879 E COMMONWEALTH AVE 90291
Certificate Information: 879 E COMMONWEALTH AVE 90291
- Application / Permit
- 18010-30000-01225
- Plan Check / Job No.
- B18WL01830
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ROOF DECK.
- Permit Issued
- Issued on 9/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 1/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2018 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/9/2018 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 5/18/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/6/2018 | APPLICANT |
| Applicant returned to address corrections | 5/7/2019 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 5/10/2019 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 6/14/2019 | JAHANSHAH POURHASSAN |
| Issued | 9/20/2019 | LADBS |
| CofO in Progress | 11/15/2020 | DAVID HEINE |
| CofO Issued-Status Void | 12/31/2020 | RONALD MYRICK |
| Permit Finaled-Status Void | 12/31/2020 | RONALD MYRICK |
| Re-Activate Permit | 1/4/2021 | RONALD MYRICK |
| Permit Finaled | 1/11/2021 | RONALD MYRICK |
| CofO Corrected | 1/11/2021 | RONALD MYRICK |
| Permit Finaled | 1/11/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/14/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 2/8/2019 | MITESH PATEL |
| Green Code | Cleared | 3/28/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 5/23/2019 | JOSE CRUZ RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Assink, Aart; Lic. No.: C39390 | 1611 EL PRADO AVE TORRANCE, CA 90501 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/7/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 1/15/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 2/21/2020 | Partial Approval | DAVID HEINE |
| HVAC-Rough | 3/2/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 3/2/2020 | Approved | DAVID HEINE |
| Underground Mechanical | 3/2/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 3/5/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 3/5/2020 | Not Ready for Inspection | DAVID HEINE |
| ELECTRICAL-Rough | 3/6/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 3/6/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 3/9/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 3/11/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 3/24/2020 | Approved | DAVID HEINE |
| Green Building Rough | 3/24/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 3/24/2020 | Partial Approval | DAVID HEINE |
| Verify Sprinkler Sign Off | 3/24/2020 | Approved | DAVID HEINE |
| Insulation | 4/21/2020 | Approved | DAVID HEINE |
| Shower Pan | 4/21/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 4/23/2020 | Partial Approval | DAVID HEINE |
| Drywall Nailing | 5/5/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 5/5/2020 | Partial Approval | DAVID HEINE |
| Interior/Exterior Lathing | 5/20/2020 | Approved | DAVID HEINE |
| Gas Test | 9/1/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 9/22/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Final | 9/22/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 9/25/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 9/25/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 9/29/2020 | Approved | DAVID HEINE |
| Final | 11/6/2020 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 11/6/2020 | Approved | DAVID HEINE |
| Green Building Final | 11/6/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV Approved | DAVID HEINE |
| Service/Power Release | 11/6/2020 | Not Ready for Inspection | DAVID HEINE |
| Smoke Detectors | 11/6/2020 | Approved | DAVID HEINE |
| Final | 11/13/2020 | OK to Issue CofO | DAVID HEINE |
| Service/Power Release | 11/13/2020 | Approved | DAVID HEINE |