250 S ROCKINGHAM AVE 90049

Certificate Information: 250 S ROCKINGHAM AVE 90049

Application / Permit
18010-30000-02263
Plan Check / Job No.
B18WL03181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD over Basement.
Permit Issued
Issued on 9/24/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2018 APPLICANT
Green Plans Picked Up 6/4/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 KRIKOR MANOUKIAN
Corrections Issued 7/11/2018 KRIKOR MANOUKIAN
Quality Review Completed 7/19/2018 TARIK SAOUD
Building Plans Picked Up 7/20/2018 APPLICANT
Applicant returned to address corrections 8/1/2018 KRIKOR MANOUKIAN
Applicant returned to address corrections 8/2/2018 KRIKOR MANOUKIAN
Applicant returned to address corrections 8/8/2018 KRIKOR MANOUKIAN
Plan Check Approved 9/24/2018 KRIKOR MANOUKIAN
Issued 9/24/2018 LADBS
CofO in Progress 12/30/2022 KEVIN SARGSYAN
Permit Finaled 1/5/2023 DANIEL ORRANTE
CofO Issued 1/5/2023 DANIEL ORRANTE
Permit Finaled 1/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/7/2018 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 8/7/2018 STEVEN JIN
Hydrant and Access approval Cleared 8/7/2018 GEORGE SUCHAND
Sewer availability Cleared 8/7/2018 MAHELET GEBEYHU
Disturb/Remove Protected Trees Cleared 8/30/2018 LUIS TORRES
Trees in Parkway Cleared 8/31/2018 LUIS TORRES
Green Code Cleared 9/12/2018 RICHARD GARCIA
Low Impact Development Cleared 9/13/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 9/19/2018 KARAN PATEL
Building over 3-story or 36-ft Cleared 9/24/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/24/2018 CALOSHA APPROVED
GPI Written Notices Cleared 9/24/2018 KRIKOR MANOUKIAN
Grading Pre-Inspection Cleared 9/24/2018 KRIKOR MANOUKIAN

Contact Information

Architect , ; Lic. No.: C21731 1419-A CLOVERFIELD BLVD      SANTA MONICA, CA 90404
Contractor Building Worx Inc; Lic. No.: 901795-B 130 N GLENDORA AVE      GLENDORA, CA 91741
Engineer , ; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Engineer Naraghi-Arani, Kamran; Lic. No.: C40985 30423 CANWOOD STREET SUITE 223      AGOURA HILLS, CA 91301

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/9/2018 Not Ready for Inspection MICHAEL PELHAM
Piling/Pier/Caisson 10/10/2018 Approved DANIEL ORRANTE
Piling/Pier/Caisson 10/12/2018 Approved DANIEL ORRANTE
Underground Mechanical 12/19/2018 Partial Approval RICHARD STEINBACH
Underground Mechanical 12/28/2018 Approved DANIEL ORRANTE
Footing/Foundation/Slab 2/26/2019 Partial Approval KENNETH NAGLE
Reinforced Concrete Frame 3/20/2019 Partial Approval ROBERT SHELLY
Reinforced Concrete Frame 4/18/2019 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval RICHARD STEINBACH
Deputy Steel/Welding 6/19/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 6/21/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/14/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 8/26/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 9/5/2019 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 9/12/2019 Conditional Approval DANNY TOLENTINO
Reinforced Concrete Frame 9/26/2019 Not Ready for Inspection TIM CHRISTENSEN
Reinforced Concrete Frame 9/30/2019 Corrections Issued TIM CHRISTENSEN
Deputy Reinf. Concrete 10/2/2019 Conditional Approval TIM CHRISTENSEN
Reinforced Concrete Frame 10/2/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/15/2019 Partial Approval DANNY TOLENTINO
Reinforced Masonry Frame 10/21/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Conditional Approval DANNY TOLENTINO
PLUMBING-Rough 12/17/2019 Corrections Issued TIM CHRISTENSEN
Deputy Drilled-In Anchors 12/19/2019 Conditional Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 12/19/2019 Conditional Approval TIM CHRISTENSEN
PLUMBING-Rough 12/19/2019 Corrections Issued TIM CHRISTENSEN
Deputy Wood Construction 1/13/2020 No Result Entered VINCENT SCIPIONI
Floor/Roof Diaphrgm/Shear Wall 1/14/2020 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 1/22/2020 Partial Approval TIM CHRISTENSEN
PLUMBING-Rough 1/30/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 2/11/2020 Corrections Issued DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval TIM CHRISTENSEN
HVAC-Rough 2/19/2020 Corrections Issued TIM CHRISTENSEN
Interior/Exterior Lathing 5/20/2020 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 8/27/2020 Approved JOHN KIDWELL
HVAC-Rough 8/27/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/2/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 9/16/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/16/2020 Approved JOHN KIDWELL
Insulation 9/17/2020 Partial Approval JOHN KIDWELL
Deputy Wood Construction 9/18/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 9/18/2020 Approved JOHN KIDWELL
Wood Frame 9/18/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 9/23/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 9/23/2020 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 9/23/2020 Approved JOHN KIDWELL
Insulation 9/30/2020 Corrections Issued TIM CHRISTENSEN
Insulation 10/2/2020 Approved JOHN KIDWELL
Drywall Nailing 10/13/2020 Approved TIM CHRISTENSEN
Shower Pan 11/16/2020 Approved KENNETH NAGLE
Interior/Exterior Lathing 1/15/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 3/26/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 4/21/2021 Corrections Issued JOHN KIDWELL
Underground Mechanical 4/21/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 8/10/2021 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 10/13/2021 Conditional Approval JOHN KIDWELL
PLUMBING-Rough 10/15/2021 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 11/2/2021 Approved JOHN KIDWELL
PLUMBING-Final 3/24/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 4/8/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 4/12/2022 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 4/22/2022 Not Ready for Inspection JUAN VALENZUELA
Gas Test 4/22/2022 Approved JUAN VALENZUELA
PLUMBING-Final 4/22/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 4/25/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 4/26/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 4/26/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 5/13/2022 Approved KENNETH NAGLE
Service/Power Release 5/16/2022 Approved KENNETH NAGLE
HVAC-Final 9/19/2022 Corrections Issued JUAN VALENZUELA
HVAC-Final 10/21/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 12/7/2022 Approved KEVIN SARGSYAN
Final 12/7/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/7/2022 Approved KEVIN SARGSYAN
Green Building Final 12/7/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/7/2022 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 12/7/2022 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/8/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/13/2022 Approved KEVIN SARGSYAN
Final 12/21/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 12/21/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 12/21/2022 Approved KEVIN SARGSYAN
Final 12/27/2022 Corrections Issued KEVIN SARGSYAN
Final 12/29/2022 OK to Issue CofO KEVIN SARGSYAN