515 1/2 S IRVING BLVD 90020
Certificate Information: 515 1/2 S IRVING BLVD 90020
- Application / Permit
- 18010-30000-02155
- Plan Check / Job No.
- B18WL03026
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2-STORY TYPE VB ACCESSORY BUILDING IN REAR. 2-CAR GARAGE WITH ATTACHED 2ND FLOOR ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 5/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2018 | APPLICANT |
| Green Plans Picked Up | 6/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | SERGIO SILVA |
| Corrections Issued | 6/27/2018 | SERGIO SILVA |
| Quality Review Completed | 7/6/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 7/10/2018 | APPLICANT |
| Applicant returned to address corrections | 9/10/2018 | SERGIO SILVA |
| Plan Check Approved | 11/8/2018 | SERGIO SILVA |
| Plan Check Approved | 11/12/2019 | SERGIO SILVA |
| Issued | 5/18/2021 | APPLICANT |
| CofO in Progress | 4/23/2026 | JEFFREY MEAD |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2018 | MICHAEL CASTILLO |
| CPC | Cleared | 8/8/2018 | SOPHIE GABEL-SCHEINBAU |
| CPC | Cleared | 8/8/2018 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2018 | MICHAEL CASTILLO |
| HPOZ | Cleared | 8/8/2018 | MAX LODER |
| Permit | Cleared | 8/8/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 8/8/2018 | MICHAEL CASTILLO |
| ZA Case | Cleared | 8/8/2018 | MAX LODER |
| ZI | Cleared | 8/8/2018 | MAX LODER |
| Low Impact Development | Cleared | 9/6/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/6/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 11/8/2018 | RICHARD GARCIA |
Contact Information
| Architect | 11533, W Pico Blvd; Lic. No.: C24842 | LOS ANGELES, CA 90064 |
| Contractor | Miller Kirk Construction; Lic. No.: 377173-B | 1072 CASITAS PASS RD #288 CARPINTERIA, CA 93013 |
| Engineer | Martinez, Michael Anthony; Lic. No.: S3825 | 902 15TH PLACE HERMOSA BEACH, CA 90254 |
| Engineer | Vondra, Thomas Edwin; Lic. No.: L8761 | 28160 MC BEAN PKWY UNIT 13202 VALENCIA, CA 91354 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 8/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 9/13/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/17/2021 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 9/28/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 11/23/2021 | No Access for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 11/23/2021 | Approved | MASHEL JONGERT |
| BUILDING-Rough-Frame | 1/24/2022 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/24/2022 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 1/24/2022 | Approved | CRAIG DAVIS |
| HVAC-Rough | 1/24/2022 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/24/2022 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 2/2/2022 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 2/8/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 2/24/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Shower Pan | 3/16/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Shower Pan | 3/29/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Shower Pan | 4/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/8/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/8/2023 | Approved | JEFFREY MEAD |
| Final | 2/8/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 2/8/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Service/Power Release | 2/8/2023 | Not Required | JEFFREY MEAD |
| Smoke Detectors | 2/8/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 2/16/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 2/16/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 4/27/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 4/27/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/27/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/27/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | LILIANA PORTILLO |
| Final | 5/5/2023 | Corrections Issued | LILIANA PORTILLO |
| Special/Order Compliance | 5/13/2025 | Corrections Issued | RAUL BARAJAS |
| Final | 11/20/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/27/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 4/2/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/22/2026 | OK to Issue CofO | JEFFREY MEAD |