9230 W NIGHTINGALE DR 90069

Certificate Information: 9230 W NIGHTINGALE DR 90069

Application / Permit
18010-30000-02336
Plan Check / Job No.
B18WL03271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 12/3/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2018 APPLICANT
Assigned to Plan Check Engineer 6/21/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 6/25/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 6/27/2018 JASON HEALEY
Building Plans Picked Up 6/28/2018 APPLICANT
Applicant returned to address corrections 7/31/2018 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 8/7/2018 APPLICANT
Applicant returned to address corrections 8/21/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/5/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/19/2018 KAMRAN GHOTBI RAVANDI
Issued 12/3/2018 LADBS
CofO in Progress 8/4/2022 RUBEN SALAS
CofO in Progress 8/4/2022 RUBEN SALAS
Permit Finaled 8/4/2022 DEROLD HAUFF
CofO Issued 8/4/2022 DEROLD HAUFF
Permit Finaled 8/4/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/12/2018 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 7/12/2018 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 7/12/2018 MARKOS PEREZ-BRAN
Permit Cleared 7/12/2018 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 7/13/2018 JOHN CONNEALLY
Mechanical Car Lift Cleared 7/13/2018 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 9/4/2018 MICHAEL CASTILLO
Green Code Cleared 9/4/2018 KAMRAN GHOTBI RAVANDI
Low Impact Development Cleared 9/4/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/4/2018 MICHAEL CASTILLO
Sewer availability Cleared 9/4/2018 MICHAEL CASTILLO
CPC Cleared 9/5/2018 TREVOR MARTIN
Excavation more than 5-ft deep Cleared 9/19/2018 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/28/2019 Not Ready for Inspection DANNY TOLENTINO
Deputy Reinf. Concrete 2/21/2019 Conditional Approval DANNY TOLENTINO
Piling/Pier/Caisson 2/21/2019 Partial Inspection DANNY TOLENTINO
Deputy Other (see comments) 2/22/2019 Conditional Approval DANNY TOLENTINO
Deputy Reinf. Concrete 2/22/2019 Conditional Approval DANNY TOLENTINO
Piling/Pier/Caisson 2/22/2019 Not Ready for Inspection DANNY TOLENTINO
Deputy Reinf. Concrete 2/26/2019 No Access for Inspection DANNY TOLENTINO
Piling/Pier/Caisson 2/27/2019 Not Ready for Inspection DANNY TOLENTINO
Piling/Pier/Caisson 3/1/2019 Not Ready for Inspection DANNY TOLENTINO
Piling/Pier/Caisson 3/12/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 3/14/2019 Approved DANNY TOLENTINO
Piling/Pier/Caisson 3/14/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 3/27/2019 Conditional Approval DANNY TOLENTINO
Deputy Steel/Welding 4/3/2019 Conditional Approval DANNY TOLENTINO
Deputy Steel/Welding 4/4/2019 Corrections Issued DANNY TOLENTINO
Footing/Foundation/Slab 4/4/2019 Approved DANNY TOLENTINO
Deputy Steel/Welding 4/5/2019 Conditional Approval DANNY TOLENTINO
Deputy Steel/Welding 4/8/2019 Conditional Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 4/26/2019 Partial Inspection DANNY TOLENTINO
ELECTRICAL-Rough 5/1/2019 Corrections Issued DANNY TOLENTINO
Deputy Reinf. Concrete 5/9/2019 Approved DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/9/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 5/10/2019 Conditional Approval DANNY TOLENTINO
Deputy Shotcrete 5/13/2019 Conditional Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/13/2019 Not Ready for Inspection DANNY TOLENTINO
Deputy Steel/Welding 5/15/2019 Conditional Approval DANNY TOLENTINO
PLUMBING-Rough 5/24/2019 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/29/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 6/12/2019 Approved DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 6/12/2019 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 6/28/2019 Partial Approval DANNY TOLENTINO
Deputy Shotcrete 7/3/2019 Conditional Approval DANNY TOLENTINO
Deputy Shotcrete 7/8/2019 Conditional Approval RICHARD STEINBACH
Pre-Inspection 7/8/2019 Partial Inspection RICHARD STEINBACH
Deputy Steel/Welding 7/17/2019 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 7/23/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 7/25/2019 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/26/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 7/29/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 7/29/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 7/31/2019 Conditional Approval RICHARD STEINBACH
Wood Frame 8/12/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 8/16/2019 Conditional Approval RICHARD STEINBACH
Wood Frame 8/16/2019 Partial Approval RICHARD STEINBACH
Deputy Other (see comments) 8/28/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 8/28/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 9/17/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 9/20/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 9/26/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 10/23/2019 Partial Approval ROBERT CORNELL
