1034 N NAPOLI DR 90272

Certificate Information: 1034 N NAPOLI DR 90272

Application / Permit
18010-30000-02085
Plan Check / Job No.
B18WL02907
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY 14,683 Sqr Ft SFD W/ BASEMENT AND ATTACHED RECREATION ROOM.
Permit Issued
Issued on 10/2/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 TARIK SAOUD
Green Plans Picked Up 5/25/2018 APPLICANT
Corrections Issued 5/29/2018 TARIK SAOUD
Quality Review Completed 6/8/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/12/2018 DONALD CRICHLOW
Plan Check Approved 9/19/2018 TARIK SAOUD
Issued 10/2/2018 LADBS
Building Plans Picked Up 2/11/2022 APPLICANT
CofO in Progress 8/16/2023 OGANES TARAKHCHYAN
Permit Finaled 9/5/2023 DANIEL ORRANTE
CofO Issued 9/5/2023 DANIEL ORRANTE
Permit Finaled 9/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/13/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 6/13/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 6/13/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 6/13/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/13/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 6/13/2018 ROBERT DUFF
Permit Cleared 6/13/2018 ADRIAN SANCHEZ
Sewer availability Cleared 6/13/2018 ADRIAN SANCHEZ
Construction near power lines Cleared 6/15/2018 WALTER RAMIREZ
Green Code Cleared 7/25/2018 DONALD CRICHLOW
Low Impact Development Cleared 8/15/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 8/15/2018 STEVE MELGAR
Excavation more than 5-ft deep Cleared 8/23/2018 CALOSHA APPROVED
Grading Pre-Inspection Cleared 8/23/2018 TARIK SAOUD

Contact Information

Contractor Owner-Builder       ,
Engineer Shah, Kamal Rajendra; Lic. No.: C46200 28039 SMYTH DR STE 200      VALENCIA, CA 91355

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/31/2018 Not Ready for Inspection MICHAEL PELHAM
Deputy Reinf. Concrete 11/2/2018 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 12/5/2018 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 12/11/2018 Conditional Approval RICHARD STEINBACH
Piling/Pier/Caisson 1/10/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 2/12/2019 Partial Approval KENNETH NAGLE
Deputy Grading 2/27/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 2/27/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 3/29/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/18/2019 Partial Approval KENNETH NAGLE
PLUMBING-Rough 4/18/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 4/25/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 5/17/2019 Partial Approval TIM CHRISTENSEN
Green Building Rough 6/10/2019 Not Ready for Inspection TIM CHRISTENSEN
Reinforced Concrete Frame 6/10/2019 Partial Approval TIM CHRISTENSEN
Verify Sprinkler Sign Off 6/10/2019 Not Ready for Inspection TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/7/2019 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 8/22/2019 Partial Approval DANNY TOLENTINO
Deputy Steel/Welding 9/10/2019 Conditional Approval MICHAEL TEMPLE
PLUMBING-Rough 10/11/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 10/21/2019 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/29/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 11/7/2019 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 1/21/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 1/23/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 2/26/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Approval ROBERT SHELLY
Insulation 3/11/2020 Partial Inspection DANNY TOLENTINO
Insulation 3/18/2020 Partial Approval ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/13/2020 Partial Approval DANNY TOLENTINO
Drywall Nailing 4/21/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/28/2020 Not Ready for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/11/2020 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 6/3/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/15/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/22/2020 Partial Approval JOHN KIDWELL
Green Building Rough 7/1/2020 Not Ready for Inspection JOHN KIDWELL
Reinforced Concrete Frame 7/1/2020 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 7/1/2020 Not Ready for Inspection JOHN KIDWELL
Piling/Pier/Caisson 7/22/2020 Partial Approval ROBERT SHELLY
Deputy Reinf. Concrete 7/27/2020 Corrections Issued ROBERT SHELLY
Piling/Pier/Caisson 7/29/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/10/2020 Partial Approval ROBERT SHELLY
Piling/Pier/Caisson 8/19/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 8/25/2020 Approved JOHN KIDWELL
Piling/Pier/Caisson 8/26/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 9/2/2020 Partial Approval JOHN KIDWELL
HVAC-Rough 9/3/2020 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/8/2020 Partial Approval JOHN KIDWELL
Green Building Rough 9/8/2020 Partial Approval JOHN KIDWELL
Reinforced Concrete Frame 9/8/2020 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 9/8/2020 Not Ready for Inspection JOHN KIDWELL
Piling/Pier/Caisson 9/29/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/2/2020 Partial Approval JOHN KIDWELL
Piling/Pier/Caisson 10/13/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/22/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/28/2020 Partial Approval JOHN KIDWELL
Pre-Inspection 11/6/2020 Partial Inspection JOHN KIDWELL
Footing/Foundation/Slab 11/10/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 11/19/2020 Partial Approval JOHN KIDWELL
Piling/Pier/Caisson 11/30/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 12/1/2020 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 12/4/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 12/8/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 12/11/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/6/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 1/6/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 No Access for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/25/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 2/10/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/11/2021 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 2/16/2021 Partial Approval JOHN KIDWELL
Shower Pan 2/16/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/3/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/10/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 3/15/2021 Partial Approval JOHN KIDWELL
HVAC-Rough 3/15/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/15/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/16/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 4/1/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 4/20/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 4/30/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 5/12/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/19/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/11/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/15/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/24/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/30/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 7/9/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 7/15/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 8/5/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 8/23/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 8/24/2021 Partial Approval JESUS RODRIGUEZ
Gas Test 8/24/2021 Partial Approval JESUS RODRIGUEZ
Pre-Inspection 9/23/2021 Approved JUAN VALENZUELA
Special/Order Compliance 9/27/2021 Partial Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/30/2021 Approved JOHN KIDWELL
Special/Order Compliance 10/7/2021 Partial Inspection JOHN KIDWELL
Special/Order Compliance 10/12/2021 Partial Inspection JOHN KIDWELL
Special/Order Compliance 11/22/2021 Partial Inspection JOHN KIDWELL
Service/Power Release 12/7/2021 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 12/15/2021 Not Ready for Inspection JOHN KIDWELL
Sewer 12/20/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/14/2022 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 1/24/2022 Approved JOHN KIDWELL
HVAC-Rough 1/24/2022 Approved JOHN KIDWELL
Special/Order Compliance 2/4/2022 Partial Inspection JOHN KIDWELL
Special/Order Compliance 2/9/2022 Partial Inspection JOHN KIDWELL
Special/Order Compliance 2/9/2022 Partial Inspection MICHAEL PELHAM
Sewer 2/23/2022 Partial Approval MICHAEL PELHAM
Underground Mechanical 2/23/2022 Partial Approval MICHAEL PELHAM
Special/Order Compliance 3/16/2022 Partial Inspection JOHN KIDWELL
Pre-Inspection 5/18/2022 Partial Inspection JOHN KIDWELL
ELECTRICAL-Final 5/31/2022 Approved JOHN KIDWELL
HVAC-Final 6/14/2022 No Access for Inspection JOHN KIDWELL
Gas Test 6/17/2022 Approved JUAN VALENZUELA
PLUMBING-Final 6/17/2022 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 6/21/2022 Approved JOHN KIDWELL
PLUMBING-Final 6/22/2022 Approved JOHN KIDWELL
Special/Order Compliance 6/28/2022 No Access for Inspection JOHN KIDWELL
Pre-Inspection 6/30/2022 Partial Inspection KENNETH NAGLE
Pre-Inspection 7/5/2022 Partial Inspection JOHN KIDWELL
Final 8/22/2022 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 8/23/2022 Partial Inspection KENNETH NAGLE
Pre-Inspection 9/27/2022 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 3/20/2023 Approved OGANES TARAKHCHYAN
Final 3/20/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/20/2023 Approved OGANES TARAKHCHYAN
Green Building Final 3/20/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 3/20/2023 Approved OGANES TARAKHCHYAN
Reinforced Concrete Frame 3/20/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 3/20/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Structural Steel Frame 3/20/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 3/20/2023 Approved OGANES TARAKHCHYAN
Pre-Inspection 4/19/2023 Partial Inspection STEPHANIE SWANSON
PLUMBING-Rough 5/5/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/23/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 6/20/2023 Approved OGANES TARAKHCHYAN
Service/Power Release 6/27/2023 Approved OGANES TARAKHCHYAN
Smoke Detectors 6/27/2023 Approved OGANES TARAKHCHYAN
Final 7/11/2023 Corrections Issued OGANES TARAKHCHYAN
Final 8/16/2023 OK to Issue CofO OGANES TARAKHCHYAN