9016 W HOPEN PL 90069
Certificate Information: 9016 W HOPEN PL 90069
- Application / Permit
- 18010-30000-01620
- Plan Check / Job No.
- B18WL02393
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHD GARAGE.
- Permit Issued
- Issued on 2/26/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2018 | APPLICANT |
| Green Plans Picked Up | 5/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 5/22/2018 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 5/25/2018 | JASON HEALEY |
| Building Plans Picked Up | 5/29/2018 | APPLICANT |
| Applicant returned to address corrections | 8/24/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/12/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/13/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/26/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 2/26/2019 | LADBS |
| CofO in Progress | 5/24/2023 | RAUL BARAJAS |
| CofO in Progress | 5/26/2023 | RAUL BARAJAS |
| CofO in Progress | 7/6/2023 | RAUL BARAJAS |
| Permit Finaled | 7/14/2023 | DEROLD HAUFF |
| Permit Finaled | 7/14/2023 | DEROLD HAUFF |
| CofO Issued | 7/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| BHO/Hillside ordinance | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| BHO/Hillside ordinance | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 6/5/2018 | GEORGE SUCHAND |
| Permit | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 6/5/2018 | MICHAEL CASTILLO |
| Trees in Parkway | Cleared | 11/29/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 1/15/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/15/2019 | CELINA MORENO |
| Green Code | Cleared | 1/17/2019 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 1/24/2019 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 2/21/2019 | BOK GOH |
Contact Information
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | Hollingsworth, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Kwan, Denny Chi-Ho; Lic. No.: S4887 | 5638 NEWFIELDS LN DUBLIN, CA 94568 |
| Geologist | Hollingsworth, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/22/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 5/10/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 6/20/2019 | Partial Approval | DANNY TOLENTINO |
| Piling/Pier/Caisson | 8/5/2019 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/7/2019 | Conditional Approval | RICHARD STEINBACH |
| Piling/Pier/Caisson | 8/13/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 8/15/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/6/2019 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/17/2019 | Partial Approval | RICHARD STEINBACH |
| Piling/Pier/Caisson | 10/3/2019 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 10/24/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Grading | 11/6/2019 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 11/8/2019 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 11/21/2019 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 11/21/2019 | Partial Approval | RICHARD STEINBACH |
| Piling/Pier/Caisson | 12/20/2019 | Partial Approval | ROBERT CORNELL |
| Deputy Reinf. Concrete | 12/23/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 12/24/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/2/2020 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/8/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 1/15/2020 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/22/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Grading | 1/31/2020 | Conditional Approval | RICHARD STEINBACH |
| Piling/Pier/Caisson | 2/14/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 2/19/2020 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 3/5/2020 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 3/23/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Grading | 3/31/2020 | Conditional Approval | ROBERT CORNELL |
| Piling/Pier/Caisson | 4/16/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/23/2020 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/23/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/29/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/6/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/11/2020 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/26/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/27/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/5/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/11/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/18/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/1/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/6/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Piling/Pier/Caisson | 7/7/2020 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 7/7/2020 | Corrections Issued | RAUL BARAJAS |
| Deputy Wood Construction | 7/13/2020 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/23/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/23/2020 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/23/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/31/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/17/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/25/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/3/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 9/3/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/30/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/30/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/29/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/5/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 11/5/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/24/2020 | No Access for Inspection | ELMER BLAND |
| PLUMBING-Rough | 11/24/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/30/2020 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/30/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/4/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 12/28/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/25/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/25/2021 | Conditional Approval | RAUL BARAJAS |
| Light Gage Steel Frame | 1/25/2021 | Approved | RAUL BARAJAS |
| Underground Mechanical | 1/25/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/3/2021 | Partial Approval | RAUL BARAJAS |
| Grounding or Bonding | 2/9/2021 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 3/4/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 3/4/2021 | Partial Approval | RAUL BARAJAS |
| Pool Piping | 3/4/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/4/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 3/19/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 3/19/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/31/2021 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/5/2021 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/19/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/26/2021 | Approved | RAUL BARAJAS |
| Reinforced Concrete Frame | 6/14/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 6/22/2021 | Partial Approval | RICHARD STEINBACH |
| HVAC-Rough | 7/8/2021 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/14/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 7/14/2021 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 7/23/2021 | Corrections Issued | RICHARD STEINBACH |
| Drywall Nailing | 9/10/2021 | Approved | RICHARD STEINBACH |
| Insulation | 9/10/2021 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 11/24/2021 | Approved | RAUL BARAJAS |
| Service/Power Release | 12/1/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 12/23/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/4/2022 | Partial Approval | RAUL BARAJAS |
| Service/Power Release | 1/4/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 10/4/2022 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 1/17/2023 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 1/18/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 1/24/2023 | Approved | RAUL BARAJAS |
| Gas Test | 2/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | RAUL BARAJAS |
| Final | 4/18/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 4/18/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 4/18/2023 | Partial Inspection | RAUL BARAJAS |
| Structural Steel Frame | 4/18/2023 | Approved | RAUL BARAJAS |
| Final | 5/24/2023 | Corrections Issued | RAUL BARAJAS |
| Smoke Detectors | 5/24/2023 | Approved | RAUL BARAJAS |
| Final | 7/3/2023 | OK to Issue CofO | RAUL BARAJAS |