3013 S VETERAN AVE 90034
Certificate Information: 3013 S VETERAN AVE 90034
- Application / Permit
- 18010-30000-01267
- Plan Check / Job No.
- B18WL01891
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229 AT REAR OF THE LOT PER WFPP.
- Permit Issued
- Issued on 11/7/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Corrected on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/15/2018 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 5/25/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/7/2018 | APPLICANT |
| Applicant returned to address corrections | 8/6/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/29/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 9/19/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 10/4/2018 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/6/2018 | JAHANSHAH POURHASSAN |
| Issued | 11/7/2018 | LADBS |
| Permit Closed-Status Void | 7/22/2019 | ROBERT SHELLY |
| Re-Activate Permit | 9/26/2019 | ROBERT SHELLY |
| CofO in Progress | 10/5/2020 | KENNETH NAGLE |
| CofO Issued-Status Void | 11/1/2020 | VINCENT COTTON |
| Permit Finaled-Status Void | 11/1/2020 | VINCENT COTTON |
| Re-Activate Permit | 7/1/2025 | DANIEL ORRANTE |
| CofO Corrected | 7/1/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/1/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2018 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 8/29/2018 | SERGIO VALENZUELA |
| Green Code | Cleared | 8/29/2018 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2018 | DENNIS BRAGIN |
| Sewer availability | Cleared | 9/19/2018 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 9/20/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/20/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/20/2018 | ADOLFO GUTIERREZ |
| Construction near power lines | Cleared | 10/25/2018 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 11/6/2018 | JAHANSHAH POURHASSAN |
Contact Information
| Architect | , ; Lic. No.: C23188 | 199 W. HILLCREST DR. THOUSAND OAKS, CA 91360 |
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/19/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 5/21/2019 | Conditional Approval | KEVIN BEAULIEU |
| Underground Mechanical | 6/7/2019 | Partial Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2019 | Not Ready for Inspection | ROBERT SHELLY |
| ELECTRICAL-Rough | 10/7/2019 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/7/2019 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2019 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/11/2019 | Partial Approval | KEVIN BEAULIEU |
| ELECTRICAL-Rough | 10/11/2019 | Approved | KEVIN BEAULIEU |
| Green Building Rough | 10/11/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| MERV13>=Rough | 10/11/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Verify Sprinkler Sign Off | 10/11/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 10/16/2019 | Conditional Approval | KEVIN BEAULIEU |
| Insulation | 10/21/2019 | Approved | KEVIN BEAULIEU |
| Drywall Nailing | 11/4/2019 | Approved | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 11/4/2019 | Approved | KEVIN BEAULIEU |
| ELECTRICAL-Rough | 1/16/2020 | Approved | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 1/16/2020 | Approved | KEVIN BEAULIEU |
| PLUMBING-Rough | 1/16/2020 | Approved | KEVIN BEAULIEU |
| Service/Power Release | 1/16/2020 | Approved | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 2/25/2020 | Approved | KEVIN BEAULIEU |
| Final | 2/25/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 2/25/2020 | Approved | KEVIN BEAULIEU |
| Green Building Final | 2/25/2020 | Approved | KEVIN BEAULIEU |
| Green Building Rough | 2/25/2020 | Approved | KEVIN BEAULIEU |
| MERV13>=Final | 2/25/2020 | Approved | KEVIN BEAULIEU |
| MERV13>=Rough | 2/25/2020 | Approved | KEVIN BEAULIEU |
| SGSOV-Seismic Gas S/O Valve | 2/25/2020 | SGSOV Not Ready | KEVIN BEAULIEU |
| Smoke Detectors | 2/25/2020 | Approved | KEVIN BEAULIEU |
| Verify Sprinkler Sign Off | 2/25/2020 | Approved | KEVIN BEAULIEU |
| Final | 3/10/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| SGSOV-Seismic Gas S/O Valve | 3/10/2020 | SGSOV Not Ready | KEVIN BEAULIEU |
| Final | 3/16/2020 | Conditional Approval | KEVIN BEAULIEU |
| SGSOV-Seismic Gas S/O Valve | 3/16/2020 | SGSOV Approved | KEVIN BEAULIEU |
| Final | 10/5/2020 | OK to Issue CofO | KENNETH NAGLE |