270 S CANYON VIEW DR 90049
Certificate Information: 270 S CANYON VIEW DR 90049
- Application / Permit
- 18010-30000-01600
- Plan Check / Job No.
- B18WL02358
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 7/25/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2018 | SERGIO SILVA |
| Corrections Issued | 6/4/2018 | SERGIO SILVA |
| Quality Review Completed | 6/15/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/15/2018 | APPLICANT |
| Green Plans Picked Up | 3/26/2019 | APPLICANT |
| Applicant returned to address corrections | 4/10/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 4/18/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 4/29/2019 | SERGIO SILVA |
| Plan Check Approved | 5/8/2019 | SERGIO SILVA |
| Issued | 7/25/2019 | LADBS |
| CofO in Progress | 5/18/2021 | JOHN KIDWELL |
| CofO Issued | 7/8/2021 | VINCENT COTTON |
| Permit Finaled | 7/8/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/30/2018 | MITESH PATEL |
| Address approval | Cleared | 9/10/2018 | KATHLEEN HUGHEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2018 | KATHLEEN HUGHEY |
| Sewer availability | Cleared | 9/10/2018 | KRISTEN LY |
| Miscellaneous | Cleared | 11/6/2018 | MARC WOERSCHING |
| Flood clearance | Cleared | 3/1/2019 | KATHLEEN HUGHEY |
| Hydrant and Access approval | Cleared | 3/7/2019 | ROBERT DUFF |
| Miscellaneous | Cleared | 3/18/2019 | KEVIN AZARMAHAN |
| Permit | Cleared | 3/18/2019 | KEVIN AZARMAHAN |
| Roof/Waste drainage to street | Cleared | 3/18/2019 | KEVIN AZARMAHAN |
| Watercourse | Cleared | 3/18/2019 | KEVIN AZARMAHAN |
| Green Code | Cleared | 4/9/2019 | RICHARD GARCIA |
| Miscellaneous | Cleared | 4/10/2019 | SERGIO SILVA |
| GPI Written Notices | Cleared | 4/18/2019 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 4/18/2019 | SERGIO SILVA |
| Miscellaneous | Cleared | 4/29/2019 | SERGIO SILVA |
| Miscellaneous | Cleared | 4/29/2019 | SERGIO SILVA |
Contact Information
| Contractor | Core Development Group Inc; Lic. No.: 845288-B | 1112 MONTANA AVE #204 SANTA MONICA, CA 90403 |
| Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Silverman, Joel Casper; Lic. No.: C16844 | 5727 CANOGA AVENUE 255 WOODLAND HILLS, CA 92367 |
| Engineer | Zweigler, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Zweigler, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 9/4/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 9/4/2019 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 9/24/2019 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 10/4/2019 | Partial Approval | DANNY TOLENTINO |
| Piling/Pier/Caisson | 10/7/2019 | Conditional Approval | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 10/9/2019 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 11/1/2019 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 11/1/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2019 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 11/12/2019 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2020 | Partial Approval | DANNY TOLENTINO |
| Deputy Steel/Welding | 1/28/2020 | No Access for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Approval | DANNY TOLENTINO |
| Sewer | 2/28/2020 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 4/30/2020 | Approved | DANNY TOLENTINO |
| Underground Mechanical | 5/5/2020 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 5/8/2020 | Approved | DANNY TOLENTINO |
| Sewer | 5/8/2020 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 5/8/2020 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 5/20/2020 | Approved | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Corrections Issued | TIM CHRISTENSEN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Verify Sprinkler Sign Off | 5/27/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 6/12/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 6/12/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 6/12/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/18/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 6/18/2020 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 6/18/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/23/2020 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 7/7/2020 | Approved | JOHN KIDWELL |
| Shower Pan | 7/24/2020 | Approved | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 7/29/2020 | Partial Approval | ROBERT SHELLY |
| Interior/Exterior Lathing | 8/6/2020 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 1/28/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 2/16/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 3/1/2021 | Approved | JOHN KIDWELL |
| Final | 5/5/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/5/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 5/5/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/5/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 5/5/2021 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 5/5/2021 | Approved | JOHNNY MIRANDA |
| Final | 5/10/2021 | OK to Issue CofO | JOHN KIDWELL |