270 S CANYON VIEW DR 90049

Certificate Information: 270 S CANYON VIEW DR 90049

Application / Permit
18010-30000-01600
Plan Check / Job No.
B18WL02358
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 4-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 7/25/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 SERGIO SILVA
Corrections Issued 6/4/2018 SERGIO SILVA
Quality Review Completed 6/15/2018 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/15/2018 APPLICANT
Green Plans Picked Up 3/26/2019 APPLICANT
Applicant returned to address corrections 4/10/2019 SERGIO SILVA
Applicant returned to address corrections 4/18/2019 SERGIO SILVA
Applicant returned to address corrections 4/29/2019 SERGIO SILVA
Plan Check Approved 5/8/2019 SERGIO SILVA
Issued 7/25/2019 LADBS
CofO in Progress 5/18/2021 JOHN KIDWELL
CofO Issued 7/8/2021 VINCENT COTTON
Permit Finaled 7/8/2021 VINCENT COTTON

Permit Application Clearance Information

Low Impact Development Cleared 8/30/2018 MITESH PATEL
Address approval Cleared 9/10/2018 KATHLEEN HUGHEY
Eng Process Fee Ord 176,300 Cleared 9/10/2018 KATHLEEN HUGHEY
Sewer availability Cleared 9/10/2018 KRISTEN LY
Miscellaneous Cleared 11/6/2018 MARC WOERSCHING
Flood clearance Cleared 3/1/2019 KATHLEEN HUGHEY
Hydrant and Access approval Cleared 3/7/2019 ROBERT DUFF
Miscellaneous Cleared 3/18/2019 KEVIN AZARMAHAN
Permit Cleared 3/18/2019 KEVIN AZARMAHAN
Roof/Waste drainage to street Cleared 3/18/2019 KEVIN AZARMAHAN
Watercourse Cleared 3/18/2019 KEVIN AZARMAHAN
Green Code Cleared 4/9/2019 RICHARD GARCIA
Miscellaneous Cleared 4/10/2019 SERGIO SILVA
GPI Written Notices Cleared 4/18/2019 SERGIO SILVA
Grading Pre-Inspection Cleared 4/18/2019 SERGIO SILVA
Miscellaneous Cleared 4/29/2019 SERGIO SILVA
Miscellaneous Cleared 4/29/2019 SERGIO SILVA

Contact Information

Contractor Core Development Group Inc; Lic. No.: 845288-B 1112 MONTANA AVE #204      SANTA MONICA, CA 90403
Engineer Babayan, Raffi Samuel; Lic. No.: C72168 1140 N COLUMBUS AVE 112      GLENDALE, CA 91202
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Silverman, Joel Casper; Lic. No.: C16844 5727 CANOGA AVENUE 255      WOODLAND HILLS, CA 92367
Engineer Zweigler, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Zweigler, Robert Ingraham; Lic. No.: EG1210 196 DIRT ROAD      THOUSAND OAKS, CA 91361

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 9/4/2019 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 9/4/2019 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 9/24/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/4/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 10/7/2019 Conditional Approval TIM CHRISTENSEN
Piling/Pier/Caisson 10/9/2019 Approved DANNY TOLENTINO
BUILDING-Rough-Frame 11/1/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 11/1/2019 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 11/6/2019 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 11/12/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/9/2020 Partial Approval DANNY TOLENTINO
Deputy Steel/Welding 1/28/2020 No Access for Inspection DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval DANNY TOLENTINO
Sewer 2/28/2020 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 4/30/2020 Approved DANNY TOLENTINO
Underground Mechanical 5/5/2020 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 5/8/2020 Approved DANNY TOLENTINO
Sewer 5/8/2020 Partial Approval DANNY TOLENTINO
Underground Mechanical 5/8/2020 Partial Approval DANNY TOLENTINO
HVAC-Rough 5/20/2020 Approved DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Corrections Issued TIM CHRISTENSEN
Green Building Rough 5/27/2020 Not Ready for Inspection TIM CHRISTENSEN
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Approved TIM CHRISTENSEN
BUILDING-Rough-Frame 6/12/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 6/12/2020 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 6/12/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/18/2020 Approved JOHN KIDWELL
Green Building Rough 6/18/2020 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 6/18/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/23/2020 Partial Approval JOHN KIDWELL
Drywall Nailing 7/7/2020 Approved JOHN KIDWELL
Shower Pan 7/24/2020 Approved TIM CHRISTENSEN
Interior/Exterior Lathing 7/29/2020 Partial Approval ROBERT SHELLY
Interior/Exterior Lathing 8/6/2020 Approved KENNETH NAGLE
ELECTRICAL-Final 1/28/2021 Approved JOHN KIDWELL
HVAC-Final 2/16/2021 Approved JOHN KIDWELL
PLUMBING-Final 3/1/2021 Approved JOHN KIDWELL
Final 5/5/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 5/5/2021 Approved JOHNNY MIRANDA
Green Building Final 5/5/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 5/5/2021 Approved JOHNNY MIRANDA
Smoke Detectors 5/5/2021 Approved JOHNNY MIRANDA
Final 5/10/2021 OK to Issue CofO JOHN KIDWELL