1622 S SHERBOURNE DR 90035

Certificate Information: 1622 S SHERBOURNE DR 90035

Application / Permit
18010-30000-01189
Plan Check / Job No.
B18WL01772
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY 24'-10" x 38'-0" ADU AT REAR OF THE LOT.
Permit Issued
Issued on 11/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2018 APPLICANT
Assigned to Plan Check Engineer 4/19/2018 JAHANSHAH POURHASSAN
Corrections Issued 5/2/2018 JAHANSHAH POURHASSAN
Building Plans Picked Up 5/4/2018 APPLICANT
Green Plans Picked Up 5/4/2018 APPLICANT
Quality Review Completed 5/11/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/21/2018 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/20/2019 JAHANSHAH POURHASSAN
Plan Check Approved 7/11/2019 JAHANSHAH POURHASSAN
Issued 11/4/2019 LADBS
CofO in Progress 2/14/2023 DAVID FEILER
Permit Finaled 2/14/2023 DANIEL ORRANTE
CofO Issued 2/14/2023 DANIEL ORRANTE
Permit Finaled 2/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/27/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/6/2018 CARLA VALLADARES
Sewer availability Cleared 7/6/2018 CARLA VALLADARES
Low Impact Development Cleared 7/30/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/30/2018 MICHAEL CASTILLO
Green Code Cleared 7/2/2019 RICHARD GARCIA
Hydrant and Access approval Cleared 7/2/2019 GILBERT URREA
Construction near power lines Cleared 7/6/2019 RIDWAN HARDY

Contact Information

Contractor Pacific Save Inc; Lic. No.: 988151-B 18357 VENTURA BLVD UNIT 163      TARZANA, CA 91356
Engineer Adefeso, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302
Engineer Zhong, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 3/6/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 4/14/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/14/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 4/14/2020 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 4/14/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 5/6/2020 Corrections Issued EVAN COOPER
Special/Order Compliance 5/12/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/17/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 10/21/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 10/21/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 10/21/2020 Approved EVAN COOPER
ELECTRICAL-Rough 10/22/2020 Approved EVAN COOPER
HVAC-Final 10/22/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 10/28/2020 Approved EVAN COOPER
HVAC-Rough 10/28/2020 Corrections Issued EVAN COOPER
Final 11/2/2020 Corrections Issued EVAN COOPER
HVAC-Final 11/2/2020 Corrections Issued EVAN COOPER
HVAC-Rough 11/4/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 11/6/2020 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 12/10/2020 Approved EVAN COOPER
Green Building Rough 12/10/2020 Approved EVAN COOPER
HVAC-Rough 12/10/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 12/10/2020 Approved EVAN COOPER
Insulation 12/16/2020 Approved EVAN COOPER
Drywall Nailing 12/22/2020 Approved EVAN COOPER
Interior/Exterior Lathing 12/29/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/9/2021 Approved EVAN COOPER
Service/Power Release 2/9/2021 Corrections Issued EVAN COOPER
Final 6/23/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 6/23/2021 Approved EVAN COOPER
Green Building Final 6/23/2021 Not Ready for Inspection EVAN COOPER
METHANE-Barrier 6/23/2021 Approved EVAN COOPER
METHANE-Subgrade 6/23/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Not Ready EVAN COOPER
Service/Power Release 6/23/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 6/23/2021 Approved EVAN COOPER
Final 1/26/2022 Not Ready for Inspection EVAN COOPER
Green Building Final 1/26/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 1/26/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Not Ready EVAN COOPER
Final 6/16/2022 Corrections Issued EVAN COOPER
Green Building Final 6/16/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 6/16/2022 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 6/16/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 6/29/2022 Approved EVAN COOPER
Final 6/29/2022 Corrections Issued EVAN COOPER
Green Building Final 6/29/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Approved EVAN COOPER
Service/Power Release 6/29/2022 Approved EVAN COOPER
Final 12/13/2022 No Access for Inspection OGANES TARAKHCHYAN
Final 12/21/2022 Corrections Issued OGANES TARAKHCHYAN
Final 2/14/2023 OK to Issue CofO DAVID FEILER