PLUMBING-Rough 10/25/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 10/29/2019 Partial Approval ROBERT CORNELL
Excavation/Setback/Form/Re-Bar 10/31/2019 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 11/1/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 11/5/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 11/6/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 11/8/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 11/13/2019 Conditional Approval RICHARD STEINBACH
Piling/Pier/Caisson 11/18/2019 No Access for Inspection ROBERT CORNELL
Deputy Drilled-In Anchors 11/21/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 11/21/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 11/25/2019 Conditional Approval RICHARD STEINBACH
Deputy Other (see comments) 12/4/2019 Conditional Approval RICHARD STEINBACH
Deputy Shotcrete 12/5/2019 Conditional Approval RICHARD STEINBACH
Deputy Other (see comments) 12/18/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 12/18/2019 Partial Approval RICHARD STEINBACH
Deputy Other (see comments) 1/7/2020 Conditional Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 1/10/2020 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 1/16/2020 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 1/21/2020 Partial Approval RICHARD STEINBACH
Deputy Other (see comments) 1/22/2020 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 1/22/2020 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 1/24/2020 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/24/2020 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 1/29/2020 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 2/3/2020 Partial Approval RICHARD STEINBACH
Deputy Steel/Welding 2/3/2020 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 2/3/2020 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 2/4/2020 Conditional Approval ROBERT CORNELL
Deputy Other (see comments) 2/18/2020 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 2/19/2020 Conditional Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 2/24/2020 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 2/27/2020 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 2/27/2020 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 3/2/2020 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 3/4/2020 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 3/12/2020 Not Ready for Inspection ROBERT CORNELL
Footing/Foundation/Slab 3/20/2020 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 3/23/2020 Conditional Approval ROBERT CORNELL
Deputy Reinf. Concrete 3/23/2020 Conditional Approval ROBERT CORNELL
Footing/Foundation/Slab 3/27/2020 Partial Approval ROBERT CORNELL
Deputy Other (see comments) 4/2/2020 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/29/2020 Partial Approval RAUL BARAJAS
Deputy Shotcrete 5/5/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Other (see comments) 5/19/2020 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/19/2020 Approved RAUL BARAJAS
Deputy Shotcrete 5/20/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 6/3/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/11/2020 Partial Approval RAUL BARAJAS
Deputy Shotcrete 6/12/2020 Approved CHRISTOPHER DELLEFIELD
Deputy Reinf. Concrete 6/15/2020 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 6/23/2020 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/29/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 6/30/2020 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/1/2020 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Steel/Welding 7/2/2020 No Access for Inspection RAUL BARAJAS
Deputy Steel/Welding 7/6/2020 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Steel/Welding 7/7/2020 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 7/8/2020 No Access for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/10/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/10/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 7/17/2020 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/21/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Steel/Welding 7/21/2020 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 7/21/2020 Conditional Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/21/2020 Partial Inspection RAUL BARAJAS
Deputy Steel/Welding 7/22/2020 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Corrections Issued RAUL BARAJAS
Wood Frame 7/22/2020 Corrections Issued RAUL BARAJAS
Deputy Steel/Welding 7/23/2020 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/24/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Steel/Welding 7/28/2020 No Access for Inspection RAUL BARAJAS
Deputy Steel/Welding 7/29/2020 No Access for Inspection RAUL BARAJAS
Deputy Steel/Welding 7/30/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 7/31/2020 No Access for Inspection ELMER BLAND
HVAC-Final 8/7/2020 Corrections Issued RAUL BARAJAS
HVAC-Rough 8/7/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 8/12/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 8/12/2020 Corrections Issued RAUL BARAJAS
Deputy Wood Construction 8/21/2020 Conditional Approval DAVID MATSON
HVAC-Rough 8/26/2020 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 8/26/2020 Partial Inspection RAUL BARAJAS
HVAC-Rough 9/4/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 9/4/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 9/18/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/6/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/13/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 10/13/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/13/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 10/21/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/29/2020 Partial Approval RAUL BARAJAS
Sewer 10/29/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 11/2/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/4/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 11/4/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/5/2020 Partial Approval RAUL BARAJAS
Light Gage Steel Frame 11/5/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 11/5/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 11/9/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection RAUL BARAJAS
Gas Test 11/10/2020 Not Ready for Inspection RAUL BARAJAS
Grounding or Bonding 11/10/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 11/10/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 11/10/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 11/12/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 11/13/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/13/2020 Approved JOSEPH MCGARRY
Gas Test 11/13/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 11/13/2020 Approved JOSEPH MCGARRY
Deputy Steel/Welding 11/20/2020 No Access for Inspection ELMER BLAND
Deputy Steel/Welding 11/24/2020 No Access for Inspection ELMER BLAND
Gas Test 12/11/2020 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 12/11/2020 Partial Inspection RAUL BARAJAS
Gas Test 12/23/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 12/23/2020 Approved RAUL BARAJAS
PLUMBING-Rough 12/23/2020 Not Ready for Inspection RAUL BARAJAS
Gas Test 12/29/2020 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 12/29/2020 Corrections Issued RAUL BARAJAS
Gas Test 1/6/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/6/2021 Approved RAUL BARAJAS
Insulation 1/20/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/20/2021 Partial Approval RAUL BARAJAS
Drywall Nailing 1/28/2021 Approved RAUL BARAJAS
Green Building Rough 1/28/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/28/2021 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 2/3/2021 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 2/22/2021 Approved RAUL BARAJAS
Sewer 2/22/2021 Approved RAUL BARAJAS
Deputy Other (see comments) 2/25/2021 Conditional Approval RAUL BARAJAS
Grounding or Bonding 3/16/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/16/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 4/5/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 4/5/2021 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 4/9/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 4/9/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/29/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/4/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 5/4/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 7/22/2021 Not Ready for Inspection RICHARD STEINBACH
Interior/Exterior Lathing 7/27/2021 Partial Approval RICHARD STEINBACH
HVAC-Final 8/10/2021 Partial Inspection RICHARD STEINBACH
Service/Power Release 10/6/2021 Approved RAUL BARAJAS
Enclosure/Fence 1/11/2022 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 1/11/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 1/24/2022 Approved AMY COLIN
Enclosure/Fence 2/17/2022 Approved RAUL BARAJAS
PLUMBING-Final 3/11/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 3/15/2022 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 3/25/2022 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 3/30/2022 Approved RAUL BARAJAS
HVAC-Final 4/1/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 4/26/2022 Not Ready for Inspection RAUL BARAJAS
Final 4/26/2022 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/26/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Final 4/26/2022 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 4/26/2022 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 4/26/2022 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 4/26/2022 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 4/28/2022 Approved RAUL BARAJAS
Final 4/28/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 4/28/2022 Approved RAUL BARAJAS
Green Building Final 4/28/2022 Approved RAUL BARAJAS
Reinforced Concrete Frame 4/28/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 4/28/2022 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 4/28/2022 Approved RAUL BARAJAS
Gas Test 5/16/2022 Approved RAUL BARAJAS
Final 8/4/2022 OK to Issue CofO RUBEN SALAS