9016 W HOPEN PL 90069

Certificate Information: 9016 W HOPEN PL 90069

Application / Permit
18010-30000-01620
Plan Check / Job No.
B18WL02393
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHD GARAGE.
Permit Issued
Issued on 2/26/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2018 APPLICANT
Green Plans Picked Up 5/8/2018 APPLICANT
Assigned to Plan Check Engineer 5/17/2018 KAMRAN GHOTBI RAVANDI
Corrections Issued 5/22/2018 KAMRAN GHOTBI RAVANDI
Quality Review Completed 5/25/2018 JASON HEALEY
Building Plans Picked Up 5/29/2018 APPLICANT
Applicant returned to address corrections 8/24/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/12/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/24/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/13/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/26/2019 KAMRAN GHOTBI RAVANDI
Issued 2/26/2019 LADBS
CofO in Progress 5/24/2023 RAUL BARAJAS
CofO in Progress 5/26/2023 RAUL BARAJAS
CofO in Progress 7/6/2023 RAUL BARAJAS
Permit Finaled 7/14/2023 DEROLD HAUFF
Permit Finaled 7/14/2023 DEROLD HAUFF
CofO Issued 7/14/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/5/2018 MICHAEL CASTILLO
BHO/Hillside ordinance Cleared 6/5/2018 MICHAEL CASTILLO
BHO/Hillside ordinance Cleared 6/5/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 6/5/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 6/5/2018 GEORGE SUCHAND
Permit Cleared 6/5/2018 MICHAEL CASTILLO
Sewer availability Cleared 6/5/2018 MICHAEL CASTILLO
Trees in Parkway Cleared 11/29/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 1/15/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/15/2019 CELINA MORENO
Green Code Cleared 1/17/2019 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 1/24/2019 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 2/21/2019 BOK GOH

Contact Information

Contractor Holz Richard Inc; Lic. No.: 294504-B 520 S SEPULVEDA BLVD #407      LOS ANGELES, CA 90049
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Kwan, Denny Chi-Ho; Lic. No.: S4887 5638 NEWFIELDS LN      DUBLIN, CA 94568
Geologist Hollingsworth, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/22/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 5/10/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 6/20/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 8/5/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/7/2019 Conditional Approval RICHARD STEINBACH
Piling/Pier/Caisson 8/13/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 8/15/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/6/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/17/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 10/3/2019 Partial Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 10/24/2019 Partial Approval RICHARD STEINBACH
Deputy Grading 11/6/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/8/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/21/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 11/21/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 12/20/2019 Partial Approval ROBERT CORNELL
Deputy Reinf. Concrete 12/23/2019 Conditional Approval RICHARD STEINBACH
Deputy Reinf. Concrete 12/24/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 1/2/2020 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 1/8/2020 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 1/15/2020 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 1/22/2020 Partial Approval RICHARD STEINBACH
Deputy Grading 1/31/2020 Conditional Approval RICHARD STEINBACH
Piling/Pier/Caisson 2/14/2020 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 2/19/2020 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/5/2020 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/23/2020 Partial Approval RAUL BARAJAS
Deputy Grading 3/31/2020 Conditional Approval ROBERT CORNELL
Piling/Pier/Caisson 4/16/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 4/23/2020 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 4/23/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/29/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 5/6/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/11/2020 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 5/26/2020 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 5/27/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/5/2020 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 6/11/2020 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 6/18/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 7/1/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/6/2020 Partial Approval CHRISTOPHER DELLEFIELD
Piling/Pier/Caisson 7/7/2020 Partial Approval RAUL BARAJAS
Wood Frame 7/7/2020 Corrections Issued RAUL BARAJAS
Deputy Wood Construction 7/13/2020 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 7/23/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 7/23/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 7/23/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 7/31/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/5/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/17/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/25/2020 Approved RAUL BARAJAS
ELECTRICAL-Rough 9/3/2020 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 9/3/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/15/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 9/30/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/30/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 10/29/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/5/2020 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 11/5/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/17/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/24/2020 No Access for Inspection ELMER BLAND
PLUMBING-Rough 11/24/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/30/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/30/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 12/4/2020 Approved RAUL BARAJAS
HVAC-Rough 12/28/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/15/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 1/25/2021 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/25/2021 Conditional Approval RAUL BARAJAS
Light Gage Steel Frame 1/25/2021 Approved RAUL BARAJAS
Underground Mechanical 1/25/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 2/3/2021 Partial Approval RAUL BARAJAS
Grounding or Bonding 2/9/2021 Partial Inspection RAUL BARAJAS
Gas Test 3/4/2021 Approved RAUL BARAJAS
Green Building Rough 3/4/2021 Partial Approval RAUL BARAJAS
Pool Piping 3/4/2021 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 3/4/2021 Approved RAUL BARAJAS
Drywall Nailing 3/19/2021 Partial Approval RAUL BARAJAS
Green Building Rough 3/19/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/31/2021 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/5/2021 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 5/19/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/26/2021 Approved RAUL BARAJAS
Reinforced Concrete Frame 6/14/2021 Approved RAUL BARAJAS
Wood Frame 6/22/2021 Partial Approval RICHARD STEINBACH
HVAC-Rough 7/8/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 7/14/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 7/14/2021 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 7/23/2021 Corrections Issued RICHARD STEINBACH
Drywall Nailing 9/10/2021 Approved RICHARD STEINBACH
Insulation 9/10/2021 Approved RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Approval RICHARD STEINBACH
Shower Pan 11/24/2021 Approved RAUL BARAJAS
Service/Power Release 12/1/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 12/23/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 1/4/2022 Partial Approval RAUL BARAJAS
Service/Power Release 1/4/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/8/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 3/15/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 9/14/2022 Partial Approval RAUL BARAJAS
Pre-Inspection 10/4/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Final 1/17/2023 Partial Inspection RAUL BARAJAS
PLUMBING-Final 1/18/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 1/24/2023 Approved RAUL BARAJAS
Gas Test 2/27/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 4/18/2023 Approved RAUL BARAJAS
Final 4/18/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Final 4/18/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved RAUL BARAJAS
Smoke Detectors 4/18/2023 Partial Inspection RAUL BARAJAS
Structural Steel Frame 4/18/2023 Approved RAUL BARAJAS
Final 5/24/2023 Corrections Issued RAUL BARAJAS
Smoke Detectors 5/24/2023 Approved RAUL BARAJAS
Final 7/3/2023 OK to Issue CofO RAUL BARAJAS