI KOBAYAKAWA
Permit Cleared 10/25/2018 HISASHI KOBAYAKAWA
Sewer availability Cleared 10/25/2018 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 10/31/2018 CALOSHA APPROVED
Grading Pre-Inspection Cleared 10/31/2018 TARIK SAOUD
Drainage to Storm Drain Cleared 11/8/2018 STEVEN JIN
Miscellaneous Cleared 11/8/2018 STEVEN JIN
Roof/Waste drainage to street Cleared 11/8/2018 STEVEN JIN

Contact Information

Architect Ungar,, Kenneth Joel; Lic. No.: C21777 988 COUNTRY VALLEY ROAD      WESTLAKE VILLAGE, CA 91362
Contractor Shain Development Inc; Lic. No.: 937795-B 14401 VILLA WOODS PLACE      PACIFIC PALISADES, CA 90272
Engineer Danz,, Joshua Franklin; Lic. No.: C84764 932 WITHERSPOON DRIVE      THOUSAND OAKS, CA 91360
Engineer Padilla,, Juan C; Lic. No.: C79760 647 ERBES ROAD      THOUSAND OAKS, CA 91362
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/31/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 2/18/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/20/2020 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/20/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/27/2020 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/16/2020 Partial Approval CARLOS MATAMOROS
Grounding or Bonding 4/16/2020 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 4/21/2020 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/29/2020 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/30/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/1/2020 Conditional Approval CARLOS MATAMOROS
Underground Mechanical 5/15/2020 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 5/19/2020 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 5/27/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Approved CARLOS MATAMOROS
Green Building Rough 5/27/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection CARLOS MATAMOROS
Masonry Wall/Backfill 6/9/2020 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/7/2020 Partial Approval CARLOS MATAMOROS
Sewer 7/13/2020 Approved CARLOS MATAMOROS
Underground Mechanical 7/13/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/29/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/15/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 10/27/2020 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/27/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval CARLOS MATAMOROS
Sewer 11/13/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Approved CARLOS MATAMOROS
Green Building Rough 11/16/2020 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 11/16/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 11/19/2020 Corrections Issued CARLOS MATAMOROS
Deputy Steel/Welding 12/9/2020 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 12/11/2020 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 12/15/2020 Conditional Approval CARLOS MATAMOROS
Interior/Exterior Lathing 12/23/2020 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 1/11/2021 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/14/2021 Approved CARLOS MATAMOROS
HVAC-Rough 1/15/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/20/2021 Approved CARLOS MATAMOROS
Green Building Rough 1/20/2021 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/20/2021 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/25/2021 Partial Approval CARLOS MATAMOROS
Shower Pan 1/28/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/19/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 2/25/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 3/4/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 3/5/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/5/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/19/2021 Not Ready for Inspection CARLOS MATAMOROS
Insulation 3/31/2021 Approved CARLOS MATAMOROS
Drywall Nailing 4/20/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/20/2021 Approved CARLOS MATAMOROS
Drywall Nailing 4/23/2021 Approved CARLOS MATAMOROS
Sewer 5/19/2021 Partial Approval CARLOS MATAMOROS
Underground Mechanical 6/15/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/16/2021 Partial Approval CARLOS MATAMOROS
Sewer 7/16/2021 Approved CARLOS MATAMOROS
Underground Mechanical 7/16/2021 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 7/21/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/23/2021 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 7/23/2021 Approved CARLOS MATAMOROS
Gas Test 10/26/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 1/26/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 1/27/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/28/2022 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 3/9/2022 Approved CARLOS MATAMOROS
Green Building Final 3/22/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 4/8/2022 Corrections Issued CARLOS MATAMOROS
HVAC-Final 4/8/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 4/13/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 4/14/2022 Approved CARLOS MATAMOROS
Service/Power Release 4/14/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Required GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 4/26/2022 Approved CARLOS MATAMOROS
Final 5/13/2022 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 5/13/2022 Approved CARLOS MATAMOROS
Smoke Detectors 5/13/2022 Approved CARLOS MATAMOROS
Final 5/24/2022 Corrections Issued CARLOS MATAMOROS
Final 8/22/2022 Partial Approval CARLOS MATAMOROS