1534 N BEVERLY DR 90210
Certificate Information: 1534 N BEVERLY DR 90210
- Application / Permit
- 18010-30000-02321
- Plan Check / Job No.
- B18WL03246
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Current Status
- CofO Issued on 11/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 6/19/2018 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/13/2018 | JASON HEALEY |
| Applicant returned to address corrections | 3/28/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/13/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/16/2019 | APPLICANT |
| Applicant returned to address corrections | 10/18/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/3/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/12/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/23/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 9/18/2020 | APPLICANT |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| CofO in Progress | 10/18/2023 | RAUL BARAJAS |
| CofO Issued | 11/7/2023 | DEROLD HAUFF |
| Permit Finaled | 11/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 6/21/2018 | LOURDES RAMIRO |
| BHO/Hillside ordinance | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| Permit | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/21/2018 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 12/27/2018 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/11/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/11/2019 | ADRIAN SANCHEZ |
| Watercourse | Cleared | 6/20/2019 | OSCAR GUTIERREZ |
| Address approval | Cleared | 7/16/2019 | CHRISTOPHER LAW |
| Green Code | Cleared | 10/25/2019 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 12/23/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Rezvani, Farbod; Lic. No.: C32315 | 2007 COLDWATER CYN BEVERLY HILLS, CA 90210 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Govil, Sanjay; Lic. No.: GE2382 | 4 TULAROSA COURT ALISO VIEJO, CA 92656 |
| Geologist | Burrows, Edward Louis; Lic. No.: EG1750 | 1303 E PALLARES LN PLACENTIA, CA 92870 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2020 | Partial Inspection | RAUL BARAJAS |
| FLOOD-Elevation Certificate | 12/31/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/31/2020 | Partial Inspection | RAUL BARAJAS |
| Special/Order Compliance | 1/13/2021 | Corrections Issued | RAUL BARAJAS |
| FLOOD-Elevation Certificate | 2/11/2021 | Approved | RAUL BARAJAS |
| Reinforced Concrete Frame | 2/11/2021 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 3/11/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/9/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/16/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Corrections Issued | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 2/3/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 2/3/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/18/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/22/2022 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 4/22/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 4/22/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | RAUL BARAJAS |
| FLOOD-Proofing Certificate | 5/26/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 5/26/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/26/2022 | Approved | RAUL BARAJAS |
| Sewer | 5/26/2022 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/26/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/30/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 7/15/2022 | Approved | RAUL BARAJAS |
| Pre-Inspection | 4/19/2023 | Partial Inspection | RAUL BARAJAS |
| Final | 8/15/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 8/15/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 8/15/2023 | Approved | RAUL BARAJAS |
| Final | 9/20/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 9/20/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 9/28/2023 | Approved | RAUL BARAJAS |
| Final | 9/28/2023 | Corrections Issued | RAUL BARAJAS |
| HVAC-Final | 9/28/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 9/28/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 9/28/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 10/18/2023 | Approved | RAUL BARAJAS |
| Final | 10/18/2023 | OK to Issue CofO | RAUL BARAJAS |
| HVAC-Final | 10/18/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 10/18/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 10/18/2023 | Approved | RAUL BARAJAS |