1461 N RISING GLEN ROAD 90069

Certificate Information: 1461 N RISING GLEN ROAD 90069

Application / Permit
18010-30000-03032
Plan Check / Job No.
B18WL03951
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 3/18/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2018 APPLICANT
Green Plans Picked Up 7/9/2018 APPLICANT
Assigned to Plan Check Engineer 7/27/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 7/31/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/1/2018 JASON HEALEY
Building Plans Picked Up 8/2/2018 APPLICANT
Applicant returned to address corrections 9/11/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/25/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/29/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/12/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/5/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/18/2019 KAMRAN GHOTBI RAVANDI
Issued 3/18/2019 LADBS
CofO in Progress 10/22/2021 BRAD BESCOS
Permit Finaled 10/27/2021 DEROLD HAUFF
CofO Issued 10/27/2021 DEROLD HAUFF
Permit Finaled 10/27/2021 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/9/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 8/9/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/9/2018 ADRIAN SANCHEZ
Permit Cleared 8/9/2018 ADRIAN SANCHEZ
Sewer availability Cleared 8/9/2018 ADRIAN SANCHEZ
ZI Cleared 8/9/2018 BRIAN CARR
Trees in Parkway Cleared 8/23/2018 LUIS TORRES
Hydrant and Access approval Cleared 9/20/2018 GEORGE SUCHAND
Green Code Cleared 10/11/2018 DONALD CRICHLOW
Low Impact Development Cleared 11/30/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/29/2019 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 2/12/2019 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Garcia, Lionel Jesus; Lic. No.: S4653 23890 HAWTHORNE BLVD      TORRANCE, CA 90505
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/28/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 3/29/2019 Conditional Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/18/2019 Not Ready for Inspection DANNY TOLENTINO
Special/Order Compliance 4/26/2019 Approved DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 4/30/2019 Partial Approval DANNY TOLENTINO
Special/Order Compliance 5/1/2019 Approved DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 6/5/2019 Corrections Issued DANNY TOLENTINO
Footing/Foundation/Slab 6/20/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 6/21/2019 No Access for Inspection DANNY TOLENTINO
Special/Order Compliance 8/6/2019 Partial Inspection RICHARD STEINBACH
Footing/Foundation/Slab 8/22/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 8/27/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/3/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 9/5/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 9/30/2019 Conditional Approval RICHARD STEINBACH
Reinforced Concrete Frame 10/3/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/6/2019 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/24/2020 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 3/27/2020 Conditional Approval ROBERT CORNELL
Special/Order Compliance 4/1/2020 Approved STUART CHAPMAN
Wood Frame 4/1/2020 Partial Approval ROBERT CORNELL
ELECTRICAL-Rough 5/1/2020 Corrections Issued RAUL BARAJAS
HVAC-Rough 5/1/2020 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 5/1/2020 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 5/21/2020 Approved RAUL BARAJAS
ELECTRICAL-Rough 5/21/2020 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Conditional Approval RAUL BARAJAS
Green Building Rough 5/21/2020 Approved RAUL BARAJAS
HVAC-Rough 5/21/2020 Approved RAUL BARAJAS
PLUMBING-Rough 5/21/2020 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 5/21/2020 Approved RAUL BARAJAS
Insulation 6/4/2020 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 6/12/2020 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/15/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/30/2020 Partial Approval CHRISTOPHER DELLEFIELD
Special/Order Compliance 7/10/2020 Partial Inspection RAUL BARAJAS
Special/Order Compliance 7/22/2020 Partial Inspection BRIAN SULLIVAN
Gas Test 8/4/2020 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 10/7/2020 Approved RAUL BARAJAS
Service/Power Release 11/25/2020 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 2/16/2021 Corrections Issued RAUL BARAJAS
Final 3/4/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 3/4/2021 Approved RAUL BARAJAS
Green Building Final 3/4/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 3/4/2021 Partial Inspection RAUL BARAJAS
Smoke Detectors 3/4/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 3/15/2021 Corrections Issued RAUL BARAJAS
Enclosure/Fence 3/23/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 3/24/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 3/25/2021 Approved RAUL BARAJAS
Enclosure/Fence 4/6/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 4/6/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 7/6/2021 Approved RAUL BARAJAS
Final 7/6/2021 Corrections Issued RAUL BARAJAS
Green Building Final 7/6/2021 Approved RAUL BARAJAS
HVAC-Final 7/6/2021 Approved RAUL BARAJAS
PLUMBING-Final 7/6/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 7/6/2021 Approved RAUL BARAJAS
Final 8/3/2021 Corrections Issued RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved RICHARD STEINBACH
Final 10/21/2021 OK to Issue CofO BRAD BESCOS