10281 W CHARING CROSS ROAD 90024
Certificate Information: 10281 W CHARING CROSS ROAD 90024
- Application / Permit
- 18010-30000-02802
- Plan Check / Job No.
- B18WL03770
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW ONE STORY ACCESSORY LIVING QUARTER. Type IB Construction per Fire Department.
- Permit Issued
- Issued on 12/12/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/12/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/13/2018 | APPLICANT |
| Green Plans Picked Up | 7/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | TSE MING HUANG |
| Corrections Issued | 8/6/2018 | TSE MING HUANG |
| Quality Review Completed | 8/7/2018 | RODOLFO ARIAS |
| Building Plans Picked Up | 8/9/2018 | APPLICANT |
| Applicant returned to address corrections | 10/12/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 11/28/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 12/14/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 12/17/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 12/28/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 1/8/2019 | TSE MING HUANG |
| Applicant returned to address corrections | 1/15/2019 | TSE MING HUANG |
| Applicant returned to address corrections | 2/11/2019 | TSE MING HUANG |
| Applicant returned to address corrections | 2/12/2019 | TSE MING HUANG |
| Applicant returned to address corrections | 2/22/2019 | TSE MING HUANG |
| Plan Check Approved | 4/16/2019 | TSE MING HUANG |
| Issued | 12/12/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2018 | PAMELA TENEZA |
| Permit | Cleared | 10/18/2018 | ADRIAN SANCHEZ |
| Street width determination | Cleared | 10/18/2018 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 12/14/2018 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 12/14/2018 | JOHN KIM |
| Low Impact Development | Cleared | 3/8/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/8/2019 | ZIXUAN CHEN |
| Green Code | Cleared | 3/12/2019 | RICHARD GARCIA |
| Landscape for retaining wall | Cleared | 3/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 3/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 3/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 3/12/2019 | SARAH GOLDMAN |
| Excavation more than 5-ft deep | Cleared | 4/16/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/16/2019 | RODOLFO ARIAS |
| Grading Pre-Inspection | Cleared | 4/16/2019 | TSE MING HUANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/28/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/8/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 6/9/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/18/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 9/27/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | MICHAEL PELHAM |
| Underground Mechanical | 10/5/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 11/2/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 11/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/1/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Sewer | 2/29/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/18/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/22/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/29/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 5/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 5/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/27/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/1/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/24/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Insulation | 8/22/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/18/2024 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/15/2024 | Approved | CHRISTOPHER WILSON |
| Insulation | 12/2/2024 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/2/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/16/2025 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/17/2025 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/17/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 1/17/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 1/31/2025 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/31/2025 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 2/10/2025 | Approved | SEAN HAUPT |
| Insulation | 2/10/2025 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/25/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 2/25/2025 | Approved | CHRISTOPHER WILSON |
| Underground Mechanical | 2/28/2025 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 3/10/2025 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/24/2025 | Approved | SEAN HAUPT |
| Gas Test | 1/23/2026 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/23/2026 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 1/29/2026 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/29/2026 | Approved | CHRISTOPHER WILSON |