13187 W CHALON ROAD 90049
Certificate Information: 13187 W CHALON ROAD 90049
- Application / Permit
- 18010-30000-01607
- Plan Check / Job No.
- B18WL02373
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2018 | APPLICANT |
| Green Plans Picked Up | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 5/8/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/14/2018 | APPLICANT |
| Quality Review Completed | 7/24/2018 | JASON HEALEY |
| Applicant returned to address corrections | 7/26/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/31/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/6/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/17/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/5/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/26/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/8/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/8/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/14/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/26/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/1/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/12/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/19/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/27/2021 | KAVIAN REFAHI |
| Plan Check Approved | 7/27/2021 | KAVIAN REFAHI |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 6/23/2023 | KENNETH NAGLE |
| Permit Finaled | 6/28/2023 | DANIEL ORRANTE |
| CofO Issued | 6/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/14/2018 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/14/2018 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/14/2018 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2018 | DENNIS BRAGIN |
| Permit | Cleared | 5/14/2018 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 6/29/2021 | MICHAEL SCADUTO |
| Permit | Cleared | 6/29/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 6/29/2021 | NIKTA MOUSAVI |
| Watercourse | Cleared | 6/29/2021 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 6/30/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 7/9/2021 | ROBERT DUFF |
| Excavation more than 5-ft deep | Cleared | 7/12/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/12/2021 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 7/12/2021 | KAVIAN REFAHI |
Contact Information
| Contractor | Tallen & Tyce Development Inc; Lic. No.: 1029383-B | 15260 VENTURA BLVD #845 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/16/2021 | Partial Inspection | JUAN VALENZUELA |
| Pre-Inspection | 9/7/2021 | Partial Inspection | JUAN VALENZUELA |
| Piling/Pier/Caisson | 9/10/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 9/13/2021 | Conditional Approval | JAVIER RAMOS JR |
| Deputy Reinf. Concrete | 9/21/2021 | Conditional Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 9/21/2021 | Partial Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 10/5/2021 | Partial Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 10/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 10/13/2021 | Conditional Approval | JUAN VALENZUELA |
| FLOOD-Elevation Certificate | 10/14/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/14/2021 | Partial Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 10/14/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 10/15/2021 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 11/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 11/8/2021 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/15/2021 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/18/2021 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 11/30/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 11/30/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 12/2/2021 | Conditional Approval | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 12/6/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 12/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Structural Steel Frame | 12/6/2021 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 12/6/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 12/13/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/13/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 12/15/2021 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Masonry | 12/17/2021 | Conditional Approval | MICHAEL PELHAM |
| Masonry Wall/Backfill | 1/3/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 2/1/2022 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/18/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Masonry | 5/5/2022 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 5/10/2022 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Masonry | 5/12/2022 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/12/2022 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 5/12/2022 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 5/16/2022 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 5/17/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/18/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/18/2022 | Approved | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 5/23/2022 | Conditional Approval | JUAN VALENZUELA |
| Gas Test | 5/23/2022 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 5/23/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 5/23/2022 | Approved | JUAN VALENZUELA |
| Deputy Other (see comments) | 5/27/2022 | No Access for Inspection | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/7/2022 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/8/2022 | No Access for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/13/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/13/2022 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 6/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Drywall Nailing | 6/23/2022 | Approved | JUAN VALENZUELA |
| Insulation | 6/23/2022 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 11/17/2022 | Partial Approval | JUAN VALENZUELA |
| HVAC-Final | 5/9/2023 | Approved | KEVIN SARGSYAN |
| Sewer | 5/9/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/10/2023 | Approved | KEVIN SARGSYAN |
| Gas Test | 5/11/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 5/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 5/16/2023 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 5/23/2023 | Approved | KEVIN SARGSYAN |
| Final | 6/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/9/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 6/9/2023 | Approved | KEVIN SARGSYAN |
| Reinforced Concrete Frame | 6/9/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/9/2023 | Approved | KEVIN SARGSYAN |
| Structural Steel Frame | 6/9/2023 | Approved | KEVIN SARGSYAN |
| Final | 6/14/2023 | Conditional Approval | KENNETH NAGLE |