4320 S INGLEWOOD BLVD 90066
Certificate Information: 4320 S INGLEWOOD BLVD 90066
- Application / Permit
- 18010-30000-02959
- Plan Check / Job No.
- B18WL03906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 4-STORY TYPE VB 14-UNIT APARTMENT BUILDING WITH PARKING GARAGE SPRINKLERED THROUGHOUT WITH NFPA-13
- Permit Issued
- Issued on 7/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2018 | SERGIO SILVA |
| Corrections Issued | 8/17/2018 | SERGIO SILVA |
| Quality Review Completed | 8/24/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/10/2018 | SERGIO SILVA |
| Applicant returned to address corrections | 2/5/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 2/13/2019 | SERGIO SILVA |
| Green Plans Picked Up | 10/22/2019 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | SERGIO SILVA |
| Plan Check Approved | 4/15/2020 | SERGIO SILVA |
| Issued | 7/6/2020 | APPLICANT |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| CofO in Progress | 8/29/2023 | GRANT WOODS |
| Permit Finaled | 9/15/2023 | DAVID TSAU |
| CofO Issued | 9/15/2023 | DAVID TSAU |
| Permit Finaled | 9/15/2023 | DAVID TSAU |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/31/2019 | ROBERT DUFF |
| Address approval | Cleared | 2/20/2019 | JEANETTE VONG |
| Permit | Cleared | 2/20/2019 | JEANETTE VONG |
| DAS Clearance | Cleared | 3/6/2019 | SERGIO SILVA |
| Fire Marshall Fire Life Safety | Cleared | 4/19/2019 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 9/17/2019 | RYAN HUDSON |
| Highway dedication | Cleared | 11/13/2019 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 11/19/2019 | CATHERINE ADROVER |
| Sewer availability | Cleared | 11/19/2019 | CATHERINE ADROVER |
| Bicycle Parking | Cleared | 11/20/2019 | VALERIA CEJA |
| Driveway location | Cleared | 11/20/2019 | VALERIA CEJA |
| Miscellaneous | Cleared | 11/20/2019 | VALERIA CEJA |
| Specific Plan | Cleared | 11/20/2019 | VALERIA CEJA |
| Green Code | Cleared | 11/21/2019 | RICHARD GARCIA |
| Frnt yard landscape/Water mgmt | Cleared | 11/25/2019 | SARAHI ORTEGA |
| Opn space landscape/Water mgmt | Cleared | 11/25/2019 | SARAHI ORTEGA |
| Trees in Parkway | Cleared | 12/2/2019 | JOHN KIM |
| Housing rent stabilization | Cleared | 3/10/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Beton Construction Inc; Lic. No.: 739823-B | 13024 SKY VALLEY RD LOS ANGELES, CA 90049 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2021 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/14/2021 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/15/2021 | Approved | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 6/28/2021 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 8/12/2021 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 9/28/2021 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 10/6/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 10/7/2021 | Partial Approval | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Approval | NICK LAROCCA |
| Special/Order Compliance | 2/14/2022 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Order to Comply Issued | GRANT WOODS |
| Special/Order Compliance | 2/25/2022 | Approved | GRANT WOODS |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 3/18/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 3/18/2022 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 4/6/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 4/6/2022 | Approved | DERRICK SPENCER |
| Wood Frame | 4/6/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Insulation | 4/12/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 6/24/2022 | Approved | DERRICK SPENCER |
| Green Building Rough | 7/5/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Interior/Exterior Lathing | 7/5/2022 | Approved | DERRICK SPENCER |
| Wood Frame | 7/5/2022 | Partial Approval | DERRICK SPENCER |
| Insulation | 7/14/2022 | Partial Approval | DAVID TSAU |
| Insulation | 7/18/2022 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 7/18/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 7/25/2022 | Partial Approval | GRANT WOODS |
| Green Building Rough | 7/25/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 7/29/2022 | Partial Approval | GRANT WOODS |
| Green Building Rough | 7/29/2022 | Not Ready for Inspection | GRANT WOODS |
| Interior/Exterior Lathing | 8/17/2022 | Partial Approval | GRANT WOODS |
| Interior/Exterior Lathing | 8/31/2022 | Approved | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/21/2022 | Partial Approval | GRANT WOODS |
| Masonry Wall/Backfill | 12/30/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 7/21/2023 | Approved | NICK LAROCCA |
| Final | 7/21/2023 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 7/21/2023 | Approved | NICK LAROCCA |
| Green Building Final | 7/21/2023 | Approved | NICK LAROCCA |
| Green Building Rough | 7/21/2023 | Approved | NICK LAROCCA |
| Reinforced Concrete Frame | 7/21/2023 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 7/21/2023 | Approved | NICK LAROCCA |
| Wood Frame | 7/21/2023 | Approved | NICK LAROCCA |
| Final | 8/15/2023 | Conditional Approval | GRANT WOODS |
| Final | 8/17/2023 | Not Ready for Inspection | GRANT WOODS